Henry C. Beck Co. v. Ross Island Sand & Gravel Co.

Decision Date24 March 1972
Docket NumberNo. 25302.,25302.
PartiesHENRY C. BECK COMPANY, a corporation, and Utah Construction & Mining Co., a corporation, doing business as Beck-Utah, a Joint Venture, Plaintiffs and Appellants, v. ROSS ISLAND SAND & GRAVEL CO., a corporation, Defendant and Appellee.
CourtU.S. Court of Appeals — Ninth Circuit

COPYRIGHT MATERIAL OMITTED

Carl R. Neil (argued), of Lindsay, Nahstoll, Hart, Duncan, Dafoe & Krause, Portland, Oregon, for plaintiffs-appellants.

James H. Clarke (argued), George L. Kirklin, of McColloch, Dezendorf, Spears & Lubersky, Portland, Or., for defendant-appellee.

Before CHAMBERS, CARTER and WRIGHT, Circuit Judges.

JAMES M. CARTER, Circuit Judge.

This damage suit for breach of contract was tried to the court without a jury. It resulted in a judgment for defendant-appellee, hereafter Ross Island.

The appellant (hereafter Beck), raises the following questions:

(1) Did the trial court err in Finding of Fact XI and Conclusion of Law I that the Standard Specifications for Ready Mix Concrete, C94, was made applicable to the concrete here in question by the specifications in the construction contract between Beck and the owner of the building?

(2) Was ASTM C94, 1967 edition, improperly relied upon by the trial court?

(3) As to the sufficiency of the evidence and the court's findings, Beck contends the concrete, supplied by Ross Island, failed to meet compressive strength standards. As to these findings, three claims are made by Beck as to the lack of compressive strength:

(a) as to Class B-1 concrete delivered July 6, 1966, and placed in the floor slab of the north wing of the fifth floor;
(b) as to Class A-1 concrete delivered on July 8, 1966, and placed in four girders of the south wing of the fourth floor;
(c) as to Class B-1 concrete delivered July 8, 1966, and placed in the floor slab of the fourth floor.
I Finding XI and Conclusion I

Beck attacks Finding of Fact XI stating that the standards of ASTM "Standard Specifications for Ready Mix Concrete, C94" were made applicable to the concrete in question by the "construction contract specifications." Attack is also made on Conclusion of Law I referring to the same contract as the "construction contract between plaintiffs and the building owner." Beck points out that none of the contract between Beck and the building owner was incorporated into the contract between Beck and Ross Island; that the contract between Beck and Ross Island consisted solely of the purchase order dated December 30, 1965, which was Exhibit "B" to the pre-trial order, and only required that Class B-1 concrete achieve a compressive strength of 3,000 psi at 28 days after pour.

We think that Beck is correct in that the court was mistaken in its reference to the construction contract between Beck and the owner of the building and that there was nothing in the purchase order, Exhibit "B" to the pretrial order, which made reference to the standards of ASTM. However, we think there was no error in this respect and that the contention is an after-thought on the part of Beck.

Our reasons are as follows:

The contention was never raised at any time until the filing of Beck's opening brief. In the motion for new trial, etc., Beck's counsel, Mr. Nahstoll, stated that the 1964 edition of ASTM C94 "was the edition applicable to the terms of this contract;" and Mr. Nahstoll stated in his affidavit supporting his motion for a new trial as follows: "The 1964 edition of ASTM-C94 which was in effect and applicable to the contract between plaintiff and defendant during the time the defective concrete complained of in this case was supplied by the defendant. . . ." Beck also offered in evidence certain portions of ASTM C94.

Thus, even in the motion for a new trial the contention was not raised and was raised for the first time in Beck's opening brief. The parties having tried the case as if ASTM C94 was part of the specifications to be followed, Beck may not now raise this contention on appeal.

II The use of ASTM C94, 1967 Edition

The concrete was poured in July 1966. The trial court relied on ASTM C94, 1967 edition. However, the fact that it was a 1967 edition was not brought to the trial court's attention until raised by appellant on motion for a new trial.

The 1967 edition was used in the trial, and although apparently no date appeared on it, appellant's counsel could have ascertained its date. In fact, appellant placed part of ASTM C94, 1967 edition, in evidence.

The motion for a new trial, etc. set forth the 1964 and 1967 editions of ASTM C94 and was supported by counsel's affidavit that after trial he had ascertained that a 1967 edition had been used and relied upon.

The question of whether the 1964 edition was newly discovered evidence within the well-known rule, and a new trial should have been granted, was one for the court's discretion. We find no abuse thereof.

III

The concrete delivered to the fifth floor

The claim as to the fifth floor was for "delay damages." The concrete was not replaced. Beck ceased work after a 7-day test. It contends that the concrete did not harden until 42 days, instead of 28 days called for in the contract.

We hold that there was sufficient evidence to support the trial court's findings that the Class B-1 concrete poured on the fifth floor satisfied the compressive strength requirements of the purchase order.

Moreover, correspondence beginning August 31, 1966 and invoices from appellant to October 26, 1967, which purported to contain an itemization of Beck's damages, made no reference to the fifth floor. The complaint filed December 5, 1967, makes no claim for the fifth floor. The claim was finally asserted in late 1968, two years and 17 depositions after the event.

IV

The class A-1 Concrete for girders on the fourth floor

The Class A-1 Concrete was delivered July 8, 1966, for the girders on the fourth floor. When the slab was determined to be defective, Beck insisted that the girders as well as the slab be removed. The girders were removed over Ross Island's objection. The girders were sound.

There was conflicting testimony as to whether the girders needed to be removed and repoured, because of a lack of bond to the steel bars on the fourth floor slab.

The trial court did not err in finding the evidence failed to establish a defect in the girders underlying the fourth floor slab, and thus impliedly finding that the bond was not defective.

V

The Class B-1 concrete in the fourth floor slab

The main thrust of appellant's argument at the hearing in this court and in its briefs involved the concrete poured in the fourth floor slab. Appellant Beck attacks the sufficiency of the trial court's findings as to the fourth floor slab. Ross Island supports the findings and contends that (1) Beck did not prove the concrete, as delivered, would not have met the 3,000 psi requirement in 28 days; (2) that if the concrete was defective, it was caused by Beck's addition of excess water; and (3) that Beck assumed the risk of the use of Pozzolith in the mix.

The purchase order provided:

"Class B-1; 3,000 psi at 28 days 3/4" aggregate, 6 sack cement with 3L poss."1

Agreed Fact No. 20 in the pretrial order reads:

"The concrete mix design for floor slabs on the Calaroga Terrace project is on page 2 of Pittsburgh Testing Laboratory letter dated October 28, 1965, a copy of which is marked Exhibit "F" and attached hereto."

Exhibit "F" lists various concrete mixtures, and states:

"These quantities will produce about a 4" `slump.\'"2

We conclude that the purchase order and Agreed Fact No. 20 provided that Ross Island agreed to supply concrete mix (1) with a compressive strength of 3,000 psi at 28 days after pour and (2) with approximately a 4" "slump."

As to the concrete in the fourth floor slab, the trial court made one general or ultimate finding, No. XXII, and several more specific findings, Nos. XVII, XIX, XX and XIII, which had a bearing on liability. We discuss each hereafter.

The sufficiency of an ultimate finding of fact, which alone may purport to decide a case, has been questioned. Federal Practice and Procedure, Rules Edition, Barron and Holtzoff, Wright; § 1127 (1961). See Kelley v. Everglades Drainage District, 319 U.S. 415, 422, 63 S.Ct. 1141, 87 L.Ed. 1485 (1943) and Official Creditor's Committee of Fox Markets, Inc. v. Ely (9 Cir. 1964) 337 F. 2d 461, 467.

We do not intend to retry the case or to undermine the well-accepted rule in this circuit that findings of fact by trial courts in civil cases will not be set aside unless clearly erroneous.

We recognize that "if the findings are sufficient to support the ultimate conclusion of the court they are sufficient . . . . The ultimate test as to the adequacy of findings will always be whether they are sufficiently comprehensive and pertinent to the issues to provide a basis for decision and whether they are supported by the evidence." Rayonier Inc. v. Polson (9 Cir. 1968) 400 F.2d 909, 923.

We may set aside findings, even if there is some evidence to support them, if we have a firm conviction that a mistake has been made. Where a case is tried to a court without a jury, "A finding is `clearly erroneous' when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed." United States v. United States Gypsum Co., 333 U.S. 364, 395, 68 S.Ct. 525, 542, 92 L.Ed. 746 (1948). Accord: Smith v. James Irvine Foundation (9 Cir. 1968) 402 F.2d 772.

We think that the nature of the findings as to the fourth floor slab requires a reversal as to this part of the decision. Accordingly, we reverse that portion of the judgment and remand for a new trial.

Facts Proven

Fifty cubic yards of Class B-1 concrete was delivered by Ross Island for the fourth floor slab on July 8, 1966. Each truck load carried 7 to 8 cubic yards of concrete. The...

To continue reading

Request your trial
3 cases
  • McCune v. F. Alioto Fish Co.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • May 30, 1979
    ...520 F.2d 608, 613-14 (9th Cir. 1975); Handeland v. Commissioner, 519 F.2d 327, 329 (9th Cir. 1975); Henry C. Beck Co. v. Ross Island Sand & Gravel Co., 456 F.2d 316, 320 (9th Cir. 1972); Rayonier, Inc. v. Polson, 400 F.2d at 923; Dale Benz, Inc. v. American Casualty Co., 303 F.2d 80, 82 (9t......
  • Ross Island Sand & Gravel Co. v. General Ins. Co. of Amer.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • January 4, 1973
    ...of California, sitting by designation. 1 The final disposition of that litigation is reported in Henry C. Beck Co. v. Ross Island Sand & Gravel Co., 456 F.2d 316 (9th Cir. 1972). 2 But where the allegation is sham or frivolous, as where a defendant has already been convicted of a willful as......
  • Handeland v. C. I. R.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • June 23, 1975
    ...they are supported by the evidence." Rayonier, Inc. v. Polson (9 Cir. 1968) 400 F.2d 909, 923. Henry C. Beck Co. v. Ross Island Sand & Gravel Co., 456 F.2d 316, 320 (9th Cir. 1972). This court has held that when the Commissioner has admitted an issue in his answer, "the Tax Court was bound ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT