United States v. Home Indemnity Company

Decision Date08 November 1973
Docket NumberNo. 72-1435.,72-1435.
Citation489 F.2d 1004
PartiesUNITED STATES of America, for the Use and Benefit of MATERIAL SERVICE DIVISION OF GENERAL DYNAMICS CORPORATION, Plaintiff-Appellant, v. The HOME INDEMNITY COMPANY et al., Defendants-Appellees.
CourtU.S. Court of Appeals — Seventh Circuit

Harry M. Coven, Howard M. Turner, Chicago, Ill., for plaintiff-appellant.

Jesse H. Brown, Chicago, Ill., Harry M. Brostoff, Oak Brook, Ill., for defendants-appellees.

Before HASTINGS and MURRAH*, Senior Circuit Judges, and PELL, Circuit Judge.

MURRAH, Senior Circuit Judge.

This is an appeal from an order dismissing a Miller Act claim1 by a materialman against a general contractor and its statutory surety on the ground that the suit was not commenced within the prescribed one-year period. The Act requires the giving of written notice within 90 days and the commencement of the suit within one year of the date when the last materials were supplied. The statute is remedial and to be liberally construed, but the giving of notice and bringing of suit within the prescribed time is a condition precedent to the right to maintain the action.2

The uncontroverted facts are that Pathman Construction Company, general contractor on a federal housing project at Fort Sheridan, Illinois, subcontracted the installation of gypsum wallboard for the project to Tri-State Drywall Corporation, and Tri-State contracted to purchase the wallboard from Material Service. Under the terms of the oral agreement, Material Service was to deliver the wallboard inside the buildings under construction. Most of the wallboard was carried by rail to the railroad siding at Fort Sheridan, unloaded there by a Material Service subcontractor, and by it delivered inside the buildings at the job site. If structures were not ready for delivery, the wallboard was stored temporarily near the railroad siding and delivered as needed.

In the fall of 1966 Tri-State abandoned the Fort Sheridan project, and its Pathman subcontract, without having fully paid Material Service for the wallboard delivered. This suit was commenced after extended but unsuccessful negotiations with Pathman over the unpaid balance.

The complaint specifically alleged that the materials were sold and delivered to Tri-State between March 25 and November 21, 1966, that written notice was given to the contractor within 90 days of the delivery of materials, as provided by § 270b(a), and that the suit was brought within one year. The contractor and the surety answered separately, admitting the demand but generally denying liability. Detailed interrogatories were propounded and answered, but unfortunately no definitive pretrial order emerged, and the case came on for trial on the issues framed by the complaint and general denials.

Apparently in support of the averments of its complaint, Material Service introduced copies of two registered letters to the contractor. The first letter, dated November 2, received November 3, transmitted an itemized statement as of September 30, 1966, "setting forth total drywall material deliveries to the subject project," and the amounts received, with a balance due of $46,445.94. The letter specifically stated that it was being transmitted in accordance with the requirements of the Miller Act. The second letter, dated the following December 8, transmitted an itemized statement as of November 30, 1966, listing undated invoices of "all dry-wall material delivered" by Material Service in the execution of its contract. The November 30 statement transmitted in the December 8 letter brought forward all of the invoices listed in the November 2 letter and only added an invoice for $2,359.29 for one carload of material not previously billed, leaving a new balance of $48,805.23. Suit was brought on November 13, 1967, a year and 11 days after the November 2 Miller Act notice, but within a year of the December 8 Miller Act notice transmitting the November 30 statement.

Treating the letters and the statements as the measure of the time of delivery of materials for purposes of the one-year statutory requirement, the trial court specifically found that the letter and statement of November 2 showed an unpaid balance for "materials previously delivered to the project," and that the last delivery of material was consequently prior to November 2, 1966—more than a year before suit was filed. Apparently referring to the December 8 letter, the court found that the added invoice (M-17489) was "an earlier invoice inadvertently omitted and later included," and that none of the listed invoices tended to show the delivery of any material subsequent to November 2. The court also referred to a certified statement of December 9, not formally introduced but read into evidence and relied upon by both parties. This statement lists all of the invoices contained in the December 8 letter and bears a notarized certification by the president of Tri-State that "the above listed invoices represent material delivered to the Pathman Job." As to this instrument, the trial court observed that "said Affidavit could only have been based on knowledge on or prior to October 28, 1966," the date on which the court found that Tri-State abandoned the project, and that it therefore confirmed the correctness of the statements contained in the November 2 letter. The court thus found the proof insufficient to establish the one-year jurisdictional requirement of the Miller Act, and the case was consequently dismissed.

Material Service introduced but never relied on the November 2 letter as truly reflecting the delivery dates of the material set forth in the itemized statements. On trial the writer of the Miller Act letters did not deny the correctness of the statements included therein, but testified that he sent the November 2 letter under the mistaken impression that the materials were being delivered inside the buildings at the job site without delay, and...

To continue reading

Request your trial
24 cases
  • Southern Elec. Health Fund v. Kelley
    • United States
    • U.S. District Court — Middle District of Tennessee
    • September 30, 2003
    ...John D. Ahern Co. v. J.F. White Contracting Co., 649 F.2d 29, 31 (1st Cir.1981); United States ex rel. Material Servs. Div. of General Dynamics Corp. v. Home Indemnity Co., 489 F.2d 1004, 1005 (7th Cir. 1973); United States ex rel. Noland Co. v. Andrews, 406 F.2d 790, 791 (4th 8. The Court ......
  • U.S. for Use and Ben. of Harvey Gulf Intern. Marine, Inc. v. Maryland Cas. Co.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • May 19, 1978
    ...States for the Use of Celanese Coatings Co. v. Gullard, 504 F.2d 466 (9th Cir. 1974); United States for the Use and Benefit of General Dynamics Corp. v. Home Indemnity Co., 489 F.2d 1004 (7th Cir. 1973); United States for the Use and Benefit of Statham Instruments, Inc. v. Western Casualty ......
  • United States v. Travelers Cas. & Sur. Co. of Am.
    • United States
    • U.S. District Court — Northern District of West Virginia
    • September 23, 2014
    ...rel. John D. Ahern Co., Inc. v. J.F. White Contracting Co., 649 F.2d 29, 31 (1st Cir.1981) ; United States ex rel. General Dynamics Corp. v. Home Indemnity Co., 489 F.2d 1004, 1005 (7th Cir.1973) ; see also Honeywell, 677 F.2d at 386 (“strict enforcement of [the notice] requirement is neces......
  • Harl v. City of La Salle
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • May 24, 1982
    ...be heard to press those other theories on appeal." Id. at 849 n.10 (This was a rule 41(b) dismissal below)).United States v. Home Indemnity Co., 489 F.2d 1004 (7th Cir. 1973). ("Although the rule is not absolute, a litigant cannot ordinarily expect to lose in the trial court on one theory a......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT