Duquesne Light Company v. Barasch

Decision Date11 January 1989
Docket NumberNo. 87-1160,87-1160
Citation109 S.Ct. 609,488 U.S. 299,102 L.Ed.2d 646
PartiesDUQUESNE LIGHT COMPANY and Pennsylvania Power Company, Appellants v. David M. BARASCH, etc., et al
CourtU.S. Supreme Court
Syllabus

In 1967, appellant Pennsylvania electric utilities joined a venture to construct seven nuclear generating units. But in 1980, because of intervening events, including the Arab oil embargo and the accident at Three Mile Island, the participants canceled plans for construction of four of the plants. Thereafter appellant Duquesne Light Co. applied to the Pennsylvania Public Utility Commission (PUC) to obtain a rate increase and to amortize its expenditures on the canceled plants over 10 years. The PUC granted a rate increase that included an amount representing the first payment of the 10-year amortized recovery of Duquesne's costs in the aborted plants. Shortly before the close of the rate proceeding, a state law (Act 335) was enacted that provided that an electric utility's cost of construction of a generating facility shall not be made part of a rate base nor otherwise included in rates charged until such time as the facility "is used and useful in service to the public." The State Office of the Consumer Advocate moved the PUC to reconsider in light of this law, but the PUC on reconsideration affirmed its original rate order, reading the new law as excluding the costs of canceled plants from the rate base, but not as preventing their recovery through amortization. Meanwhile, the PUC similarly granted appellant Pennsylvania Power Co. a rate increase and authorized it to amortize its share of the canceled plants over a 10-year period. The Consumer Advocate appealed both PUC decisions to the Pennsylvania Commonwealth Court, which held that the PUC had correctly construed Act 335. The Pennsylvania Supreme Court reversed, holding that Act 335 prohibited recovery of the costs in question either by inclusion in the rate base or by amortization, and that the statute did not take appellants' property in violation of the Takings Clause of the Fifth Amendment, applicable to the States under the Fourteenth Amendment. The court remanded the case to the PUC for further proceedings to correct its rate orders, giving effect to the exclusion required by Act 335.

Held:

1. This Court has jurisdiction to decide the case under 28 U.S.C. § 1257(2), which authorizes the Court to review by appeal "[f]inal judgments . . . rendered by the highest court of a State in which a decision could be had . . . where is drawn in question the validity of a statute of any state on the ground of its being repugnant to the Constitution and the decision is in favor of its validity." Although the Pennsylvania Supreme Court remanded the case for further proceedings to revise the rate orders, that court's judgment is final for purposes of this Court's appellate jurisdiction. The state court's last word on Act 335's constitutionality has been presented, and all that remains is the straight-forward application of its clear directive to otherwise complete rate orders. Pp. 306-307.

2. A state scheme of utility regulation, such as is involved here, does not "take" property simply because it disallows recovery of capital investments that are not "used and useful in service to the public." Pp. 307-316.

(a) Under the "prudent investment" or "historical cost" rule, a utility is compensated for all prudent investments at their actual cost when made (their "historical" cost), irrespective of whether individual investments are deemed necessary or beneficial in hindsight. It was ruled in FPC v. Hope Natural Gas Co., 320 U.S. 591, 64 S.Ct. 281, 88 L.Ed. 333, that historical cost was a valid basis on which to calculate utility compensation. Pp. 307-312.

(b) The Constitution does not require that subsidiary aspects of Pennsylvania's ratemaking methodology be examined piecemeal, as appellants argue. State legislatures are competent bodies to set utility rates, and the PUC is essentially an administrative arm of the legislature. Similarly, an otherwise reasonable rate is not subject to constitutional attack by questioning the theoretical consistency of the method that produced it, as appellants do here by noting Act 335's theoretical inconsistency in suddenly and selectively applying the "used and useful requirement," normally associated with the fair value method of ratesetting, in the context of Pennsylvania's system based on historical costs. Pp. 313-314.

(c) In this case, at all relevant times, Pennsylvania's rate system has been predominantly but not entirely based on historical costs, and it has not been shown that the rate orders in question as modified by Act 335 failed to give a reasonable rate of return on equity given the risk under such a regime. Therefore, Act 335's limited effect on those rate orders does not result in constitutionally impermissible rates. Pp. 314-315.

(d) But adoption of the "prudent investment" rule as the single constitutional standard of valuation would be inconsistent with the view of the Constitution that this Court has taken since Hope Natural Gas and would unnecessarily foreclose alternatives that could benefit both consumers and investors. The Constitution within broad limits leaves the States free to decide what ratesetting methodology best meets their needs in balancing the interests of the utility and the public. Pp. 315—316.

516 Pa. 142, 532 A.2d 325, affirmed.

REHNQUIST, C.J., delivered the opinion of the Court, in which BRENNAN, WHITE, MARSHALL, STEVENS, O'CONNOR, SCALIA, and KENNEDY, JJ., joined. SCALIA, J., filed a concurring opinion, in which WHITE and O'CONNOR, JJ., joined, post, p. 317. BLACKMUN, J., filed a dissenting opinion, post, p. 317.

Peter Buscemi, Washington, D.C., for appellants.

Irwin A. Popowsky, Harrisburg, Pa., for appellees.

Chief Justice REHNQUIST delivered the opinion of the Court.

Pennsylvania law required that rates for electricity be fixed without consideration of a utility's expenditures for electrical generating facilities which were planned but never built, even though the expenditures were prudent and reasonable when made. The Supreme Court of Pennsylvania held that such a law did not take the utilities' property in violation of the Fifth Amendment to the United States Constitution. We agree with that conclusion, and hold that a state scheme of utility regulation does not "take" property simply because it disallows recovery of capital investments that are not "used and useful in service to the public." 66 Pa.Cons.Stat. § 1315 (Supp.1988).

I

In response to predictions of increased demand for electricity, Duquesne Light Company (Duquesne) and Pennsylvania Power Company (Penn Power) joined a venture in 1967 to build more generating capacity. The project, known as the Central Area Power Coordination Group (CAPCO), involved three other electric utilities and had as its objective the construction of seven large nuclear generating units. In 1980 the participants canceled plans for construction of four of the plants. Intervening events, including the Arab oil embargo and the accident at Three Mile Island, had radically changed the outlook both for growth in the demand for electricity and for nuclear energy as a desirable way of meeting that demand. At the time of the cancellation, Duquesne's share of the preliminary construction costs associated with the four halted plants was $34,697,389. Penn Power had invested $9,569,665.

In 1980, and again in 1981, Duquesne sought permission from the Pennsylvania Public Utility Commission (PUC) 1 to recoup its expenditures for the unbuilt plants over a 10-year period. The Commission deferred ruling on the request until it received the report from its investigation of the CAPCO construction. That report was issued in late 1982. The report found that Duquesne and Penn Power could not be faulted for initiating the construction of more nuclear generating capacity at the time they joined the CAPCO project in 1967. The projections at that time indicated a growing de- mand for electricity and a cost advantage to nuclear capacity. It also found that the intervening events which ultimately confounded the predictions could not have been predicted, and that work on the four nuclear plants was stopped at the proper time. In summing up, the Administrative Law Judge found "that the CAPCO decisions in regard to the [canceled plants] at every stage to their cancellation, were reasonable and prudent." App. to Juris. Statement 19h. He recommended that Duquesne and Penn Power be allowed to amortize their sunk costs in the project over a 10-year period. The PUC adopted the conclusions of the report. App. to Juris. Statement 1i.

In 1982, Duquesne again came before the PUC to obtain a rate increase. Again, it sought to amortize its expenditures on the canceled plants over 10 years. In January 1983, the PUC issued a final order which granted Duquesne the authority to increase its revenues $105.8 million to a total yearly revenue in excess of $800 million. Pennsylvania PUC v. Duquesne Light Co., 57 Pa.P.U.C. 1, 51 P.U.R.4th 198 (1983). The rate increase included $3.5 million in revenue representing the first payment of the 10-year amortization of Duquesne's $35 million loss in the CAPCO plants.

The Pennsylvania Office of the Consumer Advocate (Consumer Advocate) moved the PUC for reconsideration in light of a state law enacted about a month before the close of the 1982 Duquesne rate proceeding. The Act, No. 335, 1982 Pa.Laws 1473, amended the Pennsylvania Utility Code by limiting "the consideration of certain costs in the rate base." 2 It provided that "the cost of construction or expansion of a facility undertaken by a public utility producing . . . electricity shall not be made a part of the rate base nor otherwise included in the rates charged by the electric utility until such time as the facility is used and useful in service to the public." 66...

To continue reading

Request your trial
214 cases
  • Temple-Inland, Inc. v. Cook, Civ. No. 14-654-GMS
    • United States
    • U.S. District Court — District of Delaware
    • 28 Junio 2016
    ...standard is used to determine whether an unconstitutional taking of money has occurred. See Duquesne Light Co. v. Barasch , 488 U.S. 299, 307, 109 S.Ct. 609, 102 L.Ed.2d 646 (1989) (explaining that, in the field of utility rate regulation, a reasonable rate is not a taking). Accordingly, th......
  • U S West Communications, Inc. v. Tcg Oregon
    • United States
    • U.S. District Court — District of Oregon
    • 30 Enero 1998
    ...challenge individual elements of the overall rate structure. In support of that contention, TCG cites Duquesne Light Co. v. Barasch, 488 U.S. 299, 109 S.Ct. 609, 102 L.Ed.2d 646 (1989). Though a superficial reading of that decision offers some support for TCG's contention that a review must......
  • American Auto. Mfrs. Ass'n v. Cahill
    • United States
    • U.S. District Court — Northern District of New York
    • 5 Agosto 1997
    ...a reasonable rate of return on their investment in ZEVs if they are forced to abide by the ZEV sales mandate. 488 U.S. 299, 308, 109 S.Ct. 609, 616, 102 L.Ed.2d 646 (1989) (if the rate charged by a power company "does not afford sufficient compensation, the State has taken the use of utilit......
  • Fireman's Fund Ins. Co. v. Garamendi, C-91-2854-CAL
    • United States
    • U.S. District Court — Northern District of California
    • 13 Abril 1992
    ...infirmities is not then important. Id. 320 U.S. at 602, 64 S.Ct. at 287 (citations omitted). In Duquesne Light Co. v. Barasch, 488 U.S. 299, 310, 109 S.Ct. 609, 617, 102 L.Ed.2d 646 (1989), the Court "reaffirmed these teachings of Hope Natural Gas." The Court An otherwise reasonable rate is......
  • Request a trial to view additional results
10 books & journal articles
  • Restructuring and Regulation of Electric and Gas Industries
    • United States
    • ABA Antitrust Library Energy Antitrust Handbook
    • 1 Enero 2017
    ...that the method employed to reach that result may contain infirmities is not then important.”); see also Duquesne Light Co. v. Barasch, 488 U.S. 299, 300 (1989); Entergy Servs ., 58 F.E.R.C. at 61,752. 53 . Commonwealth Atl. L.P., 51 F.E.R.C. ¶ 61,368 (1990). 36 Energy Antitrust Handbook re......
  • Table of cases
    • United States
    • ABA Antitrust Library Energy Antitrust Handbook
    • 1 Enero 2017
    ...CFTC, 364 F. App’x. 657, 2009 WL 3326624 (2d Cir. 2009), cert. denied , 559 U.S. 1025 (Mar. 22, 2010), 241 Duquesne Light Co. v. Barasch, 488 U.S. 299 (1989), 35 Dynegy Mktg. & Trade, 2002 WL 31835506 (C.F.T.C. 2002), 249 E E&J Gallo Winery v. EnCana Corp., 503 F.3d 1027 (9th Cir. 2007), 20......
  • THE COMPENSATION CONSTRAINT AND THE SCOPE OF THE TAKINGS CLAUSE.
    • United States
    • Notre Dame Law Review Vol. 96 No. 4, March 2021
    • 1 Marzo 2021
    ...78 FORDHAM L. REV. 1281 (2009). (51) See Verizon Commc'ns Inc. v. FCC, 535 U.S. 467, 497 (2002); Duquesne Light Co. v. Barasch, 488 U.S. 299, 305 (52) See Verizon, 535 U.S. at 539. (53) See Duquesne, 488 U.S. at 312; Balt. & Ohio R.R. Co. v. United States, 345 U.S. 146, 148 (1953). (54)......
  • Phasing Out the Use of Fossil Fuels for the Generation of Electricity
    • United States
    • Legal pathways to deep decarbonization in the United States Part V - Electricity Decarbonization
    • 24 Marzo 2019
    ...Stranded Costs and Grid Decarbonization , 82 Brook. L. Rev. 645, 648-49 (2017). 178. Id . at 673. 179. Duquesne Light Co. v. Barasch, 488 U.S. 299 (1989). See also Market St. Ry. Co. v. Railroad Comm’n, 324 U.S. 548 (1945) (denying fare relief to Page 644 Legal Pathways to Deep Decarbonizat......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT