H&J Contracting, Inc. v. Jacobs Eng'g Grp., Inc.

Decision Date28 October 2015
Docket NumberCASE NO. 15-61462-CIV-COHN/SELTZER
CourtU.S. District Court — Southern District of Florida
PartiesH and J CONTRACTING, INC., For itself and as Assignee of BROWARD COUNTY, FLORIDA, Plaintiff, v. JACOBS ENGINEERING GROUP, INC., As itself and as Asignee of EDWARDS & KELCEY, INC., Defendants.
ORDER

THIS CAUSE has come before the Court upon the Motion to Dismiss and Motion to Strike Jury Trial DE [9] of the Defendant, Jacobs Engineering Group, Inc., as itself and assignee of EDWARDS & KELCEY, INC. (hereinafter "Jacobs"). This is an action for breach of contract, indemnity and negligence brought by the Plaintiff, H and J Contracting, Inc. ("H & J"). Jurisdiction is based upon diversity of citizenship. 28 U.S.C. § 1332. Jacobs moves to dismiss the Complaint on the grounds that H & J lacks standing to sue and fails to state a claim upon which relief can be granted for common law indemnity. Jacobs also moves to strike H & J's demand for jury trial.

To survive a Rule 12(b)(6) motion to dismiss, a plaintiff must plead sufficient facts to state a claim that is "plausible on its face." Aronson v. Celebrity Cruises, Inc., 30 F. Supp. 3d 1379, 1392 (S.D. Fla. 2014), quoting Ashcroft v. Iqbal, 556 U.S. 662, 678, 129 S.Ct. 1937, 173 L.Ed.2d 868 (2009)(quoting Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570, 127 S.Ct. 1955, 167 L.Ed.2d 929 (2007)). The Court's consideration is limited to the allegations in the complaint. See GSW, Inc. v. Long Cnty., 999 F.2d 1508, 1510 (11th Cir.1993). All factual allegations are accepted as true and all reasonable inferences are drawn in the plaintiff's favor. See Speaker v. U.S. Dep't of Health & Human Servs. Ctrs. for Disease Control & Prevention, 623 F.3d 1371, 1379 (11th Cir.2010); see also Roberts v. Fla. Power & Light Co., 146 F.3d 1305, 1307 (11th Cir.1998).

This action arises out of a roadway improvement project (the "Project") undertaken by Broward County, Florida ("the County"). The County contracted with Edwards & Kelcey, Inc. ("Edwards & Kelcey") for Edwards & Kelcey to design the Project, including Project drainage. The County and Edwards & Kelcey entered into a Consultant Services Agreement (the "Agreement") which is attached to Plaintiff's Complaint. The Agreement contained an anti-assignment clause:

8.8 Neither this Agreement nor any interest herein shall be assigned, transferred, or encumbered by either party and CONSULTANT shall not subcontract any portion of the work required by this Agreement except as authorized pursuant to Section 8.7.

The Agreement also prohibited modification, amendment or alteration of terms "unless contained in a written document executed with the same formality and of equal dignity herewith." DE [1-2], Ex. A. Jacobs subsequently acquired Edwards & Kelcey and the County, Jacobs and Edwards & Kelcey entered into a written Memorandum of Understanding that Jacobs would be assuming all responsibility under the Agreement. DE [1-2], Ex. B.

H & J is a contractor which bid on, and was awarded, the contract to perform theProject in accordance with the plans and specifications prepared by Jacobs. According to the Complaint, certain defects in the Project drainage design caused the Project to be re-designed by Jacobs. As a result, H & J alleges that it and the County both sustained damages. H & J seeks to recover damages from Jacobs on its own behalf and on behalf of the County, as the County's Assignee under a Settlement Agreement between H & J and the County.

Jacobs moves to dismiss H & J's breach of contract and indemnity claims for lack of standing, due to the fact that Jacobs' Agreement with the County prohibited assignment. Generally, in Florida, "[a]ll contractual rights are assignable unless the contract prohibit assignment, the contract involves obligations of a personal nature, or public policy dictates against assignment." Kohl v. Blue Cross and Blue Shield of Florida, Inc., 988 So.2d 654, 658 (Fla. 4th DCA 2008). However, a contract provision prohibiting the assignment of rights under a contract does not, without more, prohibit the assignment of a claim for damages on account of a breach of contract. Paley v. Cocoa Masonry, Inc., 433 So.2d 70, 71 (Fla. 2d DCA 1983), citingSure Cordis Corp. v. Sonics International, Inc., 427 So.2d 782, 783 (Fla. 3d DCA 1983). "The law draws a distinction . . . between assignment of performance due under a contract and assignment of the right to receive contractual payments." Charles L. Bowman & Co. v. Erwin, 468 F.2d 1293, 1297-98 (5th Cir. 1972).

Jacobs argues that the anti-assignment clause prevents the County from assigning to H & J any claims for damages that it may have against Jacobs, because it prevents assignment of "any interest" under the Agreement: "Neither this Agreementnor any interest herein shall be assigned, transferred, or encumbered by either party...." (emphasis added). See Parrish Chiropractic Centers, P.C. v. Progressive Casualty Ins. Co., 874 P.2d 1049 (Col. 1994)(prohibition of assignment of "interest" in policy precluded assignment of post-loss assignment of policy benefits). The Court disagrees. Florida law clearly distinguishes between assignments of performance and assignments of claims for breach of contract. See Paley, 433 So.2d at 71; Cordis Corp., 427 So.2d at 783.

Although no Florida case addresses specifically the language "any interest herein," the Court finds the Washington case of Berschauer/Phillips v. Seattle Sch. Dist., 124 Wash.2d 816, 881 P.2d 986 (1994) to be instructive and on point. There, a school district contracted with an architect to design a new elementary school. The agreement between the architect and the school district prohibited any "assign[ment], sublet or transfer [of] any interest in th[e] Agreement . . . ." Id. at 829.

The contractor hired by the school district completed construction of the school and subsequently sued the school district for breach of contract alleging, inter alia, that the school district provided incomplete and defective plans. The school district and the contractor settled the contractor's claim, with the school district assigning any claims that it had against the architect to the contractor. The contractor, as assignee of the school district, then sued the architect. The Washington court rejected the architect's argument that the agreement's anti-assignment clause barred the contractor's action. Reasoning that an anti-assignment clause is designed to protect the parties from having to deal with performance by parties with whom they did not contract, the court held thatonce performance under the contract is complete, the anti-assignment clause does not prohibit the assignment of a cause of action for breach of contract. Id. at 830.

The Tennessee court made a similar analysis in Ford v. Robertson, 739 S.W.2d 3 (Tenn. App. 1987):

The law draws a distinction between the right to assign performance under a contract and the right to receive damages for its breach. The nonassignability clause prohibits the assignment or transfer of any "interest in this agreement." This "any interest" language must be construed to mean any interest in the performance of the executory contract.
Plaintiffs contend, and we agree, that this a suit for damages for breach of a fully executed contract and is not a suit for performance by the Architects of an executory contract. What the plaintiffs acquired
...