Dyno Constr. v. McWane, Inc.

Citation198 F.3d 567
Decision Date22 September 1999
Docket NumberNo. 98-4050,98-4050
Parties(6th Cir. 1999) Dyno Construction Company, Plaintiff-Appellant, v. McWane, Inc., Defendant-Appellee. Argued:
CourtUnited States Courts of Appeals. United States Court of Appeals (6th Circuit)

Appeal from the United States District Court for the Northern District of Ohio at Toledo, No. 97-07151--John W. Potter, District Judge. [Copyrighted Material Omitted] Thomas P. Whelley II, Scott L. Braum, Jack Kurt Denkewalter, CHERNESKY, HEYMAN & KRESS, Dayton, Ohio, for Appellant.

Joan C. Szuberla, Byron S. Choka, SPENGLER NATHANSON, Toledo, Ohio, for Appellee.

Before: NELSON and SILER, Circuit Judges; QUIST, District Judge. *

OPINION

GORDON J. QUIST, District Judge.

Plaintiff, Dyno Construction Company, sued Defendant, McWane, Inc., alleging various breach of contract claims arising out of Dyno's purchase of ductile iron pipe from McWane that was later found to be defective. The district court denied the parties' cross-motions for summary judgment, and a jury returned a general verdict in favor of McWane. The district court denied Dyno's motion for a new trial. Dyno appeals the order denying its motion for summary judgment, the judgment entered after trial, and the order denying Dyno's motion for a new trial. We find no error and affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

Dyno is a company engaged in the business of constructing underground utility projects, specifically underground water and sewer lines. Dyno was purchased in the fall of 1995 by Frederick Harrah, Laymond Lewis, and a third party. Prior to purchasing Dyno, Harrah and Lewis were employees of Reynolds, Inc., a large underground pipeline construction company also in the business of installing underground water and sewer lines.

McWane is a manufacturer and seller of ductile iron pipe and fittings for underground utility projects. Harrah and Lewis frequently purchased pipe from McWane during their employment with Reynolds, as McWane was the exclusive supplier of certain types of ductile iron products to Reynolds.

Sometime shortly before November 6, 1995, Dyno submitted a bid to the City of Perrysburg, Ohio, for a multimillion dollar water and sewer system project. In order to prepare the bid, Lewis contacted various suppliers, including McWane, to obtain quotes for necessary materials. On November 6, 1995, Dyno learned that it was the low bidder on the project and would be awarded the contract.

On November 8, 1995, McWane's district sales manager, Kevin Ratcliffe, faxed Dyno a document containing quantities and prices for the materials Dyno requested for the Perrysburg Project.1 Ratcliffe sent a second fax to Lewis on November 13, 1995, which included handwritten prices and notes next to each item. On the fax cover sheet, Ratcliffe asked Lewis to "[p]lease call."

On or prior to November 22, 1995, Lewis phoned Ratcliffe and told him to order the materials. Lewis testified at his deposition that he thought that there was a "done deal" when he got off the phone with Ratcliffe. However, after the phone call, Ratcliffe prepared and sent a package to Lewis via Federal Express. The Federal Express package included a purchase order, a credit application, and a cover letter in which Ratcliffe asked Lewis to review and sign the purchase order and credit application and return the originals to Ratcliffe. The purchase order and credit application each stated that the sale of the materials was subject to the terms and conditions printed on the reverse sides of those documents. The reverse side of each document contained additional terms and conditions, including a provision which limited McWane's liability for defective materials. The Federal Express invoice kept in McWane's files showed that Dyno received the package on November 24, 1995, at 8:53 a.m.

Lewis called Ratcliffe on December 1, 1995, to inquire about the status of Dyno's order. Lewis testified that Ratcliffe told him that "you have to sign our forms." Lewis indicated both in his deposition and at trial that he was not surprised when Ratcliffe told him that the purchase order and credit application would have to be signed before McWane would ship the materials. Lewis told Ratcliffe that he had not received the forms Ratcliffe sent via Federal Express and could not find the package in his office. At Lewis' request, in order to expedite the transaction, Ratcliffe faxed Lewis copies of the documents that were sent on November 22, 1995. However, Ratcliffe did not fax the back sides of the documents which included, among other things, this provision limiting McWane's liability:

SELLER SHALL NOT BE LIABLE FOR EXEMPLARY, PUNITIVE, SPECIAL, INCIDENTAL, CONSEQUENTIAL DAMAGES OR EXPENSES, INCLUDING BUT NOT LIMITED TO, LOSS PROFIT REVENUES, LOSS OF USE OF THE GOODS, OR ANY ASSOCIATED GOODS OR EQUIPMENT, DAMAGE TO PROPERTY OF BUYER, COST OF CAPITAL, COST OF SUBSTITUTE GOODS, DOWNTIME, LIQUIDATED DAMAGES, OR THE CLAIMS OF BUYER'S CUSTOMERS FOR ANY OF THE AFORESAID DAMAGES, OR FROM ANY OTHER CAUSE RELATING THERETO, AND SELLER'S LIABILITY HEREUNDER IN ANY CASE IS EXPRESSLY LIMITED TO THE REPLACEMENT (IN THE FORM ORIGINALLY SHIPPED) OF GOODS NOT COMPLYING WITH THIS AGREEMENT, OR, AT SELLER'S ELECTION, TO THE REPAYMENT OF, OR CREDITING BUYER WITH, AN AMOUNT EQUAL TO THE PURCHASE PRICE OF SUCH GOODS PRIOR PAID TO AND RECEIVED

BY SELLER, WHETHER SUCH CLAIMS ARE FOR BREACH OF WARRANTY OR NEGLIGENCE . . . .

Dyno signed the faxed pages without the quoted damages limitation provision and returned them to Ratcliffe later that day.

Dyno had substantial problems with the pipes it purchased from McWane. Although McWane repaired and reinstalled the pipe to the satisfaction of Dyno, it refused to pay Dyno for consequential damages suffered as a result of the defects in the pipes on the basis of the limitation of damages provision on the back of the purchase order. Dyno filed this suit in an attempt to recover its consequential damages.

Both parties moved for summary judgment with respect to the question of whether the quoted provision limiting McWane's liability for consequential damages was a part of the Dyno/McWane contract.2 In denying the motions, the district court rejected Dyno's contention that the two written quotations which Ratcliffe sent to Lewis were offers that Dyno accepted when Lewis informed Ratcliffe that Dyno wished to purchase the pipe from McWane because the quotations were part of preliminary negotiations between the parties. Instead, the court concluded that the contract was formed or, alternatively, modified, when Lewis signed the documents he received from Ratcliffe by fax on December 1, 1995. The district court also rejected as a matter of law McWane's arguments that Dyno's acceptance of documents containing the warranty limitation provision established a course of performance and that a course of dealing was established by Lewis' dealings with McWane while Lewis was employed at Reynolds. Instead, the district court found that McWane's argument that Lewis had knowledge of the disputed provision based upon his receipt of the Federal Express package presented a genuine issue of material fact. Thus, the district court framed the issue for the jury with respect to the limitation of damages provision as whether Lewis knew or should have known about McWane's terms and conditions at the time he signed the fax copy.

At trial, during the conference on jury instructions, the district court rejected Dyno's proposed instruction number 7, which would have allowed the jury to find that the contract had been formed on or before November 22, 1995, on the basis of its ruling with respect to the summary judgment motions that the contract was formed on December 1, 1995.3 At the conclusion of trial, the jury returned a verdict in favor of McWane.

II. ANALYSIS
A.Summary Judgment

Dyno first contends that the district court erred when it found that the contract was formed on December 1, 1995, rather than on November 22, 1995. Although Dyno does not argue that the denial of its motion for summary judgment was erroneous, Dyno asserts that the determination made by the district court in ruling on the motion that the contract was made on December 1, 1995, when Lewis signed the fax documents, was erroneous.

Dyno asserted in its motion for summary judgment, and continues to argue to this Court, that the contract was actually entered into on November 22, 1995, when Lewis told Ratcliffe to go ahead and order the materials that Ratcliffe had listed in his November 8 and November 13 faxes. Dyno claims that the parties agreed to the essential terms of price, quantity, and description, and any other terms to the contract could be supplied by the "gap-filler" provisions of the Uniform Commercial Code, which do not limit the seller's liability for consequential damages.

In order to prove the existence of a contract, a plaintiff is required to demonstrate the essential requirements of an offer, acceptance, and consideration. See Helle v. Landmark, Inc., 15 Ohio App.3d 1, 8, 472 N.E.2d 765, 773 (1984). A valid and binding contract comes into existence when an offer is accepted. See Realty Dev., Inc. v. Kosydar, 322 N.E.2d 328, 332 (Ohio Ct. App. 1974)(per curiam). Dyno contends that the written price quotations Ratcliffe faxed to Lewis on November 8, 1995, and November 13, 1995, constituted the offer, which Lewis accepted on behalf of Dyno on or about November 22, 1995, when Lewis told Ratcliffe to order the materials listed on the price quote.

"Typically, a price quotation is considered an invitation for an offer, rather than an offer to form a binding contract." White Consol. Indus., Inc. v. McGill Mfg. Co., 165 F.3d 1185, 1190 (8th Cir. 1999)(citing Litton Microwave Cooking Prods. v. Leviton Mfg. Co., 15 F.3d 790, 794 (8th Cir. 1994)); see also Realty Dev., Inc., 322 N.E.2d at 332 (finding that the price quotation furnished to the appellant was ...

To continue reading

Request your trial
80 cases
  • Stratton v. Portfolio Recovery Assocs., LLC, Civil Action No. 5:13-147-DCR
    • United States
    • U.S. District Court — Eastern District of Kentucky
    • March 21, 2016
    ...Further, an “other qualified witness” need not have “personal knowledge” of the preparation of the record. Dyno Construction Co. v. McWane, Inc. , 198 F.3d 567, 575–76 (6th Cir.1999). Instead, he or she must merely “be familiar with the company's recordkeeping practices.” Fambrough v. Wal–M......
  • State v. Fitzwater
    • United States
    • Supreme Court of Hawai'i
    • April 5, 2010
    ...witness is that he or she be familiar with the record-keeping procedures of the organization.'" (Quoting Dyno Constr. Co. v. McWane, Inc., 198 F.3d 567, 575-76 (6th Cir.1999).)). See also United States v. Box, 50 F.3d 345, 356 (5th Cir.1995) ("A qualified witness is one who can explain the ......
  • Kraft Foods North America v. Banner Engineering
    • United States
    • U.S. District Court — Eastern District of Virginia
    • August 25, 2006
    ...Audio Visual Associates, Inc. v. Sharp Electronics Corp., 210 F.3d 254, 259 (4th Cir. 2000). See also Dyno Constr. Co. v. Mc Wane, Inc., 198 F.3d 567, 572 (6th Cir. 1999) (noting that a price quotation is usually considered an invitation for an offer); Interstate Indus., Inc. v. Barclay Ind......
  • U.S.A. v. Salgado
    • United States
    • United States Courts of Appeals. United States Court of Appeals (6th Circuit)
    • September 19, 2000
    ...the foundation for the introduction of the business record have personal knowledge of their preparation." Dyno Construction Co. v. McWane, Inc., 198 F.3d 567, 575-76 (6th Cir. 1999). A computer printout is admissible under Rule 803(6) as a business record if the offer or establishes a suffi......
  • Request a trial to view additional results
2 books & journal articles
  • Hearsay Issues Most Relevant in Antitrust Cases
    • United States
    • ABA Antitrust Library Antitrust Evidence Handbook
    • January 1, 2016
    ...were admissible when a qualified witness testified about the procedures for recording the information); Dynco Constr. Co. v. McWane, Inc., 198 F.3d 567, 575-76 (6th Cir. 1999) (operations manager of Federal Express could lay the foundation for its record-keeping systems even though he did n......
  • Table of Cases
    • United States
    • ABA Antitrust Library Antitrust Evidence Handbook
    • January 1, 2016
    ...Cir. 1973), 103 Duplan Corp. v. Moulinage et Retorderie de Chavanoz, 509 F.2d 730 (4th Cir. 1974), 107 Dynco Constr. Co. v. McWane, Inc., 198 F.3d 567 (6th Cir. 1999), 33 E East Portland Imaging Ctr. v. Providence Health System-Oregon, No. 05-0465, 2006 WL 752590 (D. Or. Mar. 21, 2006), aff......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT