Ceco Concrete Const. v. JT Schrimsher Const.

Decision Date02 June 1992
Docket Number1:92-cv-359-CAM.,No. 1:92-cv-140-CAM,1:92-cv-140-CAM
Citation792 F. Supp. 109
PartiesCECO CONCRETE CONSTRUCTION, A DIVISION OF ROBERTSON-CECO CORPORATION, Plaintiff, v. J.T. SCHRIMSHER CONSTRUCTION COMPANY, INC., Defendant. J.T. SCHRIMSHER CONSTRUCTION COMPANY, INC., Plaintiff, v. CECO CONCRETE CONST., A DIVISION OF THE ROBERTSON-CECO CORPORATION, Defendant.
CourtU.S. District Court — Northern District of Georgia

Randall Frederick Hafer, Robert Clinton Chambers, Smith Currie & Hancock, Atlanta, Ga., for plaintiff.

Thomas Bart Gary, April Rich, Drew Eckl & Farnham, Atlanta, Ga., for defendant.

ORDER

MOYE, District Judge.

In these consolidated cases Ceco Concrete Construction Company seeks to have an arbitration award confirmed; Schrimsher Construction Company seeks to have it vacated.

It is conceded that the arbitration under the construction contract rules of the American Arbitration Society involved a dispute relating to a construction contract involving interstate commerce within the meaning of the Federal Arbitration Act, 9 U.S.C. section 1 et seq (Brief of J.T. Schrimsher Construction Company, Inc., in support of its motion to dismiss plaintiffs complaint and application for confirmation of award of arbitrators, filed February 24, 1992, pp. 4-5). Thus "federal law applies to all questions of interpretation, construction, validity, revocability and enforceability" (underscoring added), Coenen v. R.W. Pressprich & Co., 453 F.2d 1209, 1211 (C.A.2, 1972), cert. den. 406 U.S. 949, 92 S.Ct. 2045, 32 L.Ed.2d 337. "In deciding the question of arbitrability, the federal policy is to construe liberally arbitration clauses to find that they cover disputes reasonably contemplated by their language, and to resolve doubts in favor of arbitration," Coenen, supra, 453 F.2d at 1212, citing Metro Industrial Painting Corp. v. Terminal Construction Co., 287 F.2d 382, 385 (2d Cir., 1961).

Schrimsher argues first in support of its motion to dismiss and application to vacate, that it was entitled to a postponement of the arbitration proceeding because otherwise it would likely be exposed to the possibility of conflicting results with the owner on the one hand and Ceco on the other (Schrimsher's application to vacate arbitration award, par. 19). The thrust of this argument is that, at the time of the arbitration proceeding, cleanup "costs to correct Ceco's defective work were still being incurred and the issue of delay damages as between Schrimsher and Ceco could not reasonably be determined until that same issue had been resolved between Schrimsher and the owner, Auburn University" (application to vacate, par. 17).

9 U.S.C. section 10(a) provides that an arbitration award may be vacated.

"* * * (3) Where the arbitrators were guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown ..."

The Court does not believe such a situation has been shown here. By its motion to vacate Schrimsher effectively was seeking a stay of proceedings pending determination of a related proceeding. Such right to a stay does not exist under the Federal Arbitration Act. Volt Info. Sciences v. Leland Stanford Jr. University, 489 U.S. 468, 470, 109 S.Ct. 1248, 1250-1251, 103 L.Ed.2d 488 (1988).1

The granting or denying of an adjournment or postponement falls within the broad discretion of appointed arbitrators. Nyall Storey v. Searle Blatt Ltd., 685 F.Supp. 80, 82 (S.D.N.Y., 1988) citing Fairchild and Co. v. City of Richmond et al., 516 F.Supp. 1305, 1313 (D.D.C., 1981), and Dan River Inc. v. Cal-togs, Inc., 451 F.Supp. 497, 503-504 (S.D.N.Y.1978). Thus, assuming a reasonable basis for the arbitrators' considered decision not to grant a postponement, the Court will be reluctant to interfere with the award on these grounds. Fairchild and Co., supra, at 1313-1314. Although the arbitrators here did not articulate the basis upon which they denied the requested postponement, the Court believes that decision was not unreasonable, and certainly not the product of misconduct. The Court believes that the postponement to permit completion of related administrative proceedings involving only Schrimsher and the owner, if proper at all, was unnecessary. The Court believes all the questions presented under the agreement to arbitrate all disputes with respect to the underlying construction contract, could be decided in the proceeding involving only Schrimsher and Ceco. Schrimsher says it believes some of the delay damages may had been the responsibility of the owner, and if Ceco was damaged thereby that the construction agreement provided that Schrimsher would act as Ceco's conduit to present such claims to the owner. But Ceco claimed only that such damages as it sought were Schrimsher's fault. Had Schrimsher proven in the arbitration proceeding (in which it fully participated, albeit under protest), that the delays where the owner's fault, not Schrimsher's, presumably the arbitrators would have so found, and presumably their award is of damages solely attributable to Schrimsher. Thus, having in mind the purpose of Congress to afford participants to arbitration agreements a prompt, economical and adequate solution of their problems through arbitration if the parties are willing, as here, to accept less certainty of legally correct adjustment, the arbitrators were entirely correct in their decision to refuse postponement pending determination of the related administrative proceedings.

As to Schrimsher's claim that it was continuing to incur costs related to the matters being arbitrated, the Court notes that when the arbitrators were asked to reconsider their refusal to postpone, they informed the parties that, "Should the panel find in favor of Schrimsher in all or in part, the hearings will remain open for...

To continue reading

Request your trial
1 cases
  • Lomax v. Woodmen of World Life Ins. Society
    • United States
    • U.S. District Court — Northern District of Georgia
    • 16 July 2002
    ...Memorial Hospital v. Mercury Constr., 460 U.S. 1, 24-25, 103 S.Ct. 927, 74 L.Ed.2d 765 (1983); Ceco Concrete Construction v. J.T. Schrimsher Construction Co., 792 F.Supp. 109, 110 (N.D.Ga.1992). While arbitration agreements are creatures of contract and must be treated accordingly, courts m......
2 books & journal articles
  • The Clash Between Federal and State Arbitration Law and the Appropriateness of Arbitration as a Dispute Resolution Process
    • United States
    • University of Nebraska - Lincoln Nebraska Law Review No. 77, 2021
    • Invalid date
    ...clauses that provided for arbitration outside of Puerto Rico preempted); Ceco Concrete Constr. v. J.T. Schrimsher Constr. Co. Inc., 792 F. Supp. 109 (N.D. Ga. 1992)(Georgia rule that prohibited the award of attorneys fees in arbitration preempted); Seymour v. Gloria Jean's Coffee Bean Franc......
  • Chapter 3
    • United States
    • Full Court Press Alternative Dispute Resolution in the Work Place
    • Invalid date
    ...is involved, the Federal Arbitration Act preempts this section. See Ceco Concrete Construction v. J.T. Schrimsher Construction Co., 792 F. Supp. 109 (N.D. Ga. 1992).[307] . Hope and Associates v. Black Co., 205 Ga. App. 561, 422 S.E.2d 918 (Ga. 1992).[308] . With regard to mandatory pre-dis......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT