W.R. Cooper General Contractor, Inc. v. U.S.

Decision Date05 April 1988
Docket NumberNo. 87-1473,87-1473
Citation843 F.2d 1362
Parties28 Wage & Hour Cas. (BN 1135, 109 Lab.Cas. P 35,088 W.R. COOPER GENERAL CONTRACTOR, INC., Plaintiff-Appellant, v. The UNITED STATES, Defendant-Appellee.
CourtU.S. Court of Appeals — Federal Circuit

Richard I. Manas, Manas & Marcus, P.A., Miami, Fla., argued, for plaintiff-appellant.

Tamra Phipps, Commercial Litigation Branch, Dept. of Justice, Washington, D.C., argued, for defendant-appellee. With her on the brief were Richard K. Willard, Asst. Atty. Gen., David M. Cohen, Director and Mary Mitchelson, Asst. Director.

Before SMITH, BISSELL, and ARCHER, Circuit Judges.

BISSELL, Circuit Judge.

W.R. Cooper General Contractor, Inc. (Cooper) appeals the judgment of the United States Claims Court dismissing its complaint. See W.R. Cooper Gen. Contractor, Inc. v. United States, 12 Cl.Ct. 406 (1987). We vacate and remand.

BACKGROUND

Cooper was a subcontractor for Garcia-Allen Construction Company (Garcia-Allen), the prime contractor under a contract with the City of Miami Beach (the City), Florida. The prime contract, known as the Washington Avenue Revitalization Project (the Project), involved federal funds. Under the subcontract, Cooper installed a sprinkler system in 1981 and 1982 on the median strip of a roadway.

The Project, including subcontracts, was subject to the prevailing wage provisions of 42 U.S.C. Secs. 1440(g), 5310 (1982) and the overtime provision of 40 U.S.C. Sec. 328 (Supp. III 1985). Due to a Department of Labor (DOL) investigation concluding that Cooper had violated the cited statutes, DOL requested in May and June of 1982 that the City withhold payments to Garcia-Allen in the amount Cooper was due for work performed, which the City did.

On June 17, 1982, the City placed the disputed funds in escrow. On March 16, 1983, Garcia-Allen released any claim to the escrowed money, or alternatively, assigned its rights in the funds to the federal government. Thereafter, on September 27, 1983, the City remitted these funds to DOL.

In seeking to recover the funds, Cooper initially brought suit against Garcia-Allen, the City, and the Secretary of Labor in a Florida state court. The Secretary, however, removed the action to federal district court in Florida. On the government's motion, that court dismissed the claim against the United States because it determined that jurisdiction for the claim rested exclusively in the Claims Court. The court, moreover, remanded the remaining claims to state court.

On September 25, 1986, Cooper filed a complaint in the Claims Court. On the government's motion to dismiss for lack of jurisdiction under Fed.R.Civ.P. 12(b)(1), however, the Claims Court held that there was no Tucker Act jurisdiction for Cooper's claim. Cooper, 12 Cl.Ct. at 408-11. Subsequently, Cooper appealed.

OPINION

In cases such as this in which a party has moved to dismiss for lack of jurisdiction, we must consider the facts alleged in the complaint to be correct. Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974); Air Products and Chemicals, Inc. v. Reichhold Chemicals, Inc., 755 F.2d 1559, 1562 n. 4, 225 USPQ 121, 123 n. 4 (Fed.Cir.), cert. denied, 473 U.S. 929, 106 S.Ct. 22, 87 L.Ed.2d 700 (1985). If these facts reveal any possible basis on which the non-movant might prevail, the motion must be denied. Scheuer, 416 U.S. at 236, 94 S.Ct. at 1686.

Here the complaint alleges the following. A dispute existed between DOL and Cooper over Cooper's alleged labor violations. As a result, DOL requested that the City withhold certain payments technically owed to Garcia-Allen as the prime contractor, but actually designated to compensate Cooper for work performed. The City escrowed these funds, after which DOL...

To continue reading

Request your trial
7 cases
  • LW Constr. of Charleston, LLC v. United States, 14-960C
    • United States
    • U.S. Claims Court
    • 31 Julio 2018
    ...evidence to support the claims." TS Infosys., Inc. v. United States, 36 Fed. Cl. at 572 (quoting W.R. Cooper Gen. Contractor, Inc. v. United States, 843 F.2d 1362, 1364 (Fed. Cir. 1988)) (plaintiff's motion to dismiss government's counterclaims under the FCA, Contract Disputes Act, and Forf......
  • Harvey v. United States
    • United States
    • U.S. Claims Court
    • 20 Agosto 2020
    ...cert. denied, 516 U.S. 820 (1995); Hamlet v. United States, 873 F.2d 1414, 1416 (Fed. Cir. 1989); W.R. Cooper Gen. Contractor, Inc. v. United States, 843 F.2d 1362, 1364 (Fed. Cir. 1988) ("When the facts alleged in the complaint reveal 'any possible basis on which the non-movant might preva......
  • Atlas Corp. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 2 Febrero 1990
    ...there can be no implied agreement to pay costs over and above those prices. Unlike the complaint in W.R. Cooper Gen. Contractor, Inc. v. United States, 843 F.2d 1362 (Fed.Cir.1988), the plaintiffs' allegations and admissions in their complaints do not even raise the possibility of the exist......
  • Massie v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 29 Enero 1999
    ...reveal any possible basis on which the non-movant might prevail," we must uphold the court's denial. W.R. Cooper Gen. Contractor, Inc. v. United States, 843 F.2d 1362, 1364 (Fed.Cir.1988). The Tucker Act grants the Court of Federal Claims jurisdiction over actions "founded either upon the C......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT