Johnson v. City of Boston

Decision Date25 June 1875
Citation118 Mass. 114
PartiesRobert Johnson v. City of Boston
CourtUnited States State Supreme Judicial Court of Massachusetts Supreme Court

Suffolk. Tort for personal injuries.

At the trial in this court, before Endicott, J., the plaintiff offered to prove that he was in the employment of one Tinkham, who employed a large number of men, and whose business was drilling and blasting rock, and doing work of a like nature for all parties who chose to employ him; that he sent his workmen from place to place where he had work for them to do; that Tinkham sent the plaintiff, and eight other workmen in his employ, to drill and blast rock in the bottom of a sewer which the defendant, by its servants and agents was engaged in constructing in Warren Street, in Boston under an order of the board of aldermen of the city directing the superintendent of sewers to construct a common sewer in the said street and to report a schedule of the expense thereof to the board pursuant to law; that among the workmen sent by Tinkham was one Harrigan, who worked with the others and directed them where and how the drilling was to be done, and superintended the blasting; that he was not called or styled a foreman, and he received only the same pay as the others; that the duty of these nine men sent by Tinkham was to drill and blast the rock to deepen the sewer, in such places as might be pointed out to them by the foreman of the sewer department of the city in charge of the whole work; that they were to work in groups of three in drilling and blasting, and understood and were competent to do the work; that after it was blasted the rock was removed by men employed and paid by the defendant corporation; that the sewer was in process of construction between two street railway tracks laid in Warren Street, and the bottom of it was to be ten feet below the grade of the street; that the work of digging and removing the earth, clay and loose material, of bracing and protecting the sides of the sewer, and of laying and covering the sewer, was done by workmen and laborers employed and paid by the defendant corporation; that the whole work, including the drilling and blasting, was prosecuted under the general supervision of the defendant's superintendent of sewers, and under the direct charge and management of a foreman of the sewer department, employed and paid by the defendant corporation; that Tinkham furnished the plaintiff and his associates to do the drilling and blasting; and the defendant corporation paid Tinkham the sum of $ 2.45 per day for each of his men for the time they were actually employed, and Tinkham paid his men $ 2.25 a day each, gave them orders where to go and what to do, and retained control of them so far that he could change them from one place of work to another and could dismiss them; that at the point where the plaintiff was injured, the sewer had been dug nine feet below the grade of the street, and the clay and loose material had been removed by the men employed and paid by the defendant corporation; that it became necessary to blast and remove about one foot deep of rock-material in order to make the sewer of the required depth; that while engaged in drilling this rock, the sides or walls of the sewer above him caved or fell in, and the earth and loose material therefrom fell upon him, and he was injured.

The plaintiff also offered to prove that by reason of the negligence of those employed by the city the sides or walls of the sewer at that point were not braced in any manner, and that had they been properly braced they would not have caved or fallen in, and the earth would not have fallen upon the plaintiff and injured him; that it was not the duty or even the right of the plaintiff or any of the men in the...

To continue reading

Request your trial
52 cases
  • Sargent Paint Co. v. Petrovitzky
    • United States
    • Indiana Appellate Court
    • November 20, 1919
    ...190 Ill. 145, 60 N. E. 87;Grace & H. Co. v. Probst, 208 Ill. 147, 70 N. E. 12;Kimball v. Cushman, 103 Mass. 194, 4 Am. Rep. 528;Johnson v. Boston, 118 Mass. 114;Delory v. Blodgett, 185 Mass. 126, 69 N. E. 1078, 64 L. R. A. 114, 102 Am. St. Rep. 328; The Elton, 73 C. C. A. 467, 142 Fed. 367.......
  • Brady v. Chicago & G.W. Ry. Co.
    • United States
    • U.S. Court of Appeals — Eighth Circuit
    • March 3, 1902
    ... ... customary duties of such crews at the city of St. Paul. In ... the early morning of November 1, 1896, while it was yet dark, ... it became ... and under his direction; as in Johnson v. City of ... Boston, 118 Mass. 114, where he rents them to a city to ... work with its ... ...
  • The Chicago & Nw. Ry. Co. v. Bliss
    • United States
    • United States Appellate Court of Illinois
    • June 30, 1880
    ...Cal. 129; Hurd v. Vt. & Can. R. R. Co. 32 Vt. 480; Valtez v. O. M. R'y Co. 85 Ill. 500; Colten v. Richards, 123 Mass. 486; Johnson v. City of Boston, 118 Mass. 114. The verdict was the result of chance and should have been set aside: Ill. Cent, R. R. Co. v. Able, 59 Ill. 131; City of Pekin ......
  • Berry v. New York Cent. & H.R.r. Co.
    • United States
    • United States State Supreme Judicial Court of Massachusetts Supreme Court
    • May 21, 1909
    ... ... 5; Hasty v. Sears, 157 Mass. 123, 125, 31 N.E ... 759, 34 Am. St. Rep. 267; Kelly v. Johnson, 128 ... Mass. 530, 531, 35 Am. Rep. 398; Johnson v. Boston, ... 118 Mass. 114, 117; Zeigler v ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT