United States v. Standard Surety & Casualty Co.

Citation37 F. Supp. 323
Decision Date05 March 1941
Docket NumberCiv. No. 6-467.
PartiesUNITED STATES, for Use and Benefit of DORFMAN et al. v. STANDARD SURETY & CASUALTY CO. OF NEW YORK et al.
CourtU.S. District Court — Southern District of New York

Samuel Shapiro, of New York City, for use-plaintiffs Irving Dorfman and Barney Shapoff.

Maxwell Lehrhaupt, of New York City, for use-plaintiff Hyman Kenoff.

Max E. Greenberg, of New York City, for defendant Standard Surety & Casualty Co. of New York.

Barr, Bennett & Fullen, of New York City (Lawrence J. Lieberman, of New York City, of counsel), for defendant Herman Katz.

BYERS, District Judge.

This is an action upon a bond required by 40 U.S.C.A. § 270a(2), namely, a payment bond "for the protection of all persons supplying labor and material in the prosecution of the work * * *", namely, that specified in a contract entered into by Reuben Malkin, Inc., with the United States Government, concerning work done at 201 Varick Street (U. S. Appraiser's Stores) New York City.

It sufficiently appears that there was such a contract and that the contractor did not pay in full for the labor involved, and that some resultant liability attached to the defendant Surety Company.

It is necessary to determine the amount remaining unpaid by the contractor, and the persons who are entitled to judgment under the bond, and the amounts due.

The evidence, as a whole, is confused, fragmentary and in some respects quite difficult of acceptance.

The use-plaintiffs are Irving Dorfman and Barney Shapoff, who assert that they were subcontractors as to all the exterior painting, and that they are entitled to recover an alleged unpaid balance owing to them under the said subcontract.

For reasons to be stated, it will be found that they were not subcontractors but coforemen employed by the contractor, and their recovery must be limited to the amount remaining unpaid of their wages.

By order of January 15, 1941, Hyman Kenoff was permitted to intervene as a use-plaintiff, and he asserts that he was employed by Dorfman and Shapoff as a painter on the job, and that $131.25 of his wages remains unpaid.

It was stipulated on the trial that that is the correct amount of his claim.

The original complaint, filed December 8, 1939, named the Surety Company and Herman Katz as defendants and, in addition to the matters above stated and for a second cause of action, alleged that during the prosecution of the contract the defendant Katz loaned to the contractor Malkin the sum of $545, which was delivered to Dorfman and Shapoff, and by them applied toward the pay rolls of their laborers, and that the said $545 was included in the sum of $1,033 alleged in the first cause to have been paid by the contractor; that Katz had instituted an action to recover the $545 from Dorfman and Shapoff, and that they deny having done the borrowing, and that they were in doubt as to whether they were liable to Katz for any part of the moneys advanced by him.

On December 26, 1939, Katz filed a cross-complaint and answer, in which it was asserted that the said $545 was loaned by him to Dorfman and Shapoff to be used for the payment of labor; and for his cross-complaint against the Surety Company, the Malkin contract was alleged, and that during the months of April, May and July, 1939, Katz, at the joint request of Malkin and Dorfman and Shapoff, "caused to be performed certain labor and services consisting of painting in connection with" the said contract, of the reasonable price and value of $545, and judgment was sought against the defendant Surety Company for that sum.

There was subsequent procedural activity in great volume, and to little apparent purpose, none of which seems to require present recital.

It also appears that certain laborers, who were not paid, have filed labor claims with the Federal Works Agency for wages owing to them, namely:

                Eric Holm ....................... $27.50
                Karl Jensen .....................  23.50
                Charles Jensen ..................  23.50
                Eddie Schnitzer .................  85.00
                

as the result of which, the total sum of $159.50 was withheld from the final payment on the Malkin contract, and apparently those sums are now in the custody of the Comptroller General for the benefit of the claimants. While those sums were not paid by the contractor, they have been earmarked for the workmen, and are available to them.

It seems that the exterior painting embraced within the Malkin contract was done during a period of seven weeks, commencing about April 17, 1939, and terminating on or about June 10, 1939.

Dorfman and Shapoff have failed to satisfy this court that their status was that of subcontractors, for the following reasons:

(a) The alleged subcontract (their Exhibit 1) is dated April 17, 1939, and purports to constitute an agreement between Malkin and Dorfman and Shapoff for all the said exterior painting; Dorfman and Shapoff agreed to furnish all labor and Malkin agreed to furnish all "equipment, material and compensation" therefor, and Malkin agreed to pay $3,200 as the contract price, thirty per cent. upon the "Inspector's approval" and the balance upon receipt of his check from the Government in final payment.

In other words, Malkin was to pay for all labor and material and employees' compensation, and Dorfman and Shapoff were to assume no financial responsibility. To call this a subcontract would not make it such.

A statement of the judicial understanding of a true subcontract will be found in the opinion of Mr. Justice Day in United States to Use of Hill v. American Surety Company, 200 U.S. 197, at 205, 26 S.Ct. 168, at 171, 50 L.Ed. 437: "If the contractor sees fit to let the work to a subcontractor, who employs labor and buys materials which are used to carry out and fulfil the engagement of the original contract * * * he is thereby supplied with the materials and labor for the fulfilment of his engagement as effectually as he would have been had he directly hired the labor or bought the materials."

The only labor that Malkin...

To continue reading

Request your trial
7 cases
  • Tri-State Employment Services v. Mountbatten Sur.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (2nd Circuit)
    • 9 Julio 2002
    ...claimants under labor and materials surety bonds. See id. at *3 (citing United States for Use and Benefit of Dorfman v. Standard Sur. & Cas. Co. of New York, 37 F.Supp. 323, 326 (S.D.N.Y.1941)). The district court then While a PEO might serve more administrative functions than a creditor, i......
  • Southern Painting Company of Tenn. v. United States
    • United States
    • United States Courts of Appeals. United States Court of Appeals (10th Circuit)
    • 5 Mayo 1955
    ...v. United States, for the Use of Turner, 9 Cir., 159 F.2d 182. The case of United States, for Use and Benefit of Dorfman v. Standard Surety and Casualty Company, D.C., 37 F.Supp. 323, relied on by appellant, is clearly not in point. There the alleged subcontract was executed after everythin......
  • Gulf Ins. Co. v. GFA Group, Inc.
    • United States
    • United States Court of Appeals (Georgia)
    • 13 Septiembre 2001
    ...40 USC § 270a; Amcon, Inc. v. Southern Pipe &c. Co., 134 Ga.App. 655, 656, 215 S.E.2d 712 (1975). 6. United States v. Standard Surety &c. Co. of New York, 37 F.Supp. 323 (S.D.N.Y.1941); First Nat. Bank &c.of Dothan v. American Surety &c., 53 F.2d 746 (5th 7. First Nat. Bank &c. v. MacDougal......
  • United States v. REPUBLIC CONSTRUCTION & MAIN. CO.
    • United States
    • U.S. District Court — Virgin Islands
    • 4 Marzo 1955
    ...v. National Surety Co., 6 Cir., 150 F. 465, affirmed 211 U.S. 552, 29 S.Ct. 202, 53 L.Ed. 321; United States for Use and Benefit of Dorfman v. Standard Surety & Cas. Co., D.C., 37 F.Supp. 323. However, since the supporting affidavits filed by counsel for both parties raise a number of contr......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT