Martin Marietta Aluminum, Inc. v. General Elec. Co.

Decision Date13 November 1978
Docket NumberNo. 76-3763,76-3763
Citation586 F.2d 143
PartiesMARTIN MARIETTA ALUMINUM, INC., a California Corporation, Plaintiff-Appellant, v. GENERAL ELECTRIC COMPANY, a New York Corporation, Defendant-Appellee.
CourtU.S. Court of Appeals — Ninth Circuit

John E. Ederer (argued), of Helsell, Fetterman, Martin, Todd & Hokanson, Seattle, Wash., for plaintiff-appellant.

Coleman P. Hall (argued), of Karr, Tuttle, Koch, Campbell, Mawer & Morrow, Seattle, Wash., for defendant-appellee.

Appeal from the United States District Court for the Western District of Washington.

Before WRIGHT and GOODWIN, Circuit Judges, and JAMESON, * District Judge.

JAMESON, District Judge:

Martin Marietta Aluminum, Inc. (MMA), brought this action for damages as a result of the breakdown of 12 high voltage rectifier transformers at its aluminum reduction plant. MMA contends that its losses were the result of improper design and manufacture by General Electric Company (GE), which by contract supplied the plant's high voltage electrical system. The complaint alleged that GE was negligent and was liable for breach of implied and express warranties. An amended complaint added causes sounding in fraud and strict liability.

In its answer, GE denied the charging allegations and raised seven affirmative defenses, including MMA's failure to comply with a contractual arbitration clause. Following discovery, GE moved for summary judgment on the basis of several of its affirmative defenses. The district court granted the motion solely on the ground that MMA had failed to comply with the contractual provision requiring MMA to seek arbitration prior to instituting suit.

The contract between MMA 1 and GE consisted of a Purchase Order, General Conditions for Procurement of Equipment and three volumes of specifications. Section 24 of the General Conditions provided:

Arbitration. If any controversy arising out of the Purchase Order cannot be settled or adjusted by mutual agreement of Seller and Harvey, then either party may, within six (6) months after such controversy shall have arisen, request arbitration of such controversy to be held in the State of Washington under the rules of the American Arbitration Association; provided, however, that a request for arbitration of any controversy regarding any warranty of Seller set forth in the Purchase Order may be made at any time during the period of warranty or within six (6) months thereafter. If arbitration is entered into, the judgment on the award may be entered in any Washington court or federal court having jurisdiction. It shall be a condition precedent to the institution, by either Seller or Harvey, of any action at law or in equity on any matter arising out of the Purchase Order that such party shall have first requested arbitration of such matter, as aforesaid, and shall not have received the agreement of the other party to such arbitration within ten (10) days after such request.

In granting GE's motion for summary judgment, the court said in part:

The arbitration provision unambiguously provides that after a controversy arising out of the purchase order has arisen, the party seeking relief has six months to request arbitration. Such request gives the defending party the choice of accepting arbitration or forcing the plaintiff to litigate in the courts. It is clear that a request for arbitration must precede the institution of a suit. The conclusion is unavoidable that failure to request arbitration within six months of the arising of the controversy leaves the plaintiff barred. Notably, this arbitration clause was drafted by the plaintiff's predecessor, Harvey Aluminum.

On appeal MMA contends primarily that summary judgment was improperly granted because GE, by its pre- and post-litigation conduct, either waived or is estopped from requiring compliance with the contractual arbitration provision. 2

Interpretation of Arbitration Provision

Both parties agree that the arbitration clause is unique. The standard arbitration clause is Mandatory, requiring that any dispute be arbitrated. MMA argues that the arbitration provision here "Permits but does not require arbitration, and arbitration is possible only where both parties want to arbitrate". MMA's construction of the arbitration clause would permit a person seeking relief to decide whether to arbitrate or litigate, but require the other party to request arbitration or be forced to forego reliance on the arbitration clause as an affirmative defense.

GE contends that the arbitration clause requires the party seeking relief to request arbitration within the specified time limit, but permits the other party either to arbitrate or to refuse to arbitrate, thus forcing litigation. Under this construction if the party seeking relief does not request arbitration, the other party may do nothing and still rely on the arbitration clause as an affirmative defense.

The district court adopted GE's construction, and we agree. MMA's construction ignores the last sentence of the arbitration clause providing that, "It shall be a condition precedent to the institution" of any action that the party "shall have first requested arbitration".

Waiver

As the district court recognized, a contract provision for arbitration may be waived, expressly or impliedly. Waiver is an issue to be determined by the court, based upon the facts and circumstances relied upon. Geo. V. Nolte & Co. v. Pieler Construction Co., 54 Wash.2d 30, 337 P.2d 710, 713 (1959). When the defendant, by answer, has given notice of its arbitration defense, the burden is heavy on the party seeking to prove waiver. Hilti, Inc. v. Oldach, 392 F.2d 368, 371 (1st Cir. 1968). 3

In contending that GE's conduct constituted a waiver of the arbitration clause, MMA relies upon (1) lengthy negotiations between the parties prior to suit regarding the reason and remedy for the failure of the transformers until MMA was faced with a statute of limitations deadline; and (2) extensive discovery by both parties after suit. MMA argues that GE had an obligation to request arbitration, move to dismiss the suit because of the arbitration clause, or request a stay of the proceedings pending arbitration. Instead, MMA argues, GE sat by and did nothing, and then attempted to set up the arbitration clause as a bar.

There was no obligation, however, on GE to request arbitration. That duty under the express terms of the contract was imposed only on the party seeking relief. In concluding that there was no waiver the district court noted that GE pleaded the arbitration clause as an affirmative defense 4 and that, unlike many of the cases on which MMA relied, GE had no obligation to institute arbitration. The court found that GE's "participation in discovery consisted largely of attempts to obtain elaboration of the claims made. This was justified in light of statements by counsel for plaintiff that arbitration was not requested because certain issues were not believed to be arbitrable". 5

Estoppel

For the estoppel doctrine to be applicable there must be (1) acts, statements, or admissions inconsistent with a claim subsequently asserted, (2) action or change of position on the part of the other party in reliance upon such acts, statements, or admissions, and (3) a resulting injustice to such other party, if the first party is allowed to contradict or repudiate his former acts, statements or admissions. Witzel v. Tena, 48...

To continue reading

Request your trial
84 cases
  • Luchini v. Carmax, Inc.
    • United States
    • U.S. District Court — Eastern District of California
    • 23 Julio 2012
    ...pending compliance with a contractual arbitration clause . . . a request for a stay is not mandatory." Martin Marietta Aluminum, Inc. v. Gen. Elec. Co., 586 F.2d 143, 147 (9th Cir.1978). A district court may properly entertain a dismissal motion. Thinket Ink Information Resources, Inc. v. S......
  • McCarthy v. Azure
    • United States
    • U.S. Court of Appeals — First Circuit
    • 5 Enero 1994
    ...be read more broadly if it were the only provision extant, see, e.g., Arnold, 920 F.2d at 1271; Martin Marietta Alum., Inc. v. General Elec. Co., 586 F.2d 143, 145, 147-48 (9th Cir.1978), the use of significantly different language in two clauses, sculpted by the same parties during the sam......
  • Perry Homes v. Cull
    • United States
    • Texas Supreme Court
    • 2 Mayo 2008
    ...758 (7th Cir.2002); Ritzel Commc'ns v. Mid-American Cellular, 989 F.2d 966, 969-71 (8th Cir. 1993); Martin Marietta Aluminum, Inc. v. Gen. Elec. Co., 586 F.2d 143, 146 (9th Cir. 1978); Metz v. Merrill Lynch, Pierce, Fenner & Smith, Inc., 39 F.3d 1482, 1489-90 (10th Cir. 1994); Ivax Corp., 2......
  • Motoyama v. State
    • United States
    • U.S. District Court — District of Hawaii
    • 29 Marzo 2012
    ... ... Cook, Department of the Attorney General, Honolulu, HI, for Defendants. ORDER GRANTING ... facts, Declarations of Lisa Dau, Melanie Martin, Ben Gorospe, Maria C. Cook, and exhibits AKK ... Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d ... See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT