Wilson Elec. Contractors, Inc. v. Minnotte Contracting Corp.

Decision Date27 June 1989
Docket NumberNo. 88-3958,88-3958
Citation878 F.2d 167
PartiesWILSON ELECTRICAL CONTRACTORS, INC., Plaintiff-Appellee, v. MINNOTTE CONTRACTING CORPORATION, Defendant-Appellant.
CourtU.S. Court of Appeals — Sixth Circuit

James R. Cooper, John T. Wallace (argued), Morrow, Gordon & Byrd, Newark, Ohio, for plaintiff-appellee.

Patricia A. Davidson, Vorys, Sater, Seymour & Pease, Columbus, Ohio, George E. Yokitis (argued), Kenneth K. Kilbert, Babst, Calland, Clements & Zomnir, Pittsburgh, Pa., for defendant-appellant.

Before MARTIN and BOGGS, Circuit Judges; and CONTIE, Senior Circuit Judge.

BOYCE F. MARTIN, Jr., Circuit Judge.

Minnotte Contracting Corporation appeals the district court's denial of its motion to reconsider the Magistrate's order denying a stay of proceedings pending arbitration of this breach of contract dispute. We reverse and direct that a stay pending arbitration be issued.

On November 7, 1986, Wilson Electrical Contractors, Inc., an electrical contractor located in Granville, Ohio, entered into a contract with Minnotte, a commercial contractor based in Pittsburgh, under which Wilson was to work as a subcontractor for Minnotte on a construction project for American Electric Power in Conesville, Ohio. Article 28.1 1 of this contract provided that Minnotte had the option to arbitrate any controversy or claim arising out of or relating to the contract or a breach of the contract.

In September 1987, Wilson filed a complaint against Minnotte in Ohio state court alleging that Minnotte breached the contract by wrongfully terminating it and by excluding Wilson from the contract site and that Minnotte had failed to pay money owed under the contract. The case was removed to federal district court on the basis of diversity of citizenship. Alleging application of the Federal Arbitration Act, 9 U.S.C. Secs. 1-14, Minnotte filed a motion to stay the court proceedings pending arbitration. On April 19, 1988, a Magistrate denied Minnotte's motion, concluding that the parties' arbitration clause within the contract was an independent and separable contract which required mutual consideration to be found solely within that clause. Because the arbitration clause required only Wilson, at the election of Minnotte, to submit all controversies regarding the contract to arbitration, the Magistrate concluded that the clause lacked consideration and was therefore invalid and unenforceable. Minnotte then filed objections and a motion to reconsider the Magistrate's order in district court. On September 15, 1988, the district court denied Minnotte's objections and motion for reconsideration.

Section Two of the Federal Arbitration Act, 9 U.S.C. Sec. 2, provides that a written provision in a contract evidencing a transaction involving commerce, which calls for arbitration of controversies arising out of such contract or transaction, "shall be valid, irrevocable, and enforceable, save upon such grounds as exist at law or in equity for the revocation of any contract." It is undisputed that the contract at issue in this case was a contract evidencing a transaction involving commerce, and we agree with Minnotte, contrary to the decision of the district court, that the arbitration provision in the contract between Wilson and Minnotte is valid and enforceable.

We believe the district court erred in relying on the Supreme Court's decision in Prima Paint Corp. v. Flood & Conklin Mfg. Co., 388 U.S. 395, 87 S.Ct. 1801, 18 L.Ed.2d 1270 (1967), to deny Minnotte's motion to reconsider the Magistrate's order denying a stay of court proceedings pending arbitration. In Prima Paint, the parties had signed a contract containing an arbitration provision; one party claimed that there had been fraud in the inducement of the entire contract, although there was no claim of fraudulent inducement to enter into the arbitration agreement itself. The Court held that the language and policies of the Federal Arbitration Act required the conclusion that the issue of fraud in the inducement was arbitrable. Thus, the Court in Prima Paint upheld an arbitration clause in a contract that was allegedly invalid because of a claim of fraud in the inducement of the entire contract. We believe that the district court erred in applying this decision to strike down the arbitration clause in the otherwise valid contract between Minnotte and Wilson.

Contrary to Wilson's assertion, Prima Paint does not require separate consideration for an arbitration provision contained within a valid contract. Prima Paint may, as Wilson contends, arguably be interpreted as implying that an arbitration clause is an independent contract that is separable from the main contract in which it is found and therefore must have all of the essential elements of a contract, including consideration. 2 Prima Paint, 388 U.S. at 409-411, 87 S.Ct. at 1808-1810 (J. Black dissenting.) Such an interpretation of Prima Paint would, however, clearly be...

To continue reading

Request your trial
34 cases
  • Doctor's Associates, Inc. v. Distajo
    • United States
    • United States Courts of Appeals. United States Court of Appeals (2nd Circuit)
    • September 28, 1995
    ...arbitration cases. Most courts facing this issue have arrived at the same conclusion. See, e.g., Wilson Elec. Contractors, Inc. v. Minnotte Contracting Corp., 878 F.2d 167, 168 (6th Cir.1989); Becker Autoradio U.S.A., Inc. v. Becker Autoradiowerk GmbH, 585 F.2d 39, 47 (3d Cir.1978); W.L. Jo......
  • Hafer v. Mortgage
    • United States
    • U.S. District Court — Southern District of Texas
    • June 24, 2011
    ...173, 183 (3d Cir.1999); Doctor's Assoc., Inc. v. Distajo, 66 F.3d 438, 451–53 (2d Cir.1995); Wilson Elec. Contractors, Inc. v. Minnotte Contracting Corp., 878 F.2d 167, 168–69 (6th Cir.1989); Young v. Jim Walter Homes, Inc., 110 F.Supp.2d 1344, 1350 (M.D.Ala.2000); Pridgen v. Green Tree Fin......
  • Lozada v. Dale Baker Oldsmobile, Inc.
    • United States
    • U.S. District Court — Western District of Michigan
    • March 27, 2000
    ...Circuit has rejected the notion that arbitration clauses must be mutual to be enforceable. See Wilson Elec. Contractors, Inc. v. Minnotte Contracting Corp., 878 F.2d 167, 169 (6th Cir.1989) (rejecting notion that arbitration clause requires separate consideration, but acknowledging that pla......
  • Cheek v. United Healthcare
    • United States
    • Court of Appeals of Maryland
    • November 13, 2003
    ...consideration for the contract as a whole would cover the arbitration clause as well); Wilson Electrical Contractors, Inc. v. Minnotte Contracting Corp., 878 F.2d 167, 169 (6th Cir.1989) (finding that arbitration clause within larger contract did not require consideration independent from c......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT