Louisville & NR Co. v. Sullivan

Decision Date18 June 1979
Docket NumberCiv. A. No. 79-0485.
Citation471 F. Supp. 469
PartiesLOUISVILLE & NASHVILLE RAILROAD CO., Plaintiff, v. John M. SULLIVAN et al., Defendants.
CourtU.S. District Court — District of Columbia

Dennis G. Lyons, James R. McAlee, S. Mark Tuller, Andrew Butz, Washington, D. C., for plaintiff.

John Oliver Birch, Asst. U. S. Atty., Washington, D. C., for defendants.

MEMORANDUM OPINION

GESELL, District Judge.

Louisville & Nashville Railroad Co. ("L&N") has requested the Court to enjoin the operation of an emergency safety order ("Order") which was issued by the Administrator of the Federal Railroad Administration ("FRA") on February 7, 1979, under 45 U.S.C. § 432 without notice or a prior hearing and which substantially affects the Railroad's functions. L&N has moved for summary judgment and injunctive relief on the ground that the Order exceeds the Administrator's authority. L&N accepts for purposes of its motions the accuracy of the lengthy factual findings which accompanied the Order. A purely legal issue is presented and the motions are ripe for decision after full briefs and argument.

I.

The Order under attack is by far the most sweeping order ever issued under the authority of Section 432. Among other things, it places a 30-mile-per-hour speed limit on all trains carrying hazardous materials over tracks owned or leased by L&N, requires that L&N double the frequency of the track inspections it must perform under 49 C.F.R. Part 213, and directs that as soon as practicable the company inspect on foot all of the track over which it transports hazardous material. The "emergency situation" that induced this directive was the railroad's condition which had caused a series of recent derailments, most of which seem to have resulted from track and related deficiencies. These derailments had entailed serious losses of life and property, as well as evacuations of large numbers of people. Shortly after the Order was issued, ex post facto hearings were initiated by FRA, as prescribed by the statute. Following a few days of testimony, however, this proceeding was terminated by mutual consent. Two months later, the hearings were once again reconvened, and apparently continue to date.

Section 432 authorizes the Administrator in an "emergency situation" to issue an ex parte order prohibiting the further use of a specified railroad facility or piece of equipment until the identified unsafe condition is corrected. Although the Order in dispute here recites findings of equipment deficiencies in L&N's system, those deficiencies do not appear to have been or to be FRA's primary concern. Rather, the Order directs its main attention at L&N's tracks, a "facility" within the meaning of the Section. The Section reads as follows:

If through testing, inspection, investigation, or research carried out pursuant to this subchapter, the Secretary determines that any facility or piece of equipment is in unsafe condition and thereby creates an emergency situation involving a hazard of death or injury to persons affected by it, the Secretary may immediately issue an order, without regard to the provisions of section 431(b) of this title, prohibiting the further use of such facility or equipment until the unsafe condition is corrected. Subsequent to the issuance of such order, opportunity for review shall be provided in accordance with section 554 of Title 5.

L&N contends that the February 7, 1979, Order is defective in several respects. First, plaintiff believes that the Order did not respond to the existence of any "emergency situation." Second, the Railroad maintains that the Order improperly fails to designate any particular segment or segments of the L&N track as being defective. Rather, the Order applies to L&N's entire 10,600 miles of track, which trackage, according to plaintiff, could not conceivably be defective in its entirety. Third, plaintiff contends that the Order is regulatory, not prohibitory, and therefore does not fit within the express terms of Section 432. Finally, L&N argues that the Order improperly fails to indicate how L&N can correct the unsafe conditions so generally identified in the Order.

According to plaintiff, the open-ended nature of the Order as promulgated on February 7 has been exacerbated by the manner in which FRA has been administering the Order. When L&N received the Order, it assumed that once it could establish that a segment of its track met existing track safety standards, the Order would then be lifted as to that segment. Accordingly, L&N made several applications for relief, but most of them have encountered unexpected difficulties.

For instance, L&N requested, at various dates commencing March 1, 1979, that modifications be made in the Order with respect to some 1350 miles of its track. L&N's requests represented that these segments had been inspected and had been brought up to full compliance with FRA's Track Safety Standards. At oral argument, the Court took note of the fact that, as of June 5, 1979, these requests were still under agency consideration. Government counsel then indicated that the Administrator—in deciding whether or not to lift particular portions of the Order—considers, not only track conditions, but also inter alia the adequacy of the Railroad's training and maintenance programs and the extent to which the Railroad disciplines employees who violate safety standards; all of this in a generalized effort to upgrade the lower levels of L&N's management to such standards of performance as the Administrator in his subjective judgment might deem appropriate.

On June 11, 1979, FRA filed a revealing Partial Removal Order ("PRO") which simply reaffirmed these statements of counsel. The PRO made painfully clear the open-ended nature of the prohibitions imposed and the uncertainty and lack of precision which apparently govern the Order's present and future application. According to the PRO, before any portion of L&N's track will be completely released from all of the Order's prohibitions (including the crucial limitation on speed), FRA must perform "a thorough investigation of all aspects of railroad operations over that segment that bear on safety, including the condition of track and equipment, adequacy of training and testing of L&N operating personnel, L&N compliance with Federal safety regulations and its own rules, accident history, and the volume and character of hazardous materials moved."...

To continue reading

Request your trial
2 cases
  • United Transp. Union v. Lewis
    • United States
    • U.S. Court of Appeals — Eleventh Circuit
    • 11 Marzo 1983
    ...arising with respect to sleeping quarters. The pre-1980 wording of section 432 addressed facilities or pieces of equipment. In Louisville & N.R.R. v. Sullivan, 13 the United States District Court for the District of Columbia held that Congress did not intend to give the Secretary of Transpo......
  • Louisville & N. R. Co. v. Sullivan
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 8 Enero 1980
    ...in the brake line of the sixth car from the front of the train." (Denver Post, August 21, 1979, p. 26).4 Louisville & Nashville Railroad Co. v. Sullivan, 471 F.Supp. 469, 473 (D.D.C.1979).5 Emergency Order No. 11, at 12-13.The track standards recognize six track classes (the highest being C......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT