W.A. Botting Plumbing and Heating Co. v. Constructors-Pamco

Decision Date18 May 1987
Docket NumberCONSTRUCTORS-PAMC,No. 15877-5-I,A,15877-5-I
Citation736 P.2d 1100,47 Wn.App. 681
PartiesIn re Arbitration of W.A. BOTTING PLUMBING AND HEATING COMPANY, Respondent, andppellant.
CourtWashington Court of Appeals

Douglas K. Haughton, Thomas D. Frey, John Budlong, Stafford, Frey & Mertel, Seattle, for Constructors-Pamco.

Joel McCormick, Winston & Cashatt, Spokane, for W.A. Botting Plumbing and Heating Co.

GROSSE, Judge.

Constructors-Pamco (Pamco) appeals from an order confirming an arbitration award in favor of W.A. Botting Plumbing and Heating Company (Botting). Pamco argues that the arbitrator lacked jurisdiction to hear the case. We disagree.

Pamco was awarded a construction contract by the Snohomish County Public Utility District No. 1. Pamco thereafter subcontracted a majority of the mechanical work to Botting. The agreement between Pamco and Botting included the following arbitration clause:

ARBITRATION

Any controversy or claim affecting only CONTRACTOR and SUBCONTRACTOR and arising out of or relating to this CONTRACT, or the breach thereof, shall be settled in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association, and judgment upon the award may be entered in any court having jurisdiction thereof.

Botting sought recovery for various items and demanded arbitration pursuant to the subcontract.

After the completion of the arbitration hearing, Pamco submitted a memorandum to the arbitrator contesting, inter alia, the arbitrator's jurisdiction. Pamco's objection to the arbitrator's jurisdiction was based on the premise that the dispute involved parties in addition to the contractor and subcontractor and was therefore not subject to arbitration pursuant to a clause in the general contract between it and the Public Utility District. Pamco claims that this clause was incorporated into the subcontract. That clause, General Condition 39 of the General Contract, provided in pertinent part:

The adjusted unit price shall be mutually agreed upon between the Contractor, the Engineer and the Owner and shall be based on the Contractor's cost data when verified by the Engineer.

Pamco argues that the mutual agreement necessary to obtain a unit price adjustment involves a party other than the contractor and subcontractor, namely the owner.

The arbitrator reopened the hearing in order to rule on the issues presented in the post-hearing memorandum. Botting was given an opportunity to respond and did so. After considering all the evidence, the arbitrator issued an award in favor of Botting that was confirmed by the trial court.

AT & T Technologies, Inc. v. Communications Workers, --- U.S. ----, 106 S.Ct. 1415, 89 L.Ed.2d 648 (1986), reiterates the principles that govern arbitrability. These principles are derived from the Steelworkers' trilogy. 1 Although initially developed in the field of labor law, we find them equally pertinent to commercial arbitration. These principles are: (1) the duty to submit a matter to arbitration arises from the contract itself; (2) the question of whether parties have agreed to arbitrate a dispute is a judicial one unless the parties clearly provide otherwise; (3) a court should not determine the underlying merits of a dispute in determining the arbitrability of an issue; and (4) arbitration of disputes is favored by the courts.

In the case at bar, the contract provides for arbitration of disputes arising between the contractor, Pamco, and the subcontractor, Botting. In determining whether the parties have agreed to arbitrate a dispute the balance is weighted in favor of arbitration. As the Supreme Court noted in Mitsubishi Motors Corp. v. Soler Chrysler-Plymouth, Inc., 473 U.S. 614, 105 S.Ct. 3346, 3354, 87 L.Ed.2d 444 (1985), "the parties' intentions control, but those intentions are generously construed as to issues of arbitrability." 2

Pamco's assertion that the mere fact that the dispute involves more parties than the contractor and subcontractor automatically precludes the triggering of the arbitration clause is not well taken. Language similar to that employed in the instant contract was recently interpreted by the Ninth Circuit to the contrary. In United States ex rel. Newton v. Neumann Caribbean Int'l, Ltd., 750 F.2d 1422 (9th Cir.1985), the subcontract provided for arbitration "in disputes arising between only the general Contractor and the Sub-Contractor". Neumann, at 1424. In holding the matter to be arbitrable, the court stated:

[E]ven if the rights of Newton cannot be vindicated without consideration of the owner's ... actions, this dispute is between only two parties, the prime contractor and the sub-contractor.

Neumann, at 1425. Even if this construction is not deemed determinative in and of itself, without delving into the substantive merits of the claims, we cannot, on this limited record, determine that this dispute between Pamco and Botting requires the presence of the owner for resolution.

Application of the third Steelworkers' principle--a court should not determine the underlying merits of a dispute in determining the arbitrability of an issue--augurs for upholding the arbitration award in this case. Applying analogous reasoning, Washington courts have held that a court's inquiry into arbitrability is finished when a complaint on its face calls for an interpretation of the agreement . Electrical Workers, 40 Wash.App. at 64, 696 P.2d 1264. Interpretation of the agreement would be required in the instant case to accept Pamco's argument. The inquiry into whether or not each of the items in dispute indeed involved a party other than the contractor/subcontractor is a factual determination best left to the arbitrator.

The inexorable presumption in favor of arbitration also applies:

The threshold question of arbitrability is one of law, and a reviewing court is obligated to make its own determination of the issue.... [W]e agree ... that, where the...

To continue reading

Request your trial
20 cases
  • Chloe Z Fishing Co. v. Odyssey re (London) Ltd.
    • United States
    • U.S. District Court — Southern District of California
    • April 26, 2000
    ...the arbitrability of an issue; and (4) arbitration of disputes is favored by the courts. W.A. Botting Plumbing & Heating Co. v. Constructors-Pamco, 47 Wash.App. 681, 683, 736 P.2d 1100 (1987) (citing AT & T Techs., Inc. v. Communications Workers of Am., 475 U.S. 643, 648, 106 S.Ct. 1415, 89......
  • INTER. ASS'N OF FIRE. v. Spokane Airports
    • United States
    • Washington Supreme Court
    • April 25, 2002
    ... ... See W.A. Botting Plumbing & Heating Co. v. Constructors-Pamco, 47 Wash ... ...
  • Donaldson, Lufkin & Jenrette Futures, Inc. v. Barr
    • United States
    • Illinois Supreme Court
    • October 20, 1988
    ... ... [125 Ill.Dec. 290] 1354, 1356; In re W.A. Botting Plumbing & Heating Co. v. Constructors-Pamco (1987), 47 ... ...
  • Kamaya Co., Ltd. v. American Property Consultants, Ltd., 40801-1-I
    • United States
    • Washington Court of Appeals
    • July 27, 1998
    ...dispute to arbitration: (1) the duty to submit a matter to arbitration arises from the W.A. Botting Plumbing & Heating Co. v. Constructors-Pamco, 47 Wash.App. 681, 683, 736 P.2d 1100 (1987) (citing AT & T Techs., Inc. v. Communications Workers, 475 U.S. 643, 648, 106 S.Ct. 1415, 1418, 89 L.......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT