U.S. v. Gardner

Decision Date09 January 1976
Docket NumberNo. 75--1327,75--1327
PartiesUNITED STATES of America, Plaintiff-Appellant, v. Malcolm P. GARDNER and Herbert L. Stern, Jr., Defendants-Appellees.
CourtU.S. Court of Appeals — Sixth Circuit

Ralph B. Guy, Jr., U.S. Atty., Detroit, Mich., Irving Jaffe, Robert S. Greenspan, Ronald R. Glancz, Civ. Div., Appellate Sect., Dept. of Justice, Washington, D.C., for plaintiff-appellant.

Jack B. Schmetterer, Mark Lieberman, Chicago, Ill., Charles T. McGorisk, John P. Jacobs, Plunkett, Cooney, Rutt, Watters, Stanszyk & Pedersen, Detroit, Mich., Seth H. Barsky, Southfield, Mich., for defendants-appellees.

Before PHILLIPS, Chief Judge, McCREE, Circuit Judge, and McALLISTER, Senior Circuit Judge.

PHILLIPS, Chief Judge.

The sole issue on this appeal is whether the United States, on the facts here presented, is barred from suing on its debt priority under 31 U.S.C. §§ 191 and 192 1 and by the statute of limitations set forth in 28 U.S.C. § 2415. 2 The District Court determined, inter alia, that the right of action accrued on the date of the company's default, and that the Government's suit is barred by the statute. We reverse and remand.

In 1966, Drillmation, Inc. (the Company) entered into two contracts with the Department of the Army for carbine bolts and flash suppressors. The Company encountered difficulties in proceeding with both contracts and eventually notified the Army on April 27, 1967, that it was unable to continue performance. The Government contracting officer then terminated the two contracts for default on May 19, 1967, and May 24, 1967, respectively. Pursuant to the standard 'disputes clause' 3 of the contracts Between May and November 1967, the Company sold its unrelated Army assets and changed its name to Eight Mile Road Defense Contractors, Inc. (Eight Mile Inc.). All remaining assets of Eight Mile Inc. were surrendered to its lienholder, the American National Bank of Chicago, which after sale and satisfaction of its lien returned $170,528.43 to appellees as surplus. The appellees, officers of Eight Mile Inc., although aware of the obligation due the United States, distributed this amount to general creditors and did not pay any part of the indebtedness owed to the Government.

which provides for an administrative appeal from the decision of the contracting officer to the Armed Services Board of Contract Appeals (ASBCA), the Company appealed from the contracting officer's factual finding that it had defaulted on the contracts.

On January 19, 1968, pending the appeal to the ASBCA, Eight Mile Inc. entered into a contract with the Government whereby the Army agreed not to put Eight Mile Inc. on certain Government lists and not to refer the debt to the General Accounting Office until 45 days after the ASBCA decision. 4 This deferral agreement also provided that Eight Mile Inc. would pay the amount found owing by the ASBCA promptly within 45 days of the decision. Such payment, however, would be without prejudice to the contractor's right to move for reconsideration or to pursue other remedies available at law. The decision of the Appeals Board was handed down on April 10, 1969.

Subsequently, on November 6, 1973, the United States instituted this suit against the appellees, as fiduciaries of Eight Mile Inc., to hold them personally liable for distributing the funds in violation of their statutory duty under 31 U.S.C. § 192. The District Court held that the action was barred by the six year statute of limitations of 28 U.S.C. § 2415, finding that the right of action accrued on the date of default in May 1967.

The Government relies upon three grounds for reversal:

1) That the deferral agreement of January 19, 1968, constituted an independent contract to pay the claim, which was breached by the Company in 1969; therefore, the six year limitation period 2) That, in any event, the deferral agreement was a contract to toll the statute of limitations during the pendency of the appeal to the ASBCA; and

had not run in 1973 when the Government filed this suit;

3) Alternatively, that the Government's cause of action under 31 U.S.C. § 192 did not accrue until the defendants' payment of debts in violation of the Government's priority.

We agree with the first ground asserted by the Government. Therefore, it is not necessary to reach the other issues in disposing of this appeal.

28 U.S.C. § 2415(a) (n. 2) provides a six year period of limitations for suits 'founded upon any contract express or implied in law or fact.' The record demonstrates that the present action is a suit founded on a contract, viz, the deferral agreement entered into between the Company and the Government on January 19, 1968.

The deferral agreement provides in part as follows:

AGREEMENT BETWEEN

DRILLMATION COMPANY, INC. NOW KNOWN AS EIGHT MILE ROAD DEFENSE CONTRACTORS, INC.

1601 Wanda Avenue

Ferndale, Michigan 48220

and

THE DEFENSE SUPPLY AGENCY CAMERON STATION, ALEXANDRIA, VIRGINIA 22314

1. A Defense Supply Agency (DSA) Contracting Officer by formal decision has found that Drillmation Company, Inc. (Eight Mile Road Defense Contractors, Inc.), hereinafter referred to as the Contractor, owes the U.S. Government a total principal amount of $1,541,321.60 plus interest at the rate of 6% per annum as stipulated on the reverse hereof under Contracts DA 19--058--AMC--1509(W) and DA 19--058--AMC--1645(W).

2. The Contractor denies existence of such debt and has appealed the Contracting Officer's decision to the Armed Services Board of Contract Appeals (ASBCA).

3. The ASBCA has docketed the appeal as No. 12501 for Contract 1509(W) and 12579 for Contract 1645(W).

4. The Contractor agrees to pay to the DSA the amount, plus accrued interest, found due by reason of the ASBCA decision on the appeal, or if the appeal is dismissed by the Board without decision, the amount mentioned in paragraph 1 above. Such payment in either case shall be without prejudice to the Contractor's right to move for reconsideration or to pursue such other remedies at law as it may have. The Contractor further agrees to make such payment in full within 45 days of the date of the ASBCA decision or dismissal of the appeal or to make arrangements within that 45 day period to pay the amount on an installment basis within the bounds of the minimum requirement outlined in paragraph 5 below.

6. The DSA agrees not to circulate the name of the Contractor on certain U.S. Government lists designed to effect settlement of accounts of recalcitrant debtors and agrees not to transfer the case to the U.S. General Accounting Office or the Department of Justice before 45 days after the ASBCA decision on the appeal is published and to do so then only if the Contractor fails to comply with paragraph 4 above or fails to fulfill any agreement reached under paragraph 5 above.

We hold that the District Court erred in ruling that the cause of action accrued prior to the execution of the deferral agreement, i.e., when the Government contracting officer terminated the construction contract for default.

This action is grounded on the deferral agreement. Paragraph 12 of the complaint avers the execution of the deferral contract under which it was agreed 'that the due date of said obligation would be postponed until 45 days after rulings of the Armed Services Board of Contract Appeals' and that, in consideration of the deferment of the claim, the Company agreed 'to pay to the United States, within said 45 days whatever amount might be found due by said Armed Services Board of Contract Appeals, plus interest from June 22, 1967.'

Paragraphs 23 and 24 of the complaint are as follows:

23. By virtue of the deferred-payment...

To continue reading

Request your trial
4 cases
  • Yanover v. Hancock
    • United States
    • Court of Appeal of Michigan — District of US
    • August 25, 2022
    ... ... Contracts (rev ed), § 9.5, p 255] ... Case law applying the common-law adheres to this rule ... See, e.g., U.S. v Gardner, 528 F.2d 715, 719 (CA 6, ... 1976); US v Upper Valley Clinic Hosp, Inc, 615 F.2d ... 302, 306 (CA 5, 1980) ("Contract law recognizes ... ...
  • Yanover v. Hancock
    • United States
    • Court of Appeal of Michigan — District of US
    • August 25, 2022
    ... ... Contracts (rev ed), § 9.5, p 255] ... Case law applying the common-law adheres to this rule ... See, e.g., U.S. v Gardner, 528 F.2d 715, 719 (CA 6, ... 1976); US v Upper Valley Clinic Hosp, Inc, 615 F.2d ... 302, 306 (CA 5, 1980) ("Contract law recognizes ... ...
  • U.S. v. Upper Valley Clinic Hospital, Inc., 78-1693
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • April 10, 1980
    ...the time of each such payment or acknowledgment: . . . .6 This fundamental tenet has been applied to 28 U.S.C. § 2415. United States v. Gardner, 528 F.2d 715 (6th Cir.), cert. denied, 426 U.S. 954, 96 S.Ct. 3181, 49 L.Ed.2d 1193 (1976).7 The failure of the Hospital to file any report, howev......
  • U.S. v. Gregory, 91-3503
    • United States
    • U.S. Court of Appeals — Fourth Circuit
    • December 19, 1991
    ...anew if a partial payment is made on the debt or if the debtor makes a written acknowledgment of the debt. See United States v. Gardner, 528 F.2d 715, 719 (6th Cir.1976), cert. denied, 426 U.S. 954 (1976). Therefore, if defendant has made any payments on the debt owed to the FmHA within the......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT