Neill v. Gates
Decision Date | 12 December 1899 |
Parties | Neill, Appellant, v. Gates |
Court | Missouri Supreme Court |
Appeal from Jackson Circuit Court. -- Hon. John W. Henry, Judge.
Affirmed.
Karnes New & Krauthoff and A. F. Smith for appellant.
(1) The ordinance and contract are not inconsistent. The same tax involved in the Brannock case 70 Mo.App. 535, have been before the Kansas City Court of Appeals three times. McQuiddy v. Vineyard, 60 Mo.App. 610; McQuiddy v. Smith, 67 Mo. App., 205 and McQuiddy v Gates, 69 Mo.App. 156. The same proceedings have been followed in every case appealed from the Jackson circuit court involving Kansas City tax bills, for the last ten years, and in not one of them was the question raised. Forry v. Ridge, 56 Mo.App. 615; Quest v Johnson, 58 Mo.App. 54; Dollar Savings Bank v. Ridge, 62 Mo.App. 324; Jaicks v. Sullivan, 128 Mo. 177. (2) The common council has solemnly approved this contract in all its terms. It will be argued that the contract was void because it did not conform to the ordinance in reference to the time when the work should be completed. But the contract does conform to the ordinance. The ordinance says that the work shall be completed within ninety days from the time the contract shall take effect. So does the contract. But the ordinance does not say what the result of a failure to comply shall be. The contract does. For years it had been the custom of the succeeding boards of aldermen of Kansas City to understand that it was their duty to put a time limit in every ordinance authorizing any public improvement, and to understand that the failure of the contractor was to be punished under a general ordinance, which by the general ordinances of Kansas City was to "be deemed and taken as a part of every contract for the doing of any work," it being provided by the general ordinances that every contract "shall contain a clause that the same is entered into subject to the existing charter and ordinances of the city." People ex rel. v. Supervisors, 17 N.Y. 235; Cooley, Const. Lim. (6 Ed.), p. 216; Sheehan v. Owen, 82 Mo. 458; Marionville to use v. Henson, 65 Mo.App. 405; Johnson v. Duer, 115 Mo. 381.
Ess & Georgen for respondent.
(1) Since the contract provides that "the time of beginning, rate of progress and time of completion being essential conditions of this contract," etc., time was of the essence of this contract by the ordinance and contract. The work was not done in the time provided for, and the tax bill is void. Rose v. Trestrail, 62 Mo.App. 356; McQuiddy v. Brannock, 70 Mo.App. 539 and 542; New England Safe Deposit & Trust Co. v. James, 77 Mo.App. 618; Brown v. Guaranty Trust Co., 128 U.S. 414; Cheney v. Libby, 134 U.S. 77. The common council have the power to fix the time in which a district sewer shall be constructed. (2) The engineer canceled the contract on February 11, 1892, 202 days after the time the contractor was to have completed it; and if we exclude the time the temporary injunction was in force, 131 days after it took effect, this cancellation was valid and ended the contract. Williams v. Railroad, 112 Mo. 487; Chapman v. Railroad, 114 Mo. 549; Dinsmore v. Livingston Co., 60 Mo. 244; Kihlberg v. U.S. 97 U.S. 401; Breitting v. New Orleans, 24 La. Ann. 21; Easton v. Penn. & Ohio Canal Co., 13 Oh. 83; Chapman v. Lowell, 4 Cush. 380; Norrington v. Wright, 115 U.S. 188. (3) The time was not extended at any time during the ninety days next succeeding July 23, 1891. The contract expired by its own terms, and by ordinance numbered 3247, on October 21, 1891. The injunction was no excuse for any delay beyond October 21, 1891. Harrison v. Railroad, 74 Mo. 371; McQuiddy v. Brannock, 70 Mo.App. 542. (4) Ordinance 5453 is repealed by ordinance 5532, approved December 6, 1893. This did not in terms or by legal effect revive ordinance 3247. In order to revive it or re-enact it, "the same shall be set forth at length as if it were an original ordinance." Kansas City Charter, art. III, sec. 9; Mayor v. Trigg, 46 Mo. 288; State v. Slaughter, 70 Mo. 487; State v. Grant, 79 Mo. 132; Milne v. Huber, 3 McLean 213; Stuman v. State, 21 Tex. 736.
This is an action by plaintiff as assignee of one James Pryor on six different tax bills aggregating, not including interest when the suit was begun, the sum of $ 2,515.85, and issued by Kansas City against six different tracts of land owned by defendant, in Sewer District No. 167, in said city.
On April 18, 1891, an ordinance was passed by Kansas City establishing Sewer District No. 167, which embraced the land against which the tax bills involved in this litigation were issued. Thereafter on June 10, 1891, an ordinance No. 3247 was passed, authorizing the construction of sewers in said district, by which it was provided that "the work should be completed within ninety days from the time a contract binds and takes effect," the ordinance reciting that "this work the Board of Public Works and Common Council deem necessary for sanitary and drainage purposes."
The work was let by contract to said Pryor, and approved by ordinance of date July 23, 1891. By its terms work was to be begun in ten days and to be completed in ninety days from the time the contract was executed. The contract provided that the contractor should not be entitled to any portion of the contract price until the work was completed to the satisfaction of the city engineer, and then only in tax bills. The time in which the work was to be completed expired October 21, 1891. The work was begun, and continued up to August 21, 1891, when Jennie C. Wiltsee and others brought suit against the contractors and Kansas City, and obtained a temporary injunction restraining them from a continuation of the work. The injunction was dissolved on October 31, 1891, but from the time it was granted until its dissolution, no work was done on the sewer.
The contract provides that:
The evidence showed that work amounting to $ 4,000 at the contract price, was done up to February 11, 1892.
On February 4, 1892, the city engineer, Butts, wrote Pryor, the contractor, and his sureties on his bond as contractor, to proceed with the work in three days, and on his failure to do so he would annul the contract, which he, the engineer in so far as he had power to do so did on February 11, 1892, because Pryor would not proceed with the work, and, so notified the board of public works.
Butts, the engineer, went out of office in May, 1892, and was succeeded by John Donnelly. Pryor paid no attention to the cancellation of his contract by Butts, but continued to work on said sewer with the full knowledge and consent of Donnelly, the successor of Butts, until October 24, 1893, when the Common Council of Kansas City passed an ordinance, No. 5453, to construct a district sewer in Sewer District No. 167, and by it repealed ordinance No. 3247 entitled: "An Ordinance to establish and cause to be constructed district sewer in Sewer District No. 167," approved June 10, 1891.
This last named ordinance makes no reference to the ordinance approving the contract between the city and the contractor, nor does it refer to the contract.
On December 6, 1893, the Common Council of Kansas City passed "an ordinance to repeal an ordinance of Kansas City No. 5453, entitled: 'An ordinance to construct a district sewer in Sewer District No. 167,' approved October 24, 1893."
On March 19, 1894, said council passed an...
To continue reading
Request your trial