United States v. Joseph Holpuch Co

Citation106 Ct.Cl. 852,90 L.Ed. 1192,66 S.Ct. 1000,328 U.S. 234
Decision Date20 May 1946
Docket NumberNos. 696 and 697,s. 696 and 697
PartiesUNITED STATES v. JOSEPH A. HOLPUCH CO. (two cases)
CourtUnited States Supreme Court

Mr. Abraham J. Harris, of Washington, D.C., for petitioner.

No appearance for respondent.

Mr. Justice MURPHY delivered the opinion of the Court.

The narrow question here is whether a contractor's failure to exhaust the administrative appeal provisions of a Government construction contract bars him from bringing suit in the Court of Claims to recover damages.

Respondent, a building contractor, entered into two contracts1 with the United States through the War Department in 1933 to construct officers' quarters at Fort Sam Houston, Texas, which were being built as a Federal Emergency Administration of Public Works project. Disputes arose as to excauvations for footings and as to increased wages ordered to be paid to respondent's bricklayers. Respondent brought suit against the Government on these matters in the Court of Claims, which entered judgments in favor of respondent on both items.2

Article 15, which appeared in both contracts, provided: 'All labor issues arising under this contract which cannot be satisfactorily adjusted by the contracting officer shall be submitted to the Board of Labor Review. Except as otherwise specifically provided in this contract, all other disputes concerning questions arising under this contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor, within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto as to such questions. In the meantime the contractor shall diligently proceed with the work as directed.'

The dispute concerning the footing excavations arose out of an apparent inconsistency between certain figures sed in the specifications and in the drawings. The specifications estimated that respondent was to excavate to a depth of 37 1/2 feet below the first floor level of the buildings. The drawings, on the other hand, were found by the Court of Claims to call for excavations to the depth of 33 feet. Additional payments were to be made to respondent for excavations deeper than indicated 'on the drawings' while the Government was to receive a credit for excavations of a lesser depth. Respondent made vari- ous excavations ranging in depth from 27.58 feet to 42.42 feet. The problem thus presented itself as to whether the 37 1/2-foot figure in the specifications or the 33-foot figure in the drawings should serve as the basis for extra compensation to the respondent and for credit to the Government.

Article 2 of the contracts provided: 'In case of difference between drawings and specifications, the specifications shall govern. In any case of discrepancy in the figures or drawings, the matter shall be immediately submitted to the contracting officer'. The specifications contained a similar provision and added that the constructing quartermaster who to be the interpreter of the 'intent and meaning of the drawings and specifications.' The constructing quartermaster duly resolved the discrepancy in this instance by interpreting the specifications and drawings to mean that the footing excavations were to be paid for on the basis of the 37 1/2 feet estimated in the specifications. Respondent made no attempt to appeal from this decision to the contracting officer or to the departmental head in accordance with the terms of Article 15.

The other dispute concerned a required increase in wages for respondent's bricklayers. The contracts established $1.00 per hour as the minimum wage rate for skilled labor unless, as of April 30, 1933, there should be a higher prevailing hourly rate prescribed by collective agreements between employers and employees. Article 18(e) provided that this minimum wage rate 'shall be subject to change by the Federal Emergency Administration of Public Works on recommendation of the Board of Labor Review,' in which case 'the contract price shall be adjusted accordingly.' On March 3, 1934, the Board of Labor Review ruled that bricklayers on another Army construction project at San Antonio, Texas, with which respond- ent was unconnected, should be paid at the rate of $1.25 per hour retroactive to February 2, 1934. Respondent was informed of this decision and on March 23, 1934, the constructing quartermaster advised respondent that all bricklayers employed on the instant project 'will be paid at the rate of $1.25 per hour.' Respondent stated that it 'would be governed accordingly but under protest, and (that it) expected reimbursement of the difference of 25 cents per hour.' On May 12, 1934, the constructing quartermaster advised respondent 'that it was the decision of the contracting officer that bricklayers employed on War Department construction projects at San Antonio, Texas, and vicinity (Fort Sam Houston is in this vicinity) should be paid $1.25 per hour, retroactive to February 2, 1934,' and that respondent would be within its rights 'to file appeal with the Board of Labor Review from the decision of the contracting officer.'3 No such appeal was taken; respondent merely paid its bricklayers $1.25 per hour and then filed a claim in the court below for the 25-cent differential. Here again the provisions of Article 15 were ignored.

We cannot sanction respondent's failure to abide by the appeal provisions of Article 15 of the contracts which it made with the United States. Both the dispute over the footing excavations and the dispute over the bricklayers' wages were 'questions arising under this contract' within the meaning of Article 15. The first was a question arising under Article 2 of the contracts as well as under the specifications, which expressly contemplated that Government officers would resolve all discrepancies between specifications and drawings. Their decisions in such matters were clearly appealable under Article 15. The second dispute was a question arising under the wage provisions of Article 18 of the contracts; that question involved a consideration of the factual situation surrounding the required wage increase and a determination of the validity and effect of the increase under the circumstances. Any decision or order of a subordinate Government officer in this respect was also appealable under Article 15. Yet respondent did not even seek the contracting officer's opinion as to the footing excavation decision of the constructing quartermaster. And as to the contracting officer's order requiring an increase in the bricklayers' wages, respondent neglected to file a written appeal to the departmental head or his representative.

But Article 15 is something more than a dead letter to be revived only at the convenience or discretion of the contractor. It is a clear, unambiguous provision applicable at all times and binding on all parties to the contract. No court is justified in disregarding its letter or spirit. Article 15 is controlling as to all disputes 'concerning questions arising under this contract' unless otherwise specified in the contract. It creates a mechanism whereby adjustments may be made and errors corrected on an administrative level, thereby permitting the Government to mitigate or avoid large damage claims that might otherwise be created. United States v. Blair, 321 U.S. 730, 735, 64 S.Ct. 820, 823, 88 L.Ed. 1039. This mechanism, moreover, is exclusive in nature. Solely through its operation may claims be made and adjudicated as to matters arising under the contract. United States v. Blair, supra, 321 U.S. 735, 64 S.Ct. 823, 88 L.Ed. 1039; United States v. Callahan Walker Const. Co., 317 U.S. 56, 61, 63 S.Ct. 113, 115, 87 L.Ed. 49. And in the absence of some clear evidence that the appeal procedure is inadequate or unavailable, that procedure must be pursued and exhausted before a contractor can be heard to complain in a court.

It follows that when a contractor chooses without due cause to ignore the provisions of Article 15 he destroys his right to sue for damages in the Court of Claims. That court is then obliged to outlaw his claims, whatever may be their equity. To do otherwise is to rewrite the contract.

In this instance no justifiable excuse is apparent for respondent's failure to exhaust the appeal provisions of Article 15. Certainly the reasons relied upon by the Court of Claims are lacking in merit. The court felt that the dispute over the footing excavation figures involved only a matter of contract price computation and that the responsibility for such a computation rested solely with the Army Finance Officer at Fort Sam Houston, any decision by the contracting officer on the matter being on more than advisory. Since the contracts made no provision for an appeal of the Finance Officer's computation, the Court of Claims held that there was no appealable decision confronting respondent and that respondent's claim could be heard and determined by that court. Support for this novel interpretation was sought in the statement on th covers of the contracts that payment on the contracts was to be made 'by the Finance Officer, U.S. Army, Fort Sam Houston, Texas.' The short answer is that this designation of a disbursing officer is not a part of the contracts and cannot be used in any way to alter or amend any actual provisions thereof. The designation only identifies the person whose duty it is to perform the ministerial function of disbursement and is subject to change at any time by the War Department without notice to the contractor.4 Moreover, even if it be assumed that the issue did concern only the amount of payment under the contracts,5 such an issue is a question arising under the...

To continue reading

Request your trial
149 cases
  • Seaboard Lumber Co. v. U.S., 88-1486
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • May 17, 1990
    ...government's part. Wunderlich v. United States, 342 U.S. 98, 99, 72 S.Ct. 154, 155, 96 L.Ed. 113 (1951); United States v. Holpuch Co., 328 U.S. 234, 66 S.Ct. 1000, 90 L.Ed. 1192 (1945) (contractor's failure to appeal per dispute resolution process in contract precluded suit in Court of Clai......
  • Patsy v. Florida Intern. University
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • January 22, 1981
    ...294 (1966); Frozen Food Express v. United States, 351 U.S. 40, 76 S.Ct. 569, 100 L.Ed. 730 (1956); United States v. Joseph A. Holpuch Co., 328 U.S. 234, 66 S.Ct. 1000, 90 L.Ed. 1192 (1946); United States Alkali Export Association v. United States, 325 U.S. 196, 65 S.Ct. 1120, 89 L.Ed. 1554 ......
  • Bethlehem Steel Corporation v. Grace Line, Inc., 21050.
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • March 6, 1969
    ...States v. Anthony Grace & Sons, Inc., 384 U.S. 424, 430, 86 S.Ct. 1539, 16 L.Ed.2d 662 (1966); United States v. Joseph A. Holpuch Co., 328 U.S. 234, 240, 66 S.Ct. 1000, 90 L.Ed. 1192 (1946); United States v. Blair, 321 U.S. 730, 736-737, 64 S.Ct. 820, 88 L.Ed. 1039 41 The record discloses t......
  • Louis v. Nelson
    • United States
    • U.S. District Court — Southern District of Florida
    • June 18, 1982
    ...294 (1966); Frozen Food Express v. United States, 351 U.S. 40, 76 S.Ct. 569, 100 L.Ed. 910 (1956); United States v. Joseph A. Holpuch Co., 328 U.S. 234, 66 S.Ct. 1000, 90 L.Ed. 1192 (1946); United States Alkali Export Association v. United States, 325 U.S. 196, 65 S.Ct. 1120, 89 L.Ed. 1554 ......
  • Request a trial to view additional results
1 books & journal articles
  • The Construction Industry in the U.S. Supreme Court: Part 1, Contract Law
    • United States
    • ABA General Library The Construction Lawyer No. 41-2, April 2021
    • April 1, 2021
    ...Id. at 218–19. 64. Id. at 217, 233. 65. See supra text accompanying notes 28–35. 66. See, e.g ., United States v. Joseph A. Holpuch Co., 328 U.S. 234 (1946); United States v. Callahan Walker Constr. Co., 317 U.S. 56 (1942); Ripley v. United States, 223 U.S. 695 (1912); United States v. Glea......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT