46 Cal.2d 588, 23369, Van Meter v. Bent Construction Co.

Docket Number23369
Citation46 Cal.2d 588,297 P.2d 644
Date01 June 1956
PartiesVan Meter v. Bent Construction Co.
CourtCalifornia Supreme Court

Page 588

46 Cal.2d 588

297 P.2d 644

MORRIS S. VAN METER, Appellant,

v.

BENT CONSTRUCTION COMPANY (a Partnership) et al., Respondents.

L. A. No. 23369.

Supreme Court of California

June 1, 1956

In Bank.

Page 589

COUNSEL

Higgs, Fletcher &amp Mack and Ferdinand T. Fletcher for Appellant.

Procopio, Price, Cory &amp Schwartz, Hill, Farrer &amp Burrill, Alec L. Cory and Stanley S. Burrill for Respondents.

Page 590

OPINION

GIBSON, C.J.

Defendants contracted with the city of San Diego to construct a dam and remove brush and trees from the reservoir basin, and thereafter they entered into a subcontract with plaintiff for clearance of the basin, representing to him that the area to be cleared had been marked with flags. Plaintiff later discovered that the flagged area covered only a part of the reservoir basin, and he notified defendants that unless some adjustment was made he would not proceed with the work. It was then agreed that plaintiff should clear the entire basin without prejudice to his rights under the subcontract. Upon completion of the work he brought this action seeking, in separate counts, a declaration of rights, reformation of the subcontract, recovery of the reasonable value of services performed, and damages for false representations.

Certain issues were submitted to a jury on special interrogatories, and its answers were supplemented by findings of the court. It was found that defendants made false representations believing them to be true and that plaintiff relied on the misrepresentations and failed to use reasonable care in ascertaining the extent of the area to be cleared. The court concluded that, because the fraud perpetrated by defendants was not wilful, plaintiff's negligence precluded him from obtaining any relief. He has appealed from the ensuing judgment contending that the finding that he was negligent is not supported by the evidence and that the judgment is not supported by the findings. 1

The provisions of the general contract between the city and defendants relating to clearance of the reservoir basin are found in section H of Specification Number 9--Sutherland Dam, under the designation "H-01 Clearing." Insofar as material here, the section states that "The reservoir basin shall be cleared below elevation 2073. The contour 2073 will be flagged by City forces during the bidding period and the Bidder shall make visual observation before submitting bid. The area of the basin is about one square mile, horizontal measurement." The contract, which is in book form, consists of 110 typewritten pages, including the table of contents, and 27 folded pages at the back of the book containing drawings and maps. One of the maps is entitled "Sutherland Dam Area to be Cleared and City Camp." This map, which is not referred to in the table of contents or in section H,

Page 591

shows elevation contour 2073 enclosing an area irregular in shape consisting of two basins joined by a narrow neck. The Santa Ysabel Creek runs west through the upper basin, turns at the narrow neck and flows north through the lower basin. The upper basin, which is long and narrow, contains approximately 220 acres. The lower basin covers approximately 420 acres and is nearly as broad as it is long. The dam site is shown on the map as being located at the north end of the lower basin, and the map contains a notation on the lower basin area: "Contractor shall clear area below contour 2073 about (1) sq. mile."

Mr. Daley, a representative of defendants, asked plaintiff to submit a bid for removing trees and brush and showed him a copy of the contract, calling his attention to section H. Together they read the provisions dealing with the clearance of the reservoir basin, and Daley told plaintiff that the area to be cleared had been flagged by the city and that it was the area on which he was to bid. Plaintiff kept the copy of the general contract and marked with a paper clip the page containing section H. Daley made no reference to the map, which, as we have seen, was not mentioned in section H or listed in the table of contents, and plaintiff did not see it until after he had commenced work. When plaintiff examined the area prior to making his bid he found that flags had been placed in the lower basin along contour 2073. He looked for additional flags but found none, and it is undisputed that no flags had then been placed in the upper basin.

Plaintiff submitted a bid in the sum of $29,750, informing defendants that he was bidding on the flagged area, and he was again told by defendants that the area to be cleared was that flagged by the city. The bid was accepted, and plaintiff executed the subcontract which states that he is familiar with the terms of the general contract and that he "agrees to perform fully and completely all that portion of the work required to be done by Contractor under the General Contract which is hereinbelow particularly described as follows: All that work named in Specification Number 9, Sutherland Dam Section H--Clearing Reservoir Basin, H-01 Clearing Bid Item No. 76."

Plaintiff commenced work about August 1, 1952, and early in September he was informed by a city employee that a larger area than the one flagged was to be cleared. Shortly thereafter the city placed flags in the upper basin. Plaintiff notified defendants that he had learned that all of the area had

Page 592

not been flagged during the bidding period as required by section H of the general contract, that he had made his bid on the assumption that the flags marked the boundary of the area to be cleared, and that unless defendants made an adjustment he would stop work on October 1. The parties then agreed that plaintiff should complete the clearance of the entire reservoir basin without prejudice to their rights under the subcontract.

Evidence as to the amount of damages was deferred until determination of liability, and only a prima facie case as to costs and values was presented. Defendants' bid for constructing the dam and clearing the reservoir basin was $2,896,485, which included an estimated profit of $267,707.66. In their bid defendants listed $116,500 for clearing the reservoir area, but their accountant testified that $89,350 was included in that item to cover part of...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT