Craddock v. Greenhut Construction Company

Citation423 F.2d 111
Decision Date09 March 1970
Docket NumberNo. 27782.,27782.
PartiesG. H. CRADDOCK, d/b/a Southern Heat Pump Company, Plaintiff-Appellant, v. GREENHUT CONSTRUCTION COMPANY, Inc., Defendant-Appellee.
CourtUnited States Courts of Appeals. United States Court of Appeals (5th Circuit)

Alan H. Rosenbloum, Pensacola, Fla., Thomas F. Johnston, Memphis, Tenn., for appellant.

Gordon W. Wells, Gerald L. Brown, E. N. Stephens, Jr., Pensacola, Fla., for appellee.

Before WISDOM, GEWIN and AINSWORTH, Circuit Judges.

GEWIN, Circuit Judge:

Appellant, G. H. Craddock, d/b/a Southern Heat Pump Company, brought an action in the United States District Court for the Northern District of Florida against appellee, Greenhut Construction Company, Inc., for breach of contract to employ Craddock as a subcontractor on a construction project.1 This appeal is taken from an order of the district court granting Greenhut's motion for summary judgment. We reverse.

The controversy arises from Craddock's thwarted efforts to obtain the subcontract for the heating and air-conditioning of 300 housing units to be constructed at Eglin Air Force Base, Pensacola, Florida. Craddock is a mechanical contractor. For the five years immediately prior to the critical events, he was primarily engaged in construction work in the Panama Canal Zone. While between jobs in Panama, Craddock came to the States in search of work. He met Dudley Greenhut, appellee's president, in Charleston, South Carolina, where both had come to bid on another government project. There they discussed Greenhut's plan to submit a bid for the general contract for the forthcoming Eglin project, and it was agreed that Craddock would furnish Greenhut with a bid for the heating and air-conditioning portion of the work.

On 21 June 1967, Craddock sent Greenhut a bid of $322,500.00 not including the cost of a payment and performance bond. A second bid letter dated 17 July 1967 quoted the lump sum of $328,000.00 including the cost of acquiring the bond. Greenhut used Craddock's June 21 bid plus the normal cost of a bond in preparing its bid on the general contract. On 20 July 1967, Craddock sought and obtained a letter from Greenhut which provided in part:

We wish to advise, at this time, that in the event that we are awarded the above subject contract, that we will award you a contract covering Section 28, HEATING AND AIR CONDITIONING, as outlined in your letter of June 21, 1967, providing that we are furnished with a Performance Bond two (2) weeks thereafter. This bond must be furnished with good and sufficient surety or securities acceptable to the General Contractor and the Government.

On 8 August 1967, Greenhut was awarded the general contract for the Eglin project. It informed Craddock, by means of a letter from its president dated 12 August 1967, that unless it received the performance bond by 17 August 1967 it would "of necessity consider the matter closed." Craddock received this letter on 15 August 1967, and replied by a letter bearing that date. Craddock referred to the Greenhut letter of 20 July 1967, and reaffirmed his intention to comply with its terms. In reference to the letter of 12 August, he stated that he would do his best to expedite the bonding procedure. On 15 August 1967, Greenhut sent Craddock a telegram noting that it had been requested by the government to furnish the name of the mechanical subcontractor and stating:

Due to your inability to furnish a performance and payment bond, which we have requested from you several times, we deem it necessary to consider another source for the project.

The bonding company that Craddock had previously used was not licensed to issue bonds in the United States. Consequently, Craddock had been negotiating with Fidelity & Deposit Company of Maryland for the payment and performance bond. On 16 August 1967, an agent of this company called Dudley Greenhut and informed him that Fidelity & Deposit was prepared to issue a bond for Craddock. Greenhut stated that it would be unnecessary to furnish the bond, since Greenhut was obtaining another subcontractor for the project.

Craddock, through his counsel, sought a clarification of the situation by a letter of 22 August 1967. Greenhut received the letter but made no response. Subsequently, Craddock filed suit alleging breach of contract. Greenhut denied the existence of a contract and counterclaimed for the additional cost of the subcontractor who replaced Craddock.2 Both parties filed motions for summary judgment.

The court determined that Greenhut's letter of 20 July 1967 was a rejection of the offers embodied in Craddock's bid letters, and a counteroffer to Craddock. This counteroffer was found to call for acceptance by the act of furnishing an acceptable performance bond. The manifestations by Craddock of his intention to furnish the bond were held insufficient to form a contract since the terms of the offer required the act itself. By the court's reasoning, Greenhut was free to withdraw its offer, and did withdraw it prior to effective acceptance.

Craddock contends that the court erred in classifying the parties' dealings as an abortive unilateral contract. Quite to the contrary, he argues that the circumstances clearly reveal a bilateral agreement to which the obtaining of a performance bond was a condition subsequent.

In determining that Greenhut's offer contemplated a unilateral contract, the district court cited Ballou v. Campbell,3 as announcing rules which were dispositive. In Ballou, the plaintiff alleged that a shareholder of a failing corporation had promised to give all his capital stock to the plaintiff if he would take over management of the corporation and make it financially successful. Plaintiff allegedly accomplished the corporate rejuvenation and sued the estate of the since-deceased shareholder for specific performance. Faced with a classic unilateral contract, the court was primarily concerned with questions of consideration and mutuality. While Ballou is relevant for its citation of the definition of "unilateral" and "bilateral" contracts found in the Restatement of Contracts,4 it is of little help in resolving the precise issue of the present case.

The parties are in agreement that the district court properly determined Greenhut's 20 July 1967 letter to be a rejection of the offer in Craddock's bid letters. The wisdom of this concession is borne out by the Florida cases requiring strict conformity to an offer to accomplish an effective acceptance.5 There is also agreement that the Greenhut letter constituted a counteroffer to Craddock. The controversy centers on the interpretation of this counteroffer. The precise issue is whether the phrase, "providing that we are furnished with a Performance Bond two (2) weeks thereafter," constituted the exclusive means for accepting the offer, or expressed a condition subsequent modifying Greenhut's obligation to award the subcontract.

We deem neither interpretation of the phrase to be patently required by the language of the letter. Its wording lies somewhere between the clearest expression of either intention. In this situation, we consider the application of two canons of construction appropriate. § 31 of the Restatement of Contracts provides:

In case of doubt it is presumed that an offer invites the formation of a bilateral contract by an acceptance amounting in effect to a promise by the offeree to perform what the offer requests, rather than the formation of one or more unilateral contracts by actual performance on the part of the offeree.6

The expression of a similar position by one commentator explains the policy behind the presumption:

Whenever possible * * * a court would and should interpret an offer as contemplating a bilateral rather than a unilateral contract, since in a bilateral contract both parties are protected from a period prior to the beginning of performance on either side.7

A second guidepost for resolution of such a doubtful situation requires that unclear language be resolved against the draftsman or the party for whose...

To continue reading

Request your trial
17 cases
  • Bonar v. Barnett Bank of Jacksonville, NA
    • United States
    • U.S. District Court — Middle District of Florida
    • March 31, 1980
    ...of a contract is ambiguous or doubtful, it should be construed against the party who drafted the contract. Craddock v. Greenhut Construction Co., 423 F.2d 111 (5th Cir. 1970); Union Century Life Ins. Co. v. Neuhoff, 157 Fla. 98, 24 So.2d 906 (1946); MacIntyre v. Green's Pool Service, 347 So......
  • O'HARE v. General Marine Transport Corp.
    • United States
    • U.S. District Court — Southern District of New York
    • March 31, 1983
    ...then the other party need no longer satisfy the conditions that might otherwise be required of it. See Craddock v. Greenhut Construction Co., 423 F.2d 111 (5th Cir. 1970); Allegheny Valley Brick Co. v. C.W. Raymond Co., 219 F. 477 (2d Cir.1914); Commercial Metals Co. v. International Union ......
  • Caisse Nationale de Credit Agricole v. CBI Industries, Inc.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (7th Circuit)
    • August 20, 1996
    ...would amount to a "useless gesture") (citing 2 Corbin on Contracts § 1266, p. 442 (C. Kaufman Supp.1984)); Craddock v. Greenhut Construction Co., 423 F.2d 111, 115 (5th Cir.1970) (under Florida law, contractual condition excused where it "was a useless gesture"). In light of the forthright ......
  • Wolff & Munier, Inc. v. Whiting-Turner Contracting Co.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (2nd Circuit)
    • October 15, 1991
    ...F.2d 219, 232 (9th Cir.1989) (citing 2 Corbin on Contracts § 1266, at 442 (C. Kaufman Supp.1984)); see also Craddock v. Greenhut Constr. Co., Inc., 423 F.2d 111, 115 (5th Cir.1970) (contractual condition excused where it "was a useless gesture") (applying Florida law). New York is in accord......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT