Seaboard Lumber Company v. U.S.

Decision Date18 October 2002
Docket NumberNo. 01-5097.,No. 01-5124.,01-5097.,01-5124.
Citation308 F.3d 1283
PartiesSEABOARD LUMBER COMPANY and Capital Development Company, Plaintiffs-Appellants, v. UNITED STATES, Defendant-Appellee.
CourtU.S. Court of Appeals — Federal Circuit

Andrew R. Gala, Schwabe, Williamson & Wyatt, P.C., of Seattle, WA, argued for plaintiffs-appellants. With him on the brief was William F. Lenihan. Of counsel was Steven A. Miller.

Richard P. Nockett, Attorney, Civil Division, Department of Justice, of Washington, DC, argued for defendant-appellee. With him on the brief were Robert D. McCallum, Jr., Assistant Attorney General; David M. Cohen, Director; John W. Showalter, Assistant Director, and John Warshawsky, Attorney. Of counsel on the brief was Lori Polin Jones, Attorney, Office of the General Counsel, Department of Agriculture, of Washington, DC.

Before NEWMAN, SCHALL, and LINN, Circuit Judges.

LINN, Circuit Judge.

Seaboard Lumber Co. ("Seaboard") and Capital Development Co. ("CDC") jointly appeal from decisions of the United States Court of Federal Claims assessing liability and awarding damages to the government resulting from the respective failures of each of the companies to perform on different timber sales contracts. Seaboard Lumber Co. v. United States, 48 Fed. Cl. 814 (2001) ("Seaboard II"); Capital Dev. Co. v. United States, 49 Fed. Cl. 178 (2001). Seaboard also appeals from the rejection as a matter of law of its non-performance defenses of force majeure, impossibility of performance, commercial impracticability and frustration of purpose. Seaboard Lumber Co. v. United States, 41 Fed.Cl. 401 (1998) ("Seaboard I"). Because the Court of Federal Claims did not err in its conclusions of law, and its findings of fact on damages are not clearly erroneous, we affirm.

I. BACKGROUND
A. The Timber Contracts

At issue in this appeal are one timber sale contract, designated the "What" contract, between Seaboard and the Forest Service, and six timber sale contracts, designated the "Bride," "Pearl," "Ram," "Cougar," "Short Flat," and "Cow" contracts, between CDC and the Forest Service. Seaboard disputes both liability and damages resulting from its breach of the What contract. CDC disputes both liability and damages resulting from its breach of the Cow contract. CDC concedes liability but disputes damages resulting from its breach of the Bride, Pearl, Ram, Cougar, and Short Flat contracts.

1. The What Contract

In September 1980, Seaboard entered into the What contract — a fixed price contract to harvest timber. At that time, there was a housing boom and the price of timber was high. The contract required Seaboard, by the contract termination date of March 31, 1983, to cut, remove, and pay for all of the timber on the What parcel.

Between 1981 and 1983, the government allowed interest rates to rise in order to combat inflation, and at least in part because of the rise in interest rates, the housing and lumber markets softened. Many contractors ran into financial difficulties. The timber in all of the parcels at issue in this appeal was of sufficient quality to harvest, and the contractors had the opportunity to conduct a harvest if they so desired. Some logging contractors performed on their timber contracts during this period. Others did not.

In April 1983, the Forest Service allowed Seaboard a two-year extension of the contract term under the agency's SOFT II extension policy, which allowed contract extensions due to then-depressed markets for forest products. The What contract expired, uncompleted, on December 28, 1985.

The What contract contained a damages provision, Provision B9.4, which stated, in pertinent part, that:

Damages due the United States for Purchaser's failure to cut and remove such timber meeting Utilization Standards shall be the amount by which Current Contract Value plus the cost of resale, less any effective Purchase Credit remaining at the time of termination, exceeds the resale value at new Bid Rates. If there is no resale, damages due shall be determined by subtracting the value established by said appraisal from the difference between Current Contract Value and Effective Purchaser Credit.

In 1984, Congress enacted the Federal Timber Contract Payment Modification Act, which stated that, effective 1985, "in any contract for sale of timber from the National Forests, the Secretary of Agriculture shall require a cash down-payment at the time the contract is executed and periodic payments to be made over the remaining time of the contract." 16 U.S.C. § 618(d) (2000). The purported goal of these new financial requirements was to deter speculative bidding.

In 1987, the Forest Service resold the What contract. Pursuant to 16 U.S.C. § 618, the resale contract incorporated both a down payment requirement (10 percent of advertised resale plus a 20 percent bid premium) and a midpoint payment requirement (25 percent of the total contract value) that equaled $61,800 and $149,000, respectively. The original What contract contained neither financial requirement. In addition, the resale contract sold less timber than the original, 5,900 MBF1 as opposed to the original 6,300 MBF, and contained a shorter logging period, 9.5 months of normal operating season as opposed to the original 18.5 months.

There were three bidders on the What resale, one fewer than on the original contract. The contract was resold for less than the then-current contract value of the remaining timber plus the cost of resale. Pursuant to the governing damages provision, the Forest Service's contracting officer demanded the difference. The government subsequently reduced the requested damage amount to reflect what it estimated to be the effect of the down payment and midpoint payment requirements in reducing the resale price.

2. The Cow Contract

On April 15, 1983, CDC and the Forest Service entered into the Cow contract. The contract required CDC to cut, remove, and pay for all of the timber included in the sale by the contract termination date of March 31, 1985. By early 1985, CDC had removed over 75 percent of the original estimated volume of 4,300 MBF. CDC sought and the Forest Service granted a one-year extension pursuant to Special Provisions C8.23 & C8.231.2 In July 1985, the contracting officer sent CDC a letter stating that the Cow contract "will not qualify for any further extensions." Nevertheless, CDC requested a second one-year extension. The Forest Service denied this request. CDC abandoned the contract on December 26, 1985 after harvesting an amount of timber that was in excess of 100% of the original estimated volume but was not all of the timber in the Cow parcel.

The Cow contract, like CDC's other contracts, contained Provision C9.4, which provides, in pertinent part:

Damages due the United States for Purchaser's failure to cut and remove Included Timber meeting Utilization Standards shall be the amount by which Current Contract Value, plus costs described below, less any Effective Purchaser Credit remaining at time of termination, exceeds the resale value at new Bid Rates. If there is no resale, damages due shall be determined by subtracting the value established by said appraisal from the difference between the Current Contract Value and unused Effective Purchaser Credit, plus any of the following applicable costs:

(1) The cost of resale or reoffering;

(2) Any increase in Purchaser Credit Limit allowance for unconstructed Specified Road facilities which are needed to harvest the remaining uncut volume....;

....

(4) The Government's loss caused by the delay in receipt of stumpage payments. Such loss will be measured by interest at the current rate being paid for borrowing by the United States (as published or calculated by the Treasury Department in TFRM 6-8020-20) on the unpaid contract value at Termination Date. Interest will be charged for the total number of months, or portions thereof from Termination Date until midpoint of the contract resale period, less any time in excess of 1 year needed to make the resale;

(5) Any increase in reforestation costs ....

In August 1986, the Forest Service resold the Cow contract. The resale contract differed from CDC's original contract in several respects.

First, the original contract included an estimated 4,300 MBF of timber, while the resale included less, an estimate of only 792 MBF, due to CDC's partial performance. The resale provided one and one-half operating seasons for logging, while the original contract, as extended to March 31, 1986, provided three operating seasons in which to log. In addition, the resale contract required a 10 percent down payment of $6,300, while the original contract required only a 5 percent down payment of $27,500. Furthermore, the resale contract required a midpoint payment in the amount of $15,874.51, while the original contract did not require a midpoint payment.

The resale contract sold for less than the then-current value of the remaining timber volume, plus cost of resale. Pursuant to Provision C9.4, the Forest Service's contracting officer demanded the difference with interest as damages. The amount was $82,916.

3. The Bride Contract

The Bride resale contract differed in requiring a 10 percent down payment of $7,300, while the original contract required only 5 percent, an increase of $3,700. The resale contract required a midpoint payment in the amount of $27,853, while the original contract required a midpoint payment in the amount of $18,200, an increase of $9,653.

There was one bidder on the Bride Resale. It sold for less than the then-current value of the remaining timber volume plus the cost of resale. Pursuant to Provision C9.4, the Forest Service's contracting officer demanded $15,549.78 in damages.

4. The Pearl Contract

The Pearl resale contract differed from the original contract in several respects. First, the original sale...

To continue reading

Request your trial
114 cases
  • Shelter Forest Int'l Acquisition, Inc. v. Cosco Shipping (USA) Inc.
    • United States
    • U.S. District Court — District of Oregon
    • July 28, 2020
    ...of the risk he expressly assumed would nullify a central term of the contract. Id. at 275 ; see also Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1293 (Fed. Cir. 2002) (observing that government fiscal or monetary policy decisions "have only an attenuated effect on the contracts at ......
  • Bristol-Myers Squibb v. Andrx Pharmaceuticals
    • United States
    • U.S. District Court — Southern District of Florida
    • June 4, 2004
    ...where the Court must evaluate the evidence regardless of whether it ultimately decides to exclude it. See Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1302 (Fed.Cir.2002) (holding that, while issues of prejudice are "of lesser import in bench trials, where no screening of the factfi......
  • Casitas Mun. Water Dist. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • September 25, 2008
    ...acts defense only when the sovereign act renders the government's performance impossible. See, e.g., Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1294 (Fed.Cir.2002). Casitas argues that the sovereign acts doctrine does not apply because the ESA did not make it impossible for the go......
  • Gulf Grp. Gen. Enters. Co. v. United States
    • United States
    • U.S. Claims Court
    • July 2, 2013
    ...a party may avoid liability for breach." 482 F.3d at 1365 (quoting Winstar, 518 U.S. at 904). Seealso, Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1294 (Fed. Cir. 2002) (stating that contract performance by the government is excused under the sovereign acts defense when "it is obje......
  • Request a trial to view additional results
1 firm's commentaries
  • Material Escalation: A Difficult Road to Recover Costs
    • United States
    • LexBlog United States
    • February 28, 2022
    ...to rely on a force majeure clause to excuse performance due to increased costs. For example, in Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1294 (Fed. Cir. 2002), the court declined to excuse the contractor’s performance under a force majeure clause where a slump in the timber mark......
3 books & journal articles
  • Witness
    • United States
    • James Publishing Practical Law Books Trial Objections
    • May 5, 2022
    ...standard for review of a trial court’s decision under Daubert to admit or exclude expert testimony. Seaboard Lumber Co. v. U.S. , 308 F.3d 1283, 1302 (Fed. Cir. 2002). Overruling government’s argument that Daubert does not apply to bench trials ; Daubert ’s reliability and relevance require......
  • Coronavirus Delay and Disruption Claims
    • United States
    • ABA General Library The Construction Lawyer No. 41-2, April 2021
    • April 1, 2021
    ...determined that no contractor could perform the work. Seaboard Lumber Co. v. United States, 41 Fed. Cl. 401, 417 (Ct. Cl. 1998), aff’d , 308 F.3d 1283 (Fed. Cir. 2002). Impossibility of performance as a defense to nonperformance can be invoked only where facts making performance impossible ......
  • The "loss of chance" doctrine of damages for breach of contract.
    • United States
    • Florida Bar Journal Vol. 79 No. 9, October - October 2005
    • October 1, 2005
    ...and torts). (8) Bangor, 543 F.2d at 1111 (citations omitted). (9) Story Parchment, 282 U.S. at 564. (10) Seaboard Lumber Co. v. U.S, 308 F.3d 1283, 1302 (C.A. Fed. (11) McCORMICK, DAMAGES, 117-23; Restatement (First) of Contracts, [section] 332. (12) See, e.g., Grayson v. Irvmar Realty, 184......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT