D & L CONSTRUCTION CO. v. Triangle Elec. Supply Co.
Decision Date | 22 June 1964 |
Docket Number | No. 17493.,17493. |
Citation | 332 F.2d 1009 |
Parties | D & L CONSTRUCTION COMPANY et al., Appellants, v. TRIANGLE ELECTRIC SUPPLY COMPANY, Inc., Appellee. |
Court | U.S. Court of Appeals — Eighth Circuit |
John A. Biersmith, of Rafter, Biersmith, Miller & Walsh, Kansas City, Mo., for appellant.
Robert D. Youle, of Lathrop, Righter, Gordon & Parker, and Daniel M. Dibble, of Lathrop, Righter, Gordon & Parker, Kansas City, Mo., for appellee.
Before VAN OOSTERHOUT, RIDGE and MEHAFFY, Circuit Judges.
VAN OOSTERHOUT, Circuit Judge.
The issue presented by this appeal taken by defendants D & L Construction Company and its associates and Continental Casualty Company, its performance bond surety, is whether the trial court properly allowed plaintiff Triangle Electric Supply Company, Inc., interest and attorneys' fees upon its claim for materials furnished Mojave Electric Company, Inc., a subcontractor upon a Capehart Housing Project upon which D & L was prime contractor.
Through pleadings, discovery proceedings, stipulations and pretrial conferences, the parties ultimately agreed that the reasonable value of electrical equipment furnished by Triangle to the subcontractor and used on the project is $14,592.12. Triangle's right to judgment for such amount is not questioned. The parties stipulated in regard to their respective claims and the questions for decision as follows:
The court sustained Triangle's motion for summary judgment and entered judgment for Triangle against D & L and its surety for $14,592.12 principal, $2,924.07 interest and $6,000 attorneys' fees.1 This appeal is from such judgment.2
Defendants' statement of points relied upon for reversal reads:
Plaintiff's answer to point "a" is that, for the purpose of solving the issues here presented, it is immaterial whether the Capehart Housing Project provisions are sui generis and that all provisions of the Miller Act may not apply to Capehart Housing. We agree. Continental Cas. Co. v. United States for the Use and Benefit of Robertson Lumber Co., 8 Cir., 305 F.2d 794, relied upon by defendants, has no direct bearing upon the problem we are here considering. There we held that 42 U.S.C.A. § 1594a gave the Secretary of Defense the right to prescribe the form of bond to be furnished on Capehart Projects and that when the bond prescribed and given contained more stringent provisions as to notice to be given than the Miller Act, the procedural provisions of the Capehart bond must be followed. We said nothing about the Miller Act decisions lacking persuasiveness in instances where the Miller Act bond and Capehart bond contained substantially similar provisions. We recognized that the Capehart bond is a bond required by federal law and stated that Congress intended that Capehart should have substantive bond protection essentially similar to that of Miller Act suppliers.
Plaintiff's position is that, to the extent here material, the Capehart bond as prescribed by the Secretary of Defense pursuant to 42 U.S.C.A. § 1594a and given by the prime contractor is in substance the same as that required on Miller Act projects by 40 U.S.C.A. § 270b. The pertinent provisions of the bond here in suit are:
"* * * every claimant * * * who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant\'s work or labor was done or performed or materials furnished by such claimant * * * may sue on this bond * * in the name of the claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon * * *."
The Miller Act, as shown by 40 U.S. C.A. § 270b(a) similarly provides bond coverage for persons furnishing labor or materials "for the sum or sums justly due him."
It reasonably appears that the drafters of the Capehart bond adopted the Miller Act phraseology in the respects here material. Miller Act bonds and Capehart bonds are bonds required by federal law. Each of such bonds are designed to serve substantially the same purpose, that is, to protect parties furnishing labor and material used on federally sponsored projects. Upon the record before us, we believe that the trial court properly determined that "the rules of decision that will be applied to the factual situations involved in the various cases will be the rules of decision developed under the Heard and Miller Act decisions."3 217 F.Supp. 913, 914.
Defendants urge that in any event there are no decisions under the Heard and Miller Act which allow for recovery of pre-judgment interest or attorneys' fees. The bond here in suit clearly permits Triangle to recover sums justly due for material and labor furnished on the project. What is included in the term "justly due" may vary with the facts and circumstances of individual cases. If labor and material is furnished under express contract, the contract will ordinarily measure the sum justly due. Here the court, upon the basis of undisputed evidence, found:
The validity of the court's determination that the contract between Triangle and the subcontractor provided for 6% interest on past due invoices and a reasonable attorneys' fee in event of suit is in no way challenged. With respect to interest, the parties have agreed as to the amount of interest due in the event interest is allowable. The judgment for interest is based upon such agreement.
We agree with the trial court that the contract under which Triangle furnished materials to the...
To continue reading
Request your trial-
Continental Casualty Co. v. Allsop Lumber Co.
...to any relationship between the Miller Act and the Capehart Act." And in the very recent case of D & L Constr. Co. v. Triangle Elec. Supply Co., 332 F.2d 1009, 1011-1012 (8 Cir. 1964), another panel of this court twice referred to a Capehart bond as one "required by federal law". Other Cape......
-
Koppers Company v. Continental Casualty Company
...Supply Co. v. Mojave Elec. Co., 217 F.Supp. 913 (W.D.Mo.1963, Judge Oliver), affirmed under the name of D & L Constr. Co. v. Triangle Elec. Supply Co., 332 F.2d 1009 (8 Cir. 1964); Allsop Lumber Co. v. Continental Cas. Co. (W.D.Mo.1963, Judge Duncan, unreported opinion), affirmed under the ......
-
B. C. Richter Contracting Co. v. Continental Cas. Co.
...its principal, federal decisions under the Miller Act are applicable in actions under Capehart Act bonds (D. & L. Const. Co. v. Triangle Elec. Supply Co., 332 F.2d 1009 (8th Cir. 1964); National State Bank of Newark v. Terminal Const. Corp., supra, 217 F.Supp. at pp. 350-351; United States ......
-
Tropic Builders, Limited v. Naval Ammunition Depot Lualualei Quarters, Inc.
...Casualty Co. v. United States for the Use and Benefit of Robertson Lumber Co., 305 F.2d 794 (8th Cir.); D & L Construction Co. v. Triangle Elec. Supply Co., 332 F.2d 1009 (8th Cir.); Continental Casualty Co. v. Allsop Lumber Co., 336 F.2d 445 (8th Cir.); Lasley v. United States for the Use ......