Firestone Tire & Rubber Company v. United States
Decision Date | 11 June 1971 |
Docket Number | No. 246-69.,246-69. |
Parties | The FIRESTONE TIRE & RUBBER COMPANY v. The UNITED STATES. |
Court | U.S. Claims Court |
Loren K. Olson, Washington, D. C., attorney of record, for plaintiff.
R. W. Koskinen, Washington, D. C., with whom was Asst. Atty. Gen. L. Patrick Gray, III, for defendant.
Before COWEN, Chief Judge, and LARAMORE, DURFEE, DAVIS, COLLINS, SKELTON, and NICHOLS, Judges.
ON PLAINTIFF'S MOTION AND DEFENDANT'S CROSS MOTION FOR SUMMARY JUDGMENT
This is a Government contracts case wherein plaintiff, a body corporate of the State of Ohio, seeks review of an adverse decision rendered by the Armed Services Board of Contract Appeals (hereinafter the Board or ASBCA), under the provisions of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1964). In the proceedings before the Board, the parties filed a Stipulation of Facts which has been incorporated in major part below. The controversy focuses upon the proper and reasonable interpretation of the Price Escalation clause which became an integral part of the contract in suit.
On May 14, 1965, defendant, acting through the United States Army Tank-Automotive Center, issued an Invitation for Bids for the production and delivery of Shoe Assemblies, Rubber, Track, for tanks. At the time the invitation for bids was issued, as stated therein, defendant had a present two-year requirement for track shoe assemblies. The invitation further stated that the contract would be awarded to fulfill this requirement either in whole on a multi-year basis identified as Alternate A in the bid schedule, or in part on a single-year basis identified as Alternate B. Alternate A of the bid schedule was divided into two Program Year increments; the first year increment consisting of 224,886 track shoe assemblies and the second year increment consisting of an additional 243,000 assemblies. Defendant reserved the right to increase the quantity of each program year by not more than 50 percent.
The invitation for bids further provided that in the event an award was made under Alternate A, the contract would be subject to the Limitation of Price and Contractor Obligations clause which stated:
The invitation required that bids be submitted for the entire quantity of each item under both Alternates A and B, or for Alternate B only. In addition, bidders were instructed to submit identical unit price bids for each of the two Program Year increments covered by Alternate A, i. e., the second year increment was to be bid at the same unit price as that submitted for the first year increment. However, the invitation for bids provided that in the event award was made under Alternate A, the contract would be written on a firm fixed price basis, subject to the contract provision entitled "Price Escalation" for the second program year.
Plaintiff submitted identical unit price bids of $23.33 for each of the two Program Year increments. In view of the provision for price escalation, plaintiff's bid included no contingency allowance in the unit prices to cover possible fluctuations in cost which might occur during the second year of performance. As low bidder, plaintiff was awarded the contract on July 1, 1965.
Pursuant to the conditions outlined in the invitation for bids, plaintiff was notified, by Change Order dated July 5, 1965, that the second year increment had been funded and production of the same was accordingly authorized. By Change Order dated May 31, 1966, defendant exercised its option to increase the quantity of the second year increment by 50 percent.
The Price Escalation clause set forth in the invitation for bids and in the contract is as follows:
All of the contract documents, including the language of the Price Escalation clause, were prepared by defendant without the advice or consultation of plaintiff. Plaintiff did not question any clause or seek clarification or amendment of any language prior to award of the contract.
The "Wholesale Prices and Price Indexes" (hereinafter Index) referred to in the Price Escalation clause is designed to measure average changes in prices of all commodities sold in primary markets of the United States. Specifically, it compiles and publishes wholesale price indexes for "commodity groups", e. g., reference 10, Metals and Metal Products; "subgroups", e. g., reference 101, Iron and Steel; "product classes", e. g., reference 1014, Finished Steel Products; and "individual commodities", e. g., reference 1014-37.03, Bars, H.R., Alloy (described below as Steel, Forging). Each individual commodity in the index is representative of a class of prices and is assigned its own statistical weight plus the statistical weights of other commodities not directly priced but whose prices are known or assumed to move similarly. The statistical weight for the product class is the total of the statistical weights of the individual commodities included in the product class. The price index for the product class "Finished Steel Products" (reference 1014), is the statistically weighted average of the individually weighted price indexes of approximately 50 individual commodities, at least three, but no more than five of which are used in the manufacture of track shoe assemblies.2
Approximately 63 pounds of steel were required in the manufacture of each track shoe assembly. The component breakdown by weight, including the applicable individual commodity reference in the Index, is set forth in the following table:
___________________________________________________________________________________________ Component Approximate Specified Applicable weight steel price index ___________________________________________________________________________________________ Tube ______________________ 10½ pounds __________ Carbon Steel Tubing _____ 1014-63.04 Pins ______________________ 16½ pounds __________ Steel, Forging __________ 1014-37.03 or Tubing, Steel, Alloy, Not indexed Seamless End Plate, Center Guide, 28 pounds _____________ Steel, Forging __________ 1014-37.03...
To continue reading
Request your trial-
Stathis v. United States
...its interpretation.'" Beta Sys., Inc. v. United States, 838 F.2d 1179, 1185 (Fed. Cir. 1988) (quoting Firestone Tire & Rubber Co. v. United States, 444 F.2d 547, 551 (Ct. Cl. 1971)); Alvin, Ltd. v. United States Postal Serv., 816 F.2d 1562, 1565 (Fed. Cir. 1987) ("In the case of contracts, ......
-
Bruhn NewTech v. United States, 16-783C
...(Fed. Cir. 2010) (quoting Beta Sys., Inc. v. United States, 838 F.2d 1179, 1185 (Fed. Cir. 1988) (quoting Firestone Tire & Rubber Co. v. United States, 195 Ct. Cl. 21, 30 (1971))); Alvin, Ltd. v. U.S. Postal Serv., 816 F.2d 1562, 1565 (Fed. Cir. 1987) ("In the case of contracts, the avowed ......
-
Valley Realty Co. v. United States
...its interpretation.'" Beta Sys., Inc. v. United States, 838 F.2d 1179, 1185 (Fed. Cir. 1988) (quoting Firestone Tire & Rubber Co. v. United States, 444 F.2d 547, 551 (Ct. Cl. 1971)); Alvin, Ltd. v. United States Postal Service, 816 F.2d 1562, 1565 (Fed. Cir. 1987) ("In the case of contracts......
-
Oasis Int'l Waters, Inc. v. United States
...Cir. 2010) (quoting Beta Sys., Inc. v. United States, 838 F.2d 1179, 1185 (Fed. Cir. 1988) (quoting Firestone Tire & Rubber Co. v. United States, 195 Ct. Cl. 21, 30, 444 F.2d 547, 551 (1971))); Alvin, Ltd. v. United States Postal Serv., 816 F.2d 1562, 1565 (Fed. Cir. 1987) ("In the case of ......