Him Portland, LLC v. Devito Builders, Inc.

Citation317 F.3d 41
Decision Date17 January 2003
Docket NumberNo. 02-1955.,02-1955.
PartiesHIM PORTLAND, LLC, Plaintiff, Appellant, v. DEVITO BUILDERS, INC., Defendant, Appellee.
CourtUnited States Courts of Appeals. United States Court of Appeals (1st Circuit)

Philip P. Mancini, with whom Paul M. Koziell and Drummond & Drummond, LLP were on brief, for appellant.

Louis B. Butterfield, with whom Olafsen & Butterfield was on brief, for appellee.

Before TORRUELLA, Circuit Judge, CYR and STAHL, Senior Circuit Judges.

TORRUELLA, Circuit Judge.

This case requires us to decide whether a party to an arbitration agreement that is subject to conditions precedent can, without satisfying those conditions, compel arbitration under the Federal Arbitration Act. ("FAA"). HIM Portland ("HIM") moved the district court, pursuant to an arbitration agreement, to compel DeVito Builders ("DeVito") to arbitrate a contract dispute between them. DeVito contends that their agreement provided that a request for mediation was a condition precedent to arbitration. Because the parties intentionally conditioned arbitration upon either party's request for mediation, we conclude that HIM Portland's failure to request mediation precludes it from compelling arbitration under the FAA. Therefore we affirm the district court's Order denying HIM's motion to compel arbitration and stay matters pending the completion of arbitration.

I. Background

HIM contracted with DeVito for the renovation of a Suisse Chalet motel in Portland, Maine. On April 3, 2002, HIM filed a complaint against DeVito in the District Court for the District of Maine seeking to recover damages under claims for breach of contract, slander of title and fraudulent misrepresentation. After DeVito filed its answer to HIM's complaint, HIM moved to compel arbitration and stay the proceedings in the district court until the completion of arbitration, asserting that the contract contained an arbitration clause that required the parties to arbitrate the dispute. The contract provides, in pertinent part:

9.10.1 Claims, disputes and other matters in question arising out of or relating to this Contract, including those alleging an error or omission by the Architect but excluding those arising under Paragraph 15.2 [Hazardous Materials], shall be referred initially to the Architect for decision. Such matters, except those relating to aesthetic effect and except those waived as provided for in Paragraph 9.11 [Consequential Damages] and Subparagraphs 14.5.3 and 14.5.4 [making or acceptance of final payment constitutes waiver], shall, after initial decision by the Architect, or 30 days after submission of the matter to the Architect, be subject to mediation as a condition precedent to arbitration or the institution of legal or equitable proceedings by either party.

9.10.3 The parties shall endeavor to resolve their disputes by mediation which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Mediation Rules of the American Arbitration Association currently in effect.... The request may be made concurrently with the filing of a demand for arbitration, but, in such event, mediation shall proceed in advance of arbitration or legal or equitable proceedings, which shall be stayed pending mediation for a period of 60 days from the date of filing, unless stayed for a longer period by agreement of the parties or court order.

9.10.4 Claims, disputes and other matters in question arising out of or relating to the Contract that are not resolved by mediation, except matters relating to aesthetic effect and except those waived as provided for in Paragraph 9.11 and Subparagraphs 14.5.3 and 14.5.4, shall be decided by arbitration which, unless the parties mutually agree otherwise, shall be in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect.... The award rendered by the arbitrator or arbitrators shall be final, and judgment may be entered upon it in accordance with applicable law in any court having jurisdiction thereof. (Emphasis added).

On July 26, 2002, the district court issued a Memorandum and Order denying HIM's motion to compel arbitration and to stay proceedings until the completion of arbitration. The court reasoned that the plain language of the contract manifested the parties' clear intent to require mediation as a condition precedent to arbitration. Accordingly, the court found that HIM's failure to request mediation precluded enforcement of the contract's arbitration clause. This timely appeal followed.

II. Discussion

Congress enacted the FAA in 1925 to place arbitration agreements "upon the same footing as other contracts" and to render them "valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract." EEOC v. Waffle House, Inc., 534 U.S. 279, 288-89, 122 S.Ct. 754, 151 L.Ed.2d 755 (2002). To facilitate arbitration agreements, the FAA provides that when a federal court reviews an issue that is subject to an arbitration agreement the court shall, on the motion of one of the parties, stay its proceedings until "arbitration has been had in accordance with the terms of the agreement." 9 U.S.C.A. § 3. The Supreme Court has held that "questions of arbitrability must be addressed with a healthy regard for the federal policy favoring arbitrations." Moses H. Cone Mem'l. Hosp. v. Mercury Constr. Corp., 460 U.S. 1, 24, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983).

Nevertheless, arbitration is a matter of contract law and consequently "a party cannot be required to submit to arbitration any dispute which he has not agreed so to submit." AT & T Techs., Inc. v. Communications Workers of America, 475 U.S. 643, 648, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986). The Court specified that "the FAA's proarbitration policy does not operate without regard to the wishes of the contracting parties." Mastrobuono v. Shearson Lehman Hutton, 514 U.S. 52, 57, 115 S.Ct. 1212, 131 L.Ed.2d 76 (1995). Indeed, were a court to employ the FAA to...

To continue reading

Request your trial
43 cases
  • Chorley Enters., Inc. v. Dickey's Barbecue Rests., Inc., s. 14–1799
    • United States
    • U.S. Court of Appeals — Fourth Circuit
    • 5 August 2015
    ...precedent to arbitration is not fulfilled, a party to a contract does not have a right to arbitration."); HIM Portland LLC v. DeVito Builders Inc., 317 F.3d 41, 44 (1st Cir.2003) (refusing to compel arbitration because "[u]nder the plain language of the contract, the arbitration provision o......
  • Nat'l BANK Of Ariz. v. LEE
    • United States
    • Arizona Court of Appeals
    • 21 June 2010
    ...the same as [that in] the... cited cases, [all] of which involve conditions precedent to arbitration." See HIM Portland, LLC v. DeVito Builders, Inc., 317 F.3d 41 (1st Cir. 2003); Douglass v. Allstate Ins. Co., 953 P.2d 770, 771 (Or. App. 1998); Lind v. Allstate Ins. Co., 902 P.2d 603, 604-......
  • Eazy Elecs. & Tech., LLC v. LG Elecs., Inc.
    • United States
    • U.S. District Court — District of Puerto Rico
    • 30 December 2016
    ...favors arbitration over litigation, so long as an agreement to arbitrate exists in the first place. See HIM Portland, LLC v. DeVito Builders, Inc. , 317 F.3d 41, 43 (1st Cir. 2003). Thus, "there is a presumption of arbitrability in the sense that ‘[a]n order to arbitrate the particular grie......
  • Melendez v. Starwood Hotels & Resorts Worldwide, Inc.
    • United States
    • U.S. District Court — District of Puerto Rico
    • 1 February 2013
    ...favors arbitration over litigation, so long as an agreement to arbitrate exists in the first place. See HIM Portland, LLC v. DeVito Builders, Inc., 317 F.3d 41, 43 (1st Cir.2003). Thus, “there is a presumption of arbitrability in the sense that ‘[a]n order to arbitrate the particular grieva......
  • Request a trial to view additional results
1 books & journal articles
  • Summary Judgement for Failure to Mediate
    • United States
    • Kansas Bar Association KBA Bar Journal No. 77-6, June 2008
    • Invalid date
    ...547, 7 P3d at 1183 (citing Atterberry v. Ritchie, 243 Kan. 277, 285, 756 P.2d 424 (1988)). [66] HIM Portland LLC v. DeVito Builders Inc., 317 F.3d 41, 44 (1st Cir. 2003). [67] Id. at 44. [68] 9 U.S.C.A. §§ 3-4. See also K.S.A. 5-402(d). [69] See the Kansas Dispute Resolution Act, K.S.A. 5-5......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT