460 F.3d 470 (3rd Cir. 2006), 04-3936, Morton Intern., Inc. v. A.E. Staley Mfg. Co.
Citation | 460 F.3d 470 |
Party Name | MORTON INTERNATIONAL, Inc.; Velsicol Chemical Corporation; NWI Land Management Co.; Fruit of the Loom, Incorporated v. A.E. STALEY MANUFACTURING COMPANY; Airco Industrial Gases, f/k/a Airco Inc, a/k/a Air Reduction Company, Inc; Allied Chemical Corporation; Aluminum Company of America, (ALCOA); American Cyanamid Company; Armstrong World Industries; |
Case Date | August 18, 2006 |
Court | United States Courts of Appeals, U.S. Court of Appeals — Third Circuit |
Page 470
Argued June 7, 2006.
Page 471
[Copyrighted Material Omitted]
Page 472
[Copyrighted Material Omitted]
Page 473
Kim Hoyt Sperduto (argued), T. Stewart Rauch, The Sperduto Law Firm, Washington, DC, Steven M. Richman, Sandra A. Jeskie, Duane Morris, Hamilton, NJ, Attorneys for Appellee.
Samuel P. Moulthrop (argued), Alexa Richman-La Londe, Andrew M. Contreras, Riker, Danzig, Scherer, Hyland & Perretti, Morristown, NJ, Robert A. Lonergan, Vice President and General Counsel, Ellen S. Friedell, Associate General Counsel, Philadelphia, PA, Attorneys for Appellant.
Before AMBRO, FUENTES, and GREENBERG, Circuit Judges.
OPINION
GREENBERG, Circuit Judge.
I. INTRODUCTION
This matter comes on before the court on an appeal by Morton International, Inc. ("Morton") from the district court's order entered on March 30, 1999, dismissing Morton's contribution claim against Redland Minerals, Ltd. ("RML") for want of personal jurisdiction. The contribution action succeeded a state court proceeding in which the court found Morton and various other entities jointly and severally liable for mercury contamination in the area of Berry's Creek in Bergen County, New Jersey. Morton later filed an action against RML and other defendants seeking contribution. The district court dismissed RML from the action for want of personal jurisdiction on March 30, 1999, and granted summary judgment to another defendant, Tennessee Gas Pipeline Company ("Tenneco"), on July 23, 2001. Thereafter, with the remaining parties' consent and at their request, the court dismissed the case without prejudice as to the remaining defendants on October 23, 2001. Morton subsequently appealed from the July 23, 2001 order, and after we vacated that order on September 16, 2003, and remanded the case against Tenneco to the district court, that court on September 14, 2004, dismissed the action against Tenneco
Page 474
without prejudice. Then, on October 6, 2004, Morton filed an appeal from the order of March 30, 1999, dismissing the action against RML. 1 RML has filed a motion to dismiss the appeal for lack of appellate jurisdiction. We will grant RML's motion to dismiss because we lack jurisdiction over Morton's premature appeal.
II. FACTS AND PROCEDURAL HISTORY
In 1976, the New Jersey Department of Environmental Protection ("DEP") commenced an enforcement action in the Superior Court of New Jersey against various entities as a result of contamination in the Berry's Creek area. 2 The DEP was successful in the action, and, on the ensuing appeal the Supreme Court of New Jersey in 1983 affirmed a Superior Court order requiring those entities, including Morton, to remediate the contamination in the Berry's Creek area. See Dep't of Envtl. Prot. v. Ventron Corp., 94 N.J. 473, 468 A.2d 150 (1983). In 1996, Morton, which is the successor in interest to Ventron Corporation, a defendant in the state case, filed this action seeking contribution for its damages arising out of the Ventron litigation from RML and numerous other defendants under the Comprehensive Environmental Response, Compensation, and Liability Act ("CERCLA"), 42 U.S.C. § 9601 et seq.; the Resource Conservation and Recovery Act of 1976 ("RCRA"), Pub.L. No. 94-580, 90 Stat. 2795 (1976), as amended 42 U.S.C. § 6901 et seq.; the New Jersey Spill Compensation and Control Act, N.J. Stat. Ann. § 58:10-23.11 et seq. (West 1992); the Declaratory Judgment Act, 28 U.S.C. § 2201 et seq.; and the common law. 3 RML, which formerly was known as F.W. Berk & Co., Ltd. ("Berk U.K."), was the British parent corporation of the former F.W. Berk & Company, Inc. ("Berk U.S."). According to Morton, RML was liable for contribution based on Berk U.S.'s operation of a manufacturing facility from 1929 to the 1950s "which ... continued to result in the handling, storage, treatment, transportation, disposal, and/or release of solid and/or hazardous wastes ... around the Berry's Creek area." J.A. at 102-03. 4
On March 13, 1997, RML filed a motion in the district court seeking to dismiss Morton's contribution claim against it for lack of personal jurisdiction. The parties engaged in discovery on the jurisdictional issue following which, as we have indicated, on March 30, 1999, the court granted RML's motion ("RML Dismissal Order"). 5
Page 475
At that time Morton did not file a motion seeking an order certifying the RML Dismissal Order as final and appealable pursuant to Fed.R.Civ.P. 54(b) ("Rule 54(b)"), and it has not done so since. As we also have indicated, on July 23, 2001, the district court entered summary judgment in favor of defendant Tenneco and dismissed Morton's complaint as to Tenneco ("2001 Tenneco Order"). Then, on October 23, 2001, the court entered the consent order dismissing the action without prejudice as to the remaining defendants ("2001 Dismissal Order"). 6 As of October 23, 2001, the court had dismissed the action as to RML for lack of jurisdiction, granted Tenneco summary judgment on the merits, and dismissed the action without prejudice against the remaining defendants by consent. Thus, as there were no remaining defendants, the court on October 25, 2001, marked the case "closed" on the docket. Nevertheless on October 29, 2001, at Morton's request in a motion it filed before the entry of the 2001 Dismissal Order, the district court entered an order certifying the 2001 Tenneco Order as final and appealable pursuant to Rule 54(b).
On November 27, 2001, Morton filed an appeal from the 2001 Tenneco Order ("Tenneco Appeal"). On September 16, 2003, we vacated the 2001 Tenneco Order and remanded the case for further proceedings. Morton Int'l, Inc. v. A.E. Staley Mfg. Co., 343 F.3d 669 (3d Cir.2003). On remand on September 14, 2004, the district court entered a stipulation and agreed order of voluntary dismissal without prejudice between Morton and Tenneco ("2004 Tenneco Order"). The 2004 Tenneco Order was nearly identical...