Ohio Environmental Council v. U.S. Dist. Court, Southern Dist. of Ohio, Eastern Div.

Decision Date04 November 1977
Docket NumberNo. 76-2581,76-2581
Citation565 F.2d 393
Parties, 8 Envtl. L. Rep. 20,042 The OHIO ENVIRONMENTAL COUNCIL, Petitioner, v. UNITED STATES DISTRICT COURT, SOUTHERN DISTRICT OF OHIO, EASTERN DIVISION, and Columbus and Southern Ohio Electric Company, Respondents.
CourtU.S. Court of Appeals — Sixth Circuit

A. Mark Segreti, Jr., Segreti & Tousey, Columbus, Ohio, for petitioner.

A. G. Green, President and Chairman of Board of Directors, Columbus and Southern Ohio Elec. Co., Columbus, Ohio, J. Jeffrey McNealey, Porter, Stanley, Platt & Arthur, Columbus, Ohio, for respondents.

Before CELEBREZZE, PECK and ENGEL, Circuit Judges.

JOHN W. PECK, Circuit Judge.

The Ohio Environmental Council has petitioned this Court to issue a writ of mandamus directing the District Court to enter a judgment ordering Columbus & Southern Ohio Electric Company to comply with the fuel boiler emission limitations in Ohio's plan for implementation of national ambient air standards under the Clean Air Act, 42 U.S.C. § 1857 et seq. * The District Court entered a stay of Clean Air Act enforcement proceedings initiated by the OEC against C&SOE, until C&SOE has had an opportunity to contest the Environmental Protection Agency's approval of the plan.

The factual background of this case is complicated, but some detail is required for an understanding of the issues involved. In 1970, extensive amendments to the Clean Air Act were passed. The operation of the regulatory scheme is discussed at length in Train v. Nat'l Resources Def. Council, 421 U.S. 60, 95 S.Ct. 1470, 43 L.Ed.2d 731 (1975), but in brief, each state was required to formulate, subject to EPA approval, a State Implementation Plan (SIP) designed to achieve national primary ambient air quality standards "as expeditiously as practicable but in no case later than three years from the date of approval of such plan." Clean Air Act § 110(a)(2)(A), 42 U.S.C. § 1857c-5(a)(2)(A).

The Amendments provide for judicial review of the EPA's approval of a plan for a state within the circuit in the United States Court of Appeals, if a petition for review is filed within thirty days of the EPA's action. Sec. 307(b)(1), 42 U.S.C. § 1857h-5(b)(1). This concern for speedy review and implementation of an SIP is reflected in Section 307(b)(2), clearly aimed at preventing delay in enforcement. It provides that any action taken by the EPA which could have been reviewed in a Section 307(b)(1) proceeding "shall not be subject to judicial review in civil or criminal proceedings for enforcement." 42 U.S.C. § 1857h-5(b)(2).

The Ohio SIP was originally submitted to the EPA for approval on January 30, 1972, and was approved on May 31, 1972. A year later, this Court remanded the Ohio SIP to the EPA for informal rulemaking procedures. Buckeye Power Inc. v. EPA, 481 F.2d 162 (6th Cir. 1973) (Buckeye I ). The EPA reapproved the plan in 1974. At that time, the plan's deadline for achieving the emission limitations was July 1, 1975, but extensive modifications of the plan, including an extension of the deadline to April 15, 1977, were submitted to the EPA for approval on July 16, 1975.

This enforcement suit was filed October 16, 1975, pursuant to the Citizen Suit Provisions of Section 304, 42 U.S.C. § 1857h-2, which grants the district courts jurisdiction to enforce the requirements of approved plans. OEC sought to enforce the emission standards of the original plan against C&SOE which would essentially have meant the shutdown of three C&SOE boilers. The next day, a second revision was submitted for approval to the EPA. Approval of this second revision would apparently moot this law suit, since it would exempt the two C&SOE boilers which are still not in compliance with the standards.

Meanwhile, steel and utility companies (including the defendant in this case) were again seeking judicial review of the original plan in this Court. On October 23, 1975, in Buckeye Power, Inc. v. EPA, 525 F.2d 80 (6th Cir. 1975) (Buckeye II ), this Court held that the controversies raised by the petitioners were not yet ripe for judicial review. Since the plan was in the process of major revision, this Court could "perceive no immediate harm to petitioners in allowing the environmental protection administrative processes to arrive at definitive administrative conclusions on these disputed issues." 525 F.2d at 84.

Eleven months later, on September 26, 1976, the EPA finally approved the first revision proposal. The second proposal, dealing specifically with the boilers involved in this suit, was not approved, and was eventually returned to the state as inadequate.

On December 1, 1976, the District Court entered a stay of the enforcement proceedings "pending the further order of this Court." The Court held "that 42 U.S.C. § 1857h-5(b) vests exclusive jurisdiction in the Court of Appeals concerning judicial review of the Administrator's action in approving the SIP, and further that enforcement proceedings cannot be had against defendants under that SIP until it has had an opportunity to contest the Administrator's approval of the plan." The Court reasoned that since review of the plan had been denied the defendant in Buckeye II, the plan could not be enforced. This petition for a writ of mandamus ordering the District Court to enforce the plan was promptly filed. On April 15, 1977, the deadline for attainment of the standards passed, and C&SOE is admittedly not in compliance with the requirements of the plan.

This Court can perceive no reason for delay in the enforcement of Ohio's emission limitations. There is no dispute that Ohio has an "applicable implementation plan," as defined in § 110(d) of the Clean Air Act, and that the Citizen Suit Provisions of § 304 grant jurisdiction to the district courts to enforce such plans. Since Buckeye II did not remand the Ohio SIP or disapprove it in any way, the sole issue involved here is the propriety of the stay of enforcement issued by the District Court.

We note at the outset that "the power to stay proceedings is incidental to the power inherent in every court to control the disposition of the causes in its docket with economy of time and effort for itself, for counsel and for litigants," Landis v. North American Company, 299 U.S. 248, 254-55, 57 S.Ct. 163, 166, 81 L.Ed. 153 (1936), and that the entry of such an order ordinarily rests with the sound discretion of the District Court. We see nothing in the Clean Air Act to alter these basic principles, and reject plaintiff's argument that the District Court is stripped of this fundamental power in the context of an enforcement proceeding simply because its jurisdiction is limited by Section 307(b)(2). Cf., Scripps-Howard Radio v. FCC, 316 U.S. 4, 62 S.Ct. 875, 86 L.Ed. 1229 (1942) (Courts of Appeals retain power to order stay during review of FCC determinations).

Given this, however, it is also clear that a court must tread carefully in granting a stay of proceedings, since a party has a right to a determination of its rights and liabilities without undue delay. In Landis v. North American Company, supra, the Supreme Court set out guidelines for a court to consider in granting stays. In a suit brought by two holding companies seeking to restrain enforcement of the Holding Company Act, the District Court had entered an order staying all proceedings until the conclusion of the trial and appeal of a similar challenge in another court. The Supreme Court held that such an order constituted a clear abuse of discretion. First, it pointed out:

The suppliant for a stay must make out a clear case of hardship or inequity in being required to go forward, if there is even a fair possibility that the stay for which he prays will work damage to someone else. Only in rare circumstances will a litigant in one cause be compelled to stand aside while a litigant in another settles the rule of law that will define the rights of both.

299 U.S. at 255, 57 S.Ct. at 166. Thus the burden is on the party seeking the stay to show that there is pressing need for delay, and that neither the other party nor the public will suffer harm from entry of the order. A court should be particularly hesitant when, as here, the stay will disrupt a statutory or administrative timetable. Furthermore, even if the reasons for the stay are proper, the stay itself "is immoderate and hence unlawful unless so framed in its inception that its force will be spent within reasonable limits, so far at least as they are susceptible of prevision and description." 299 U.S. at 257, 57 S.Ct. at 167. See also, Dellinger v. Mitchell, 143 U.S.App.D.C. 60, 442 F.2d 782 (D.C.Cir.1971).

Measured by these standards, we reluctantly conclude that the District Court has clearly abused its discretion in entering the present order. With no safeguards for the health of the public, and in spite of the fact that the final deadline for compliance has passed, the District Court has entered an order which could place this case in limbo for years. The cause has already been delayed for more than a year and a half by successive stays.

On the other hand, C&SOE has failed to demonstrate how prompt enforcement would harm it in any way other than the burden it must bear in meeting its responsibility under the Ohio SIP. Both the District Court and C& SOE relied on the argument that the defendant is entitled to judicial review of the emission limitations contained in the SIP. However, the burden is wholly on the defendant to seek judicial review if it has an objection to the propriety of the EPA's action in approving the Ohio SIP, and the review provided for in Section 307(b)(1) is completely independent of any enforcement proceeding. If C&SOE has failed to seek review prior to enforcement, it has no right to claim that it has been denied review, although the District Court is correct in concluding that it is without jurisdiction to review any action of the EPA which...

To continue reading

Request your trial
265 cases
  • Schobert v. CSX Transp. Inc.
    • United States
    • U.S. District Court — Southern District of Ohio
    • 30 Noviembre 2020
    ... ... Case No. 1:19-cv-76 United States District Court, S.D. Ohio, Western Division. Signed November 30, ... Adams Cnty. Reg'l Water Dist. , 409 F.3d 758, 767 (6th Cir. 2005) (denying ... The Eastern District of Michigan, although perhaps ... See Lingle v. Norge Div. of Magic Chef, Inc. , 486 U.S. 399, 411, 108 ... 2014) (quoting Ohio Env'tl. Council v. U.S. Dist. Court, S. Dist. of Ohio, E. Div. , ... ...
  • United States v. Cargill, Inc.
    • United States
    • U.S. District Court — District of Delaware
    • 12 Febrero 1981
    ... ... No. 80-135 ... United States District Court, D. Delaware ... February 12, 1981. 508 F ... interstitial interpretation and environmental exploration as the partners pirouette. The ... Colorado River Water Conservation Dist. v. United States, 424 U.S. 800, 813, 96 S.Ct ... at 255, 57 S.Ct. at 166; Ohio Environmental Council v. United States District ... ...
  • In re Application for Water Rights of US
    • United States
    • Colorado Supreme Court
    • 8 Noviembre 2004
    ... ... Emmons Mining, Opposers, and ... Environmental Defense; High Country Citizens' Alliance; the ... ; Western Slope Environmental Resource Council; and Trout Unlimited, Additional Opposers ... No. 03SA321 ... Supreme Court of Colorado, En Banc ... November 8, 2004 ... for the Tenth Circuit's decision in Southern Utah Wilderness Alliance v. Norton, 301 F.3d ... See, e.g. Colo. River Water Conservation Dist. v. United States, 424 U.S. 800, 807-08, 96 ... Id. See also Ohio Envtl. Council v. Dist. Court, 565 F.2d 393 (6th ... ...
  • Hall v. U.S. EPA
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • 8 Enero 2001
    ... ... UNITED STATES ENVIRONMENTAL PROTECTION AGENCY, Respondent ... No. 99-70853 ... UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT ... Page 1147 ... 1976); Ohio Envtl. Council v. U.S. Dist. Ct., S. Dist. of o, E. Div., 565 F.2d 393, 396 (6th Cir. 1977); Kamp v ... 110(l) of the Clean Air Act, affording us no basis to understand the EPA's reasoning ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT