LYKES-YOUNGSTOWN CORPORATION v. United States, 399-67.

Decision Date23 January 1970
Docket NumberNo. 399-67.,399-67.
Citation190 Ct. Cl. 348,420 F.2d 735
PartiesLYKES-YOUNGSTOWN CORPORATION v. The UNITED STATES.
CourtU.S. Claims Court

J. Alton Boyer, Washington, D. C., for plaintiff, Odell Kominers, Washington, D. C., attorney of record, J. Alton Boyer, Michael Joseph, and Kominers, Fort, Schlefer, Farmer & Boyer, Washington, D. C., of counsel.

Edward J. Friedlander, Washington, D. C., with whom was Asst. Atty. Gen. William D. Ruckelshaus, for defendant.

Before COWEN, Chief Judge, and LARAMORE, DURFEE, DAVIS, COLLINS, SKELTON and NICHOLS, Judges.

ON PLAINTIFF'S MOTION AND DEFENDANT'S CROSS MOTION FOR SUMMARY JUDGMENT

SKELTON, Judge.

This is a suit by a steamship company against the United States for damages for an alleged breach of three construction-differential subsidy contracts involving the construction of twelve ships. (Four ships in each of the contracts.)1

The plaintiff is now, and, at all times relevant to this case, has been engaged in the business of operating ocean-going cargo ships on regular routes found by the Maritime Subsidy Board to be essential trade routes of the United States between ports in this country and ports in foreign countries throughout the world.2

These operations are conducted under an operating-differential subsidy contract (No. FMB-59) entered into pursuant to Title VI of the Merchant Marine Act of 1936, 49 Stat. 1985, as amended (46 U.S.C. §§ 1171-1183) by plaintiff and the United States in 1957 for a term of twenty years beginning January 1, 1958. Under this contract, plaintiff is required to perform specified numbers of voyages annually on essential trade routes and to replace its existing ships by contracting to build new ones. The replacement program in the contract required plaintiff to build three groups of four ships each, construction of which was to commence on or about March 18, 1963, July 1, 1963, and July 1, 1964, respectively. Plaintiff's obligation to have these ships constructed was conditioned upon the board's policy to provide construction-differential subsidy pursuant to Title V of the Act for such new construction, and, if not provided, was to be deferred until such subsidy was provided.

The purpose of the construction-differential subsidy, which is a shipyard subsidy, is to equalize the cost of building ships in high-cost domestic United States shipyards with the lower cost of building such ships in foreign shipyards, from the standpoint of the owner, which is required by law and contract to have its ships built in the United States. The plaintiff filed applications for construction-differential subsidy covering each of the three groups of ships and the Board approved such applications and agreed to provide construction-differential subsidy in accordance with contracts entered into between the plaintiff and the defendant as described in the following paragraphs.

On April 4, 1963, November 21, 1963, and June 26, 1964, the plaintiff, as owner, and the Board entered into three construction-differential subsidy contracts Nos. MA/MSB-20, MA/MSB-31, and MA/MSB-37, each covering a group of four ships and each specifying the terms of the grant of subsidy by the Board in connection with the construction of said ships. At the same time, three construction contracts, Nos. MA/MSB-19, MA/MSB-30, and MA/MSB-36, were entered into between the plaintiff, as owner, and Avondale Shipyards, Inc., as contractor, and the Board, which provided for the construction of the twelve ships by the contractor. These construction contracts are only incidentally involved in this case. Each of the construction contracts contained the same provisions as those set forth below from contract No. MA/MSB-19, differing only in the amount of subsidy per vessel and the percentage for changes determined by the Board to be eligible for subsidy:

* * * * * *
ARTICLE IV. Payment of Contract Price. (a) Progress payments on account of the Contract Price, adjusted as herein provided, shall be made to the Contractor by the Owner and the Board as the Contract work progresses. * * * Such progress payments shall be made at monthly intervals or at such other intervals as the parties agree and as follows:
(i) The Board shall pay the Contractor forty-nine and eight-tenths percent (49.8%) and the Owner shall pay the Contractor fifty and two-tenths percent (50.2%) of that portion of each progress payment on account of the Contract Price set out in Article I(a) hereof (excluding, however, the sum of Three Thousand Three Hundred and Sixty Dollars ($3,360) of the Contract Price for the National Defense Features incorporated in the Vessels).
(ii) The Board shall pay the Contractor forty-nine and eight-tenths percent (49.8%) and the Owner shall pay the Contractor fifty and two-tenths percent (50.2%) of that portion of each progress payment on account of the net increase in Contract Price, pursuant to Article 4 of the General Provisions, for changes in the contract work approved by the Board as eligible for construction-differential subsidy; provided, however, in the event there is a net decrease in the Contract Price on account of such changes, the amounts otherwise payable by the Owner and the Board pursuant to this Article IV shall be reduced by the respective percentages of such net decrease.
* * * * * *
(v) The Owner shall pay the Contractor one hundred percent (100%) of that portion of each progress payment covering increases in the Contract Price pursuant to Article 4 of the General Provisions hereof on account of changes of the Owner approved by the Board but not approved as eligible for construction-differential subsidy; provided, however, in the event there is a decrease in the Contract Price on account of such changes, the amounts otherwise payable by the Owner shall be reduced by the amount of such decrease.3
* * * * * *

The contractor is not a party to this suit. When the dispute arose between the plaintiff and the Board, an agreement was signed between them to the effect that the plaintiff would make payments to the contractor in excess of the amounts which plaintiff contends should be paid by it and that the making of such payments should be without prejudice to the rights of the plaintiff to assert its contention in court to recover from the United States the amounts which the plaintiff claims it is entitled to as subsidy for the changes involved in this case. Consequently, we are not required to determine any rights which the contractor may have had with respect to these construction contracts. However, the pertinent provisions of such contracts, which are quoted above, are included here so that the whole picture may be presented with respect to the claim of the plaintiff for subsidy payments arising out of the changes in its vessels described above.

Each of the three construction-differential subsidy contracts contained provisions that are pertinent to this case which are the same as those set forth below from contract No. MA/MSB-20, differing only in the amount of subsidy per vessel and the percentage for changes determined by the Board to be eligible for subsidy:4

* * * * * *
ARTICLE 1. Grant of Construction-Differential Subsidy. (a) The Board grants, in compliance with the provisions of Sections 501 and 502 of the Act, a construction-differential subsidy to aid in the construction of the Vessels by the Owner in the total sum of the following:
(i) A sum of $5,002,073 per Vessel which is the dollar difference between (a) the Board\'s final determination of the estimated fair and reasonable price of $5,037,000 for constructing each of the Vessels in West Germany (exclusive of the national defense features) and (b) the fixed price bid of $10,039,073 of the Avondale Shipyards, Inc. for the construction of each of the Vessels (exclusive of the national defense features).
(ii) A sum which shall be equal to 49.8% of the net increase in the Contract Price under Contract No. MA/MSB-19 for changes in the contract work pursuant to Article 4 of the General Provisions thereof (exclusive of changes in the national defense features, and exclusive of changes of the Owner approved by the Board as ineligible for construction-differential subsidy) approved by the Board as eligible for construction-differential subsidy and if there shall be a net decrease in the Contract Price on account of changes in the contract work (exclusive of changes of the Owner approved by the Board as ineligible for construction-differential subsidy) the construction-differential subsidy granted by the Board pursuant to this Article 1(a) shall be reduced by 49.8% of said net decrease.
* * * * * *
ARTICLE 2. Board\'s Payment of Construction-Differential Subsidy and the Cost of National Defense Features. (a) The Board agrees to pay the Shipbuilder under the provisions of Contract No. MA/MSB-19, 49.8% of that portion of each progress payment on account of the Contract Price set out in Article I(a) of the Special Provisions of Contract No. MA/MSB-19 (excluding the sum of $3,360 which sum covers the national defense features\' portion of the Contract Price).
(b) The Board agrees to pay the Shipbuilder 49.8% of that portion of each progress payment on account of the net increases in such Contract Price pursuant to Article 4 of the General Provisions of Contract No. MA/MSB-19 on account of changes in the contract work, approved by the Board as eligible for construction-differential subsidy, and in the event of a net decrease on account of changes deleting subsidized work the payments to be made by the Board as provided in (a) above shall be reduced by 49.8% of such net decrease.
* * * * * *

It will be observed from the foregoing provisions of the subsidy contracts that Article 1(a) (1) obligated the United States to pay a grant equal to the dollar difference between established foreign costs for building comparable ships and the cost of building the ships in the United States. These differentials were reflected in...

To continue reading

Request your trial
7 cases
  • Community Heating & Plumbing Co., Inc. v. Kelso
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • March 11, 1993
    ...of Community's contract interpretation, the Navy is bound to that interpretation by its failure to object. Lykes-Youngstown Corp. v. United States, 420 F.2d 735, 190 Ct.Cl. 348, cert. denied, 400 U.S. 865, 91 S.Ct. 102, 27 L.Ed.2d 104 (1970); Maxwell Dynamometer Co. v. United States, 386 F.......
  • FARRELL LINES INCORPORATED v. United States, 42-72.
    • United States
    • U.S. Claims Court
    • June 19, 1974
    ...our decisions in Sun Shipbuilding & Dry Dock Co. v. United States, 183 Ct.Cl. 358, 393 F.2d 807 (1968) and Lykes-Youngstown Corp. v. United States, 190 Ct.Cl. 348, 420 F.2d 735 (1970), cert. denied, 400 U.S. 865, defendant maintains that plaintiff is bound by the Board's interpretation of t......
  • LOCKHEED AIRCRAFT CORPORATION v. United States
    • United States
    • U.S. Claims Court
    • May 15, 1970
    ...knowing the meaning put upon a provision by his opposite number, he is bound by that interpretation. See Lykes-Youngstown Corp. v. United States, 420 F.2d 735, 743-744, 190 Ct.Cl. 348, — (Jan. 1970); Sun Shipbuilding & Dry Dock Co. v. United States, 393 F.2d 807, 817-818, 183 Ct.Cl. 358, 37......
  • Sun Shipbuilding & Dry Dock Co. v. United States, 756-71.
    • United States
    • U.S. Claims Court
    • June 16, 1972
    ...183 Ct.Cl. 358 (1968); Moore-McCormack Lines, Inc. v. United States, 413 F.2d 568, 188 Ct.Cl. 644 (1969); Lykes-Youngstown Corp. v. United States, 420 F.2d 735, 190 Ct.Cl. 348, cert. denied, 400 U.S. 865, 91 S.Ct. 102, 27 L.Ed.2d 104 2 The percentage of payment was divided differently betwe......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT