Kellogg Bridge Co v. Hamilton

Decision Date14 January 1884
Citation110 U.S. 108,28 L.Ed. 86,3 S.Ct. 537
PartiesKELLOGG BRIDGE CO. v. HAMILTON
CourtU.S. Supreme Court

The Kellogg Bridge Company, which brings this writ of error and was defendant below, undertook to construct, for the Lake Shore & Michigan Southern Railroad Company, an iron bridge across Maumee river, at Toledo, Ohio. After doing a portion of the work it entered into a written contract with Hamilton, the defendant in error, for the completion of the bridge under its directions. That contract is the basis of this action and contains, among others, these stipulations:

'That the said party of the first part [Hamilton] hereby agrees to furnish and prepare all the necessary false work and erect the iron bridge now being constructed by the said party of the second part [the Kellogg Bridge Company] for the Lake Shore and Michigan Southern R. R. Co., at Toledo, Ohio, over the Maumee river, receiving said bridge material as it arrives on the cars at the site of said bridge and erecting the same in the best manner, according to the design of said bridge and the directions of said second party, from time to time, commencing the erection of said work when required to do so by said second party, and proceed- ing with the same with a force sufficient to complete the entire work on or before the first day of March next; the said first party also agrees to assume and pay for all work done and materials furnished up to the time of executing this contract, including piling and piles, timber, and other materials and labor done on the same, but not including bolts and washers which have been furnished by the party of the second part, but to return said bolts and washers to the said second party, or pay for the same on completion of said bridge. And the said first party in consideration of the payments hereinafter mentioned, to be made by said second party, agrees to perform all the stipulations of this agreement in a through and workmanlike manner and to the satisfaction of the second party. And if at any time the said second party is not satisfied with the manner of performing the work herein described, or the rapidity with which it is being done, the second party shall have full power and liberty to put on such force as may be necessary to complete the work within the time named, and provide such tools or materials for false work as may be necessary, and charge the cost of the same to the said first party, who agrees to pay therefor.'

In consideration of the faithful performance of these stipulations, Hamilton was to receive from the Bridge Company $900 on the completion of the first span, a like sum on the completion of the second span, $800 on the completion of the third span, and $1,403 on the completion of the draw and the entire work—such payments to be made only on the acceptance of each part of the work by the chief engineer of the Lake Shore & Michigan Southern Railroad Company.

The bridge which Hamilton undertook to erect consisted of three independent fixed spans, each to be 175 feet 6 inches in length, suspended between and resting at each end of the span upon stone piers, which had been prepared to receive the same, and one draw span of 185 feet in length, resting upon a pier in the center, also then prepared. In erecting the several spans it was necessary to build and use what the contract describes as 'false work,' which consisted of piles driven in the river be- tween the piers upon which the spans were to rest, and upon which was placed a platform.

As indicated in the written contract, the bridge company had previously constructed a part of this false work between the first and second spans, the cost of which Hamilton paid, as by the contract he agreed to do. Assuming this work to be sufficient for the purposes for which it was designed, Hamilton proceeded to complete the erection of the bridge according to the plans furnished him.

There was evidence before the jury tending to establish the following facts: A part of the false work or scaffolding put up by the company sank under the weight of the first span, and was replaced by Hamilton. When the second fixed span was about two-thirds completed, the ice, which before that had formed in the river, broke up in consequence of a flood, carrying away the false work under that span, and causing the whole of the iron material then in place on the span, or on the span ready to be put in place, to fall in the river, which at that place was about 16 feet deep. If the piles driven by the bridge company had been driven more firmly into the bed of the river, they would have withstood the force of the ice and flood. In consequence of the insufficiency of the false work done by that company, Hamilton was delayed in the completion of the bridge and subjected to increased expense.

In this action his claim is that the company is liable, not only for the amount specified in the contract, but also for such damages as he sustained by reason of the insufficiency of the false work it constructed. Charging defendant with these amounts, and crediting it with such sums as had been paid to or for Hamilton, a balance of $3,693.78 was claimed to be due the latter. Defendant, by way of counter-claim, asked judgment against Hamilton for $6,619.70. There was a verdict and judgment in favor of plaintiff for $3,039.89.

Richard Waite and E. T. Waite, for plaintiff in error.

J. C. Lee, for defendant in error.

HARLAN, J.

It is insisted by the defendant in error that the value of the matter really in dispute here is less than the amount requisite to give this court jurisdiction. Upon this ground a motion to dismiss was heretofore made, and was denied. To that ruling we adhere. Upon the pleadings it is apparent that the defendant asserts its right to judgment for $6,619.70 after crediting plaintiff, not only with the sum specified in the contract, but with every other sum to which he is entitled in the accounting. This is conclusive as to our jurisdiction upon this writ of error.

It was not claimed on the trial, nor is it contended here, that the company made any statement or representation as to the nature or character of the false work it did, and which, by the contract, Hamilton agreed to assume and pay for. But there was evidence tending to show that the insufficiency of that false work was unknown to Hamilton at the time the contract was made; was not apparent upon any examination he then or could have made; and was not discovered, indeed, could not have been discovered, until, during the progress of the erection of the bridge, the false work was practically tested.

The court, among other things, instructed the jury, at the request of plaintiff, and ov r the objections of the defendant, that by the contract—looking at all the circumstances attending its execution and giving to its terms a fair and reasonable interpretation—there was an implied warranty upon the part of the company that the false work it did, and which plaintiff agreed to assume and pay for, was suitable and proper for the purposes for which the bridge company knew it was to be used. This instruction was accompanied by the observation that if the evidence showed 'that the particular work which was said to be defective was such that the plaintiff could not by examination ascertain its defects for if they were apparent by mere examination of the false work it was the duty of the plaintiff to make that good—he had the right to rely upon the implied warranty; that is, if the defects were such that they could not be, by ordinary observation and care on behalf of the plaintiff, ascertained and found out.' That instruction presents the only question we deem necessary to determine. Although there are several assignments of error, they depend, as counsel for plaintiff in error properly concede, upon the inquiry whether the court erred in ruling that by the terms of the contract there was an implied warranty that the false work constructed by the bridge company was suitable and proper for the purposes for which it was to be used by Hamilton.

The argument in behalf of plaintiff in error proceeds upon the ground that there was a simple transfer by the company of its ownership of the work and materials as they existed at the time of the contract; that Hamilton took the false work for what it was, and just as it stood; consequently, that the rule of caveat emptor applies with full force. The position of counsel for Hamilton is that, as in cases of sales of articles by those manufacturing or making them, there was an implied warranty by the bridge company that the work sold or transferred to Hamilton was reasonably fit for the purposes for which it was purchased. The cases in which the general rule of caveat emptor applies are indicated in Barnard v. Kellogg, 10 Wall. 388, where, speaking by Mr. Justice DAVIS, the court observed that 'no principal of the common law has been better established, or more often affirmed, both in this country and in England, than that in sales of personal property, in the absence of express warranty, where the buyer has an...

To continue reading

Request your trial
174 cases
  • Zesch v. Abrasive Co. of Philadelphia
    • United States
    • Missouri Supreme Court
    • March 11, 1946
    ... ... v. Strait ... Scale Co., 322 Mo. 502, 15 S.W.2d 766, 64 A.L.R. 936; ... Kellogg Bridge Co. v. Hamilton, 110 U.S. 108, 3 ... S.Ct. 537, 28 L.Ed. 86. (9) The defendant's ... ...
  • London Guar. & Acc. Co., Ltd., of London, England v. Strait Scale Co.
    • United States
    • Missouri Supreme Court
    • March 29, 1929
    ...For a summarization of them, as applicable to the facts of this case, we quote the language of the Supreme Court in Kellogg Bridge Co. v. Hamilton, 110 U.S. 108, 116: "When the seller is the maker or manufacturer of thing sold, the fair presumption is that he understood the process of its m......
  • Kennedy v. Bowling
    • United States
    • Missouri Supreme Court
    • March 17, 1928
    ... ... v. Clark, 58 Mo. 145; Railroad Co. v. Smith, 21 ... Wall. (88 U.S.) 255; Kellogg Bridge Co. v. Hamilton, ... 110 U.S. 108; Boiler Works Co. v. Sievert, 256 S.W ... 555; ... ...
  • Kennedy v. Bowling
    • United States
    • Missouri Supreme Court
    • March 17, 1928
    ...Pump Co. v. Sprinkler Co., 84 Mo. App. 204; Smith v. Clark, 58 Mo. 145; Railroad Co. v. Smith, 21 Wall. (88 U.S.) 255; Kellogg Bridge Co. v. Hamilton, 110 U.S. 108; Boiler Works Co. v. Sievert, 256 S.W. 555; Title Guarantee Co. v. Pam, 155 N.Y. Supp. 333; O'Neil Engineering Co. v. City of S......
  • Request a trial to view additional results
1 books & journal articles
  • The Construction Industry in the U.S. Supreme Court: Part 1, Contract Law
    • United States
    • ABA General Library The Construction Lawyer No. 41-2, April 2021
    • April 1, 2021
    ...note 13, at 125–26. 20. 109 U.S. 200 (1883). 21. Id. at 203. 22. Id. at 203–04. 23. Id. at 204–05. 24. Kellogg Bridge Co. v. Hamilton, 110 U.S. 108, 119 (1884). 25. D.C. v. Clephane, 110 U.S. 212 (1884). 26. See generally RESTATEMENT (SECOND) OF CONTRACTS § 347 (AM. LAW INST. 1981); 6 PHILI......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT