James Luterbach Const. Co., Inc. v. Adamkus, 84-1223

Citation781 F.2d 599
Decision Date13 January 1986
Docket NumberNo. 84-1223,84-1223
PartiesJAMES LUTERBACH CONSTRUCTION COMPANY, INC., Plaintiff-Appellant, v. Valdas V. ADAMKUS, Regional Administrator for the U.S. Environmental Protection Agency Region V and United States Environmental Protection Agency, Defendants-Appellees.
CourtUnited States Courts of Appeals. United States Court of Appeals (7th Circuit)

Mark M. Camp, Pfannerstill & Camp, Wauwatosa, Wis., for plaintiff-appellant.

Kathleen P. Dewey, Dept. of Justice, Land Div., Washington, D.C., for defendants-appellees.

Before ESCHBACH and COFFEY, Circuit Judges and SWYGERT, Senior Circuit Judge.

ESCHBACH, Circuit Judge.

James Luterbach Construction Co. appeals from a summary judgment for the United States Environmental Protection Agency ("EPA"). The district court held that the EPA properly instructed the Village of East Troy, Wisconsin, to award a contract for a waste-water treatment facility to another bidder. Because Luterbach sought only declaratory and injunctive relief and construction of the facility was substantially completed when the district court entered judgment, we vacate the district court's judgment and remand with directions to dismiss as moot.

I

In February 1981 the EPA, pursuant to Title II of the Clean Water Act of 1977, 33 U.S.C. Sec. 1281(g)(1), awarded the Village of East Troy, Wisconsin, a grant for 75 percent of the construction cost of a waste-water treatment facility. In March 1981 the Village invited construction firms to bid on the project.

The Village informed bidders that the EPA's Minority Business Enterprises ("MBE") policy, see 43 Fed.Reg. 60220 (1978), set as a goal participation by minority businesses in ten percent of the cost of the work under the contract. The Village instructed bidders to strive to comply with the ten percent goal, to state in the bid whether the goal would be met, and, if the goal could not be met, to document efforts taken by the bidder to encourage minority participation and reasons for failing to meet the goal. The bidding instructions, which the Village adopted from those recommended by the EPA's regional office, stated in pertinent part:

Failure to submit such [MBE] information shall be deemed, relative to MBE compliance, nonresponsive.

....

Failure to submit such [MBE] information may cause rejection of the bid as nonresponsive.

Instructions to Bidders Sec. 21(B)(1), (C)(1) (emphasis added).

The Village opened the bids for the waste-water treatment facility in April 1981. Joseph Lorenz, Inc. ("Lorenz") submitted the low bid. However, Lorenz listed minority participation as zero percent and did not document efforts taken to encourage minority participation or reasons that the goal was not met. The bid submitted by James Luterbach Construction Co. ("Luterbach") was the second lowest. It listed minority participation as 0.009 percent and documented efforts to encourage minority participation and reasons for not meeting the MBE goal. Following the opening of the bids, both Lorenz and Luterbach informed the Village of errors in their statements of MBE participation. Lorenz's should have been 10 percent, instead of 0 percent. Luterbach's should have been 0.9 percent, rather than 0.009 percent.

In May 1981 the Village rejected Lorenz's bid as "nonresponsive" for failure to comply with the MBE participation requirements. "Bid responsiveness" and "bidder responsibility" are terms of art used in government procurement contracts. A bid is responsive if the bidder promises to do exactly what the bidding instructions demand. A bidder is responsible if it can perform the contract as promised. Whereas bidder responsibility is determined on the basis of information available before or after submission of the bid, bid responsiveness is determined only by facts available prior to or at the opening of the bid. Lorenz filed a protest to this decision with the Village pursuant to 40 C.F.R. 35.939. After a public hearing, the Village affirmed its decision that Lorenz's bid was nonresponsive and denied the protest.

Lorenz and its proposed minority business enterprise subcontractor then filed requests for review of the Village's decision with the EPA's Regional Administrator. Valdas Adamkus, then the Acting and now the Regional Administrator, adopted the report and recommendation of the EPA Regional Counsel and reversed the Village's decision in July 1981. Adamkus decided that the bidding instructions were ambiguous as to whether compliance with the MBE reporting requirements was a matter of bid responsiveness or of bidder responsibility. The Regional Administrator reasoned that the bidding instructions created this ambiguity by stating that noncompliance "may cause rejection," rather than stating that noncompliance shall cause rejection of the bid. EPA regulations provide that the "grantee shall not reject a bid as nonresponsive for failure to list or otherwise indicate the selection of a subcontractor(s) or equipment, unless the grantee has unambiguously stated in the solicitation document that such failure to list shall render a bid nonresponsive and shall cause rejection of the bid." 40 C.F.R. 35.938-4(h)(6) (emphasis added). The Regional Administrator, however, did not address the additional language in the bidding instructions that "[f]ailure to submit such information shall be deemed, relative to MBE compliance, nonresponsive." He noted that bidders may provide post-bid documentation on matters of bidder responsibility, but cannot supplement matters of bid responsiveness. Lorenz supplemented its bid in the reasonable belief that MBE documentation was a matter of bidder responsibility, rather than bid responsiveness. He therefore concluded that the Village improperly rejected Lorenz's bid as nonresponsive. The Regional Administrator thus instructed the Village, pursuant to 40 C.F.R. Sec. 35.939(e)(5), to award the contract to Lorenz.

Having learned that the Village would abide by the Regional Administrator's determination, Luterbach filed suit in August 1981 against Adamkus, the Environmental Protection Agency, the Village and the President of the Village Board, Kenneth Pluess. In its complaint Luterbach sought a declaratory judgment that it should be awarded the contract, and requested preliminary and permanent injunctions enjoining the award of the contract and the payment of any public funds to Lorenz. Luterbach did not, however, seek damages. The district court dismissed the Village and Pluess as defendants in January 1982. Luterbach does not now appeal from that dismissal order. In January 1984, two years later, the district court granted the remaining federal defendants' motion for summary judgment. James Luterbach Construction Co. v. Adamkus, 577 F.Supp. 869 (E.D.Wis.1984). It held that the Regional Administrator had a reasonable basis for his decision. Id. at 872. Luterbach appeals from this judgment.

The district court did not address the EPA's argument in its motion for summary judgment that the completion of the plant mooted Luterbach's suit. Nonetheless, the uncontested affidavit of James Jensen, Engineer for the Village of East Troy, submitted in support of defendants' motion for summary judgment, states that as of June 1983 "fully 98 [percent] of all construction work was completed on the sewerage treatment plant" and that the "facility is now fully operational, having first gone 'on-line' on March 15, 1983."

II

Luterbach seeks a declaratory judgment that it should have been awarded the construction contract on the basis that the EPA improperly applied federal regulations, instead of Wisconsin law, when it instructed the Village of East Troy to award the contract to Lorenz. Luterbach, however, does not dispute that construction of the wastewater treatment facility has been completed. In light of this fact, neither a declaratory judgment that the EPA incorrectly instructed the Village to grant the contract to Lorenz, nor an injunction barring the award of the contract or the payment of public funds to Lorenz, which Luterbach had requested in its complaint, would afford Luterbach relief.

Luterbach did not seek damages in its complaint or on any other occasion before the district court. Indeed, it stated in its complaint that it had no adequate remedy at law other than a declaratory judgment. Complaint p 5. In an attempt to avoid mootness, Luterbach asks for damages for the first time on appeal. We will not consider Luterbach's prayer for damages because it was not brought before the district court. See Walker v. Maccabees Mutual Life Insurance Co., 753 F.2d 599, 602 (7th Cir.1985). Because a declaratory judgment and an injunction cannot afford Luterbach relief and because its claim for damages is not properly before us, Luterbach's suit is moot.

Luterbach, however, urges that its claim is not moot because it is capable of repetition, yet evading review. See Southern Pacific Terminal Co. v. ICC, 219 U.S. 498, 515, 31 S.Ct. 279, 283, 55 L.Ed. 310 (1911). Before we can find that a claim is not moot on the ground that it is capable of repetition yet evading review, two conditions must be met: " 'the challenged action was in its duration too short to be fully litigated prior to its cessation...

To continue reading

Request your trial
35 cases
  • Great West Contractors Inc. v. Irvine Unified Sch. Dist.
    • United States
    • California Court of Appeals Court of Appeals
    • December 1, 2010
    ...of bid responsiveness, as shown by its need to cite to a Seventh Circuit opinion from the Midwest, James Luterbach Constr. Co. v. Adamkus (7th Cir.1986) 781 F.2d 599 ( Luterbach ) for the definition: "A bid is responsive if it promises to do what the bidding instructions demand." ( Taylor B......
  • Am. Civil Liberties Union of Mass. v. U.S. Conference of Catholic Bishops
    • United States
    • U.S. Court of Appeals — First Circuit
    • January 15, 2013
    ...that contract's expiration. See, e.g., Columbian Rope Co. v. West, 142 F.3d 1313, 1316–17 (D.C.Cir.1998); James Luterbach Constr. Co., Inc. v. Adamkus, 781 F.2d 599, 602 (7th Cir.1986); cf. Air Line Pilots Ass'n, Int'l v. UAL Corp., 897 F.2d 1394, 1398 (7th Cir.1990) ( “[W]e agree that if t......
  • Bader v. Wernert
    • United States
    • U.S. District Court — Northern District of Indiana
    • April 14, 2016
    ...a motion for a preliminary injunction separate from the prayer for relief contained in the complaint.” James Luterbach Const. Co. v. Adamkus , 781 F.2d 599, 603 n. 1 (7th Cir.1986). This suggests that strict congruity between a movant's complaint (specifically the prayer for relief) and mot......
  • Great West Contractors Inc v. Irvine Unified Sch. Dist.
    • United States
    • California Court of Appeals Court of Appeals
    • August 31, 2010
    ...of bid responsiveness, as shown by its need to cite to a Seventh Circuit opinion from the Midwest, James Luterbach Constr. Co. v. Adamkus (7th Cir. 1986) 781 F.2d 599 (Luterbach) for the definition: "A bid is responsive if it promises to do what the bidding instructions demand." (Taylor Bus......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT