United States v. Rohleder, 9093

Citation157 F.2d 126
Decision Date15 August 1946
Docket NumberNo. 9093,9123.,9093
PartiesUNITED STATES v. ROHLEDER, et al. (two cases).
CourtUnited States Courts of Appeals. United States Court of Appeals (3rd Circuit)

J. Gregory Bruce, of Washington, D. C., (John F. Sonnett, Asst. Atty. Gen., and Gerald A. Gleeson, U. S. Atty., and Thomas J. Curtin, Asst. U. S. Atty., both of Philadelphia, Pa., and Joseph M. Friedman, Chief, War Frauds Civil Section, of Washington, D. C., on the brief), for the United States.

James F. Masterson, of Philadelphia, Pa., (G. Fred Di Bona, of Philadelphia, Pa., on the brief), for defendants.

Before MARIS, GOODRICH and McLAUGHLIN, Circuit Judges.

McLAUGHLIN, Circuit Judge.

This is a civil suit brought by the United States under Sections 3490-3492 inclusive, and Section 5438 of the Revised Statutes, 31 U.S.C.A. §§ 231-233, 18 U.S.C.A. §§ 80, 82-86, to recover the forfeitures and double damages provided by Section 3490 for submitting false claims for materials supplied as a subcontractor on a Navy shipbuilding project.1 The government offered no evidence of actual damage at the trial and sought only to recover the statutory forfeitures. The case was tried without a jury. The District Judge found that the defendants had violated Section 3490 as to the sixteen contracts involved. He assessed the statutory penalty of $2,000 against the defendants on each of the contracts. From the judgment entered therein the defendants appeal. The government, claiming that each of the ninety purchase orders in the matter called for a separate forfeiture, cross appeals on that point.

The defendant, Charles F. Rohleder, is a building contractor in Philadelphia; the other defendants were employed by him as his agents and carried on with him the activities described below. Rohleder entered into subcontracts with the Cramp Shipbuilding Company, which was under contract with the Navy Department. This main contract between Cramp and the Navy, dated October 29, 1940 (designated NOD 1550), obligated Cramp to improve its shipyards in Philadelphia by the erection of "Emergency Plant Facilities" preparatory to the building of six light cruisers. The provisions of the contract were that the Cramp Company would, without profit to it, by itself or through contracts with others, make improvements of the value of about $12,000,000. Records and accounts of the project were to be kept by Cramp, and capital for carrying it on was obtained by arrangement with a number of banks. The Navy, represented by the Supervisor of Shipbuilding at the Cramp plant, had broad rights of inspection of work and records during and after construction. The Supervisor's approval was required in advance for all plans, prices, subcontractors and subcontracts involved. At the completion of the work, a Final Cost Certificate would be presented by Cramp to the Navy, which would then reimburse the company from government funds at 1/60 per month.

On the same date as the main contract, Cramp entered into the first of sixteen subcontracts with Rohleder, eight of which are classed as principal and eight as extension of work projects. The ensuing fifteen were concluded at various times up to September 8, 1941, the date of the last one. These subcontracts were for the actual construction, required by NOD 1550, by Rohleder. They were on a cost-plus-fixed-fee basis, the estimated cost being $1,935,179 and the fixed fee being $63,003. All but two of the subcontracts expressly stated that the work involved was let under and was subject to NOD 1550. All but one of the subcontracts required purchases of $100 or over should be approved by Cramp before being placed.2 All of the subcontracts were approved about the time of execution by the Navy representative.

Before the execution of any of these subcontracts, an authorized Navy representative orally informed some of the Cramp officials that, in order to obtain the approval for purchase of material, there would have to be furnished to him in advance, three or more bids together with the vendor's name and the price submitted by him. This requirement was reduced to memorandum form. The District Court found that the defendants were aware of this requirement and purported to comply with it in connection with purchase orders submitted in their contract work.

The vast majority of such orders submitted by defendants are not questioned. But ninety of them were found by the District Court to contain "three or more bids, one or more of which bids the defendants knew or had cause to know were false, fictitious, and not bona fide competitive bids." The practice as to these of Rohleder, the other defendants, or their subordinates, was to obtain from dealers bids higher than the one it was desired to have accepted, with the understanding that these bids were not seriously made on the part of the dealers. The ninety items so treated were included in work under all sixteen of the contracts. The bids involved were forwarded by Rohleder to the Cramp Company and approved without suspicion by it. They were sent to the Navy representative who upon inspection and in reliance on the facts presented gave the final approval, also without suspicion. Rohleder was then provided with copies of the correspondence between Cramp and the Navy, indicating the approved bid. This method was followed for each of the ninety items, and for each of them Rohleder was reimbursed by Cramp. In some instances, the material upon which the bids were given had been installed by Rohleder before the approval procedure got under way. The prices thus obtained were reflected in the Final Cost Certificate submitted by Cramp and paid by the United States through the Navy Department under the terms of NOD 1550.

The Court below also found that "No evidence of any damage suffered by the United States as a result of the alleged illegal acts was offered," and that there "is no evidence * * * that the government would have saved any money had genuine * * * bids * * * been submitted." It appears in the record that the defendants were acquitted of the related criminal action in 1943.

The defendants contend that there can be no recovery under Section 3490 unless actual damages, pecuniary or proprietary, are alleged and proved. They argued that as Section 5438 stood at the time it was incorporated into Section 3490, it required pecuniary loss in order that a conviction be sustained. The question is not wholly free from doubt. It is somewhat complicated by the circumstances that Section 5438 was amended in 1918 among other particulars not presently important by inclusion of the phrase "or for the purpose and with the intent of cheating or swindling or defrauding the Government of the United States." United States v. Cohn, 270 U.S. 339, 46 S.Ct. 251, 70 L.Ed. 616, was decided under the 1918 amendment and the Supreme Court specially stressing the above amendment language held that actual loss to the government was necessary to sustain a conviction. Capone v. United States, 7 Cir., 51 F.2d 609, and United States ex rel. Starr v. Mulligan, 2 Cir., 59 F.2d 200, are much to the same effect.

Section 5438 was further amended in 1934. The important changes for our purposes were, the dropping of the above quoted part of the 1918 amendment and the addition of the clause "in any matter within the jurisdiction of any department or agency of the United States * * *." That last amendment was considered by the Second Circuit in United States v. Mellon, 96 F.2d 462, on the contention that there could be no violation of the statute without pecuniary loss to the government. The Court said 96 F.2d at page 463: "Before the amendment of 1934 the scope of the statute was, indeed, so limited. United States v. Cohn, 270 U.S. 339, 46 S.Ct. 251, 70 L.Ed. 616; United States ex rel. Starr v. Mulligan, 2 Cir., 59 F.2d 200." It is particularly noted that the Court is there referring to Section 5438 with the 1918 "defrauding" phrase relied on in the Cohn opinion and not to the original Section 5438 as it was incorporated into Section 3490. Love v. Mantz, 8 Cir., 72 F.2d 631, does not answer the question either, as the Court there applied the rule of the above cases under the 1918 amendment to indicate that pecuniary loss was a vital element of the claim.

Closest to the present situation is United States ex rel. Marcus v. Hess, 317 U.S. 537, 63 S.Ct. 379, 87 L.Ed. 443, rehearing denied 318 U.S. 799, 63 S.Ct. 756, 87 L.Ed. 1163. That was a civil suit by an informer under Sections 3490-3494, 31 U.S. C.A. §§ 231-235. The District Judge correctly held that it must rest on violations of Section 5438 as that section read when it was incorporated in Section 3490. United States v. Hess, D.C.W.D.Pa., 41 F.Supp. 197, 205. This is conceded by both sides in this appeal. In the Hess case, just as here, the government asked for forfeitures on items, among others, for which no damage was shown. The District Judge said as to this, 41 F.Supp. at page 218: "The next reason urged by defendants for a new trial is that the court erred in refusal of defendants' 9th point, which reads as follows: `9. There can be no recovery of any penalty or forfeiture on account of any project in which no actual damages have been shown.' Section 3490, R.S., expressly provides for a penalty of $2,000, `and, in addition, double the amount of damages which the United States may have sustained.' This makes it plain that regardless of damages sustained, the United States would still be entitled to recover the penalty. This point refers to instances where the United States withheld payments on account of the discovery of the fraud, so that no actual damage was shown. However, that would not preclude the United States from recovery of the penalty prescribed by Section 3490, R.S."

The judgment of the District Court including the forfeitures allowed for eight projects as to...

To continue reading

Request your trial
48 cases
  • US v. Kensington Hosp.
    • United States
    • U.S. District Court — Eastern District of Pennsylvania
    • March 13, 1991
    ...219, 100 L.Ed. 149 (1956); United States ex rel. Marcus v. Hess, 317 U.S. 537, 63 S.Ct. 379, 87 L.Ed. 443 (1943); United States v. Rohleder, 157 F.2d 126 (3d Cir.1946).3 In Marcus, electrical contractors submitted fraudulent bills to the government for work on numerous projects. In some ins......
  • United States v. Winchester
    • United States
    • U.S. District Court — District of Delaware
    • December 24, 1975
    ...(3d Cir. 1959) (claim grounded in fraud where fraudulent misrepresentation induced government to assume obligation); United States v. Rohleder, 157 F.2d 126 (3d Cir. 1946) (recovery of civil penalties under sections 3490, 5438 on contracts obtained through collusive bidding Moreover, the ca......
  • Gulf Grp. Gen. Enters. Co. v. United States
    • United States
    • U.S. Claims Court
    • July 2, 2013
    ...rel. Marcus v. Hess, 41 F. Supp. 197, 218. The judgment of the District Court [in Marcus] was affirmed here. See United States v. Rohleder, 157 F.2d 126, 129 [(3d Cir. 1946)]."). The anti-fraud provision of the Contract Disputes Act, 41 U.S.C. § 604 (now 41 U.S.C. § 7103(c)(2)) provides:If ......
  • U.S. ex rel. Thompson v. Columbia/Hca Healthcare
    • United States
    • U.S. District Court — Southern District of Texas
    • August 18, 1998
    ...198 (D.C.Cir. 1995); United States ex rel. Hagood v. Sonoma Co. Water Agency, 929 F.2d 1416, 1421 (9th Cir.,1991); United States v. Rohleder, 157 F.2d 126 (3d Cir.1946) (relied on by Fifth Circuit in Ridglea State Bank and holding that FCA claimant need not show that government would have s......
  • Request a trial to view additional results
1 books & journal articles
  • CHAPTER 9 LITIGATION UNDER THE FEDERAL FALSE CLAIMS ACT
    • United States
    • FNREL - Special Institute Federal and Indian Oil and Gas Royalty Valuation and Management (FNREL) 1998
    • Invalid date
    ...cert. denied, 353 U.S. 930 (1957); Murray & Sorenson, Inc. v. United States, 207 F.2d 119 (1st Cir. 1953); United States v. Rohleder, 157 F.2d 126 (3d Cir. 1946); United States v. DiBona, 614 F. Supp. 40, 44 (E.D. Pa. 1984); United States v. Aerodex, Inc., 327 F. Supp. 1027 (S.D. Fla. 1970)......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT