Frank M. Dorsey & Sons, Inc. v. Frishman, Civ. A. No. 667-65.

Decision Date04 October 1968
Docket NumberCiv. A. No. 667-65.
Citation291 F. Supp. 794
PartiesFRANK M. DORSEY & SONS, INC., Plaintiff, v. Bernard Lyon FRISHMAN, Defendant and Third-Party Plaintiff, v. Arthur PREVILL, Third-Party Defendant.
CourtU.S. District Court — District of Columbia

Erwin A. Alpern, Washington, D. C., for defendant and third-party plaintiff.

Gerald W. Farquhar, Washington, D. C., for third-party defendant.

OPINION

HOLTZOFF, District Judge.

The Court has before it a claim for damages against an engineer for negligence in the preparation of plans for an air conditioning system that, it is claimed, did not operate properly.

The claim is asserted by a third-party complaint. The facts are as follows. A building at 1430 K Street, in the city of Washington, was being constructed under a contract with M. Cladney Construction Company as the principal contractor. The owners of the building were a group of individuals, one of whom was the defendant and third-party plaintiff, Bernard Frishman. He is an architect by profession and was also the architect of the building. Frishman hired Previll, the third-party defendant, an engineer who specialized in air conditioning apparatus, to prepare the plans for the air conditioning system. Previll was an employee of Frishman and worked in his office. In addition to doing Frishman's work he also carried on a business of his own.

It is claimed that the plans prepared by Previll were inadequate, inoperative and defective, and that the air conditioning system installed was inadequate and did not fulfill what was required. The evidence shows that Frishman decided, either in his capacity as architect or in his capacity as part owner, that certain changes should be made in the air conditioning system, and assumed liability for the cost of making the alterations. He engaged the plaintiff, Frank M. Dorsey & Sons, Incorporated, to make the necessary changes.

The plaintiff later brought suit to foreclose a mechanic's lien, and also to recover from the owners of the building of whom Frishman was one, the amount due it for the work ordered by Frishman. Frishman settled the case by paying the amount asserted to be due, namely, the sum of over $19,000. Consequently, the principal case has been disposed of. Frishman asserted a third-party claim against Previll for damages for negligence in preparing defective plans. This third-party claim is now before the Court for adjudication.

It is not denied that Frishman retained Previll to prepare the plans for the air conditioning system, and that Previll did so. Those plans were modified and Previll approved the modifications. An air conditioning system was then installed. It departed from both the original and revised plans. There is a dispute, for example, whether it was necessary to subdivide the air conditioning apparatus on each floor into three zones, or whether a single zone was sufficient. The dispute appears to be more or less academic, because the plaintiff's expert witness, Herbert Arey, admitted that the shop drawings which the plaintiff has introduced in evidence, and which were later revised, did show three zones. Even a layman, by examining those plans, can observe the designations: zone 1, zone 2, zone 3. The system actually installed contained pumps that were located in the penthouse, whereas the specifications and the drawings called for them to be on the first floor.

The evidence showed that the system actually installed did not operate properly and that certain changes were necessary, which Mr. Frishman ordered. There is not sufficient showing, however, that the original plans, which were not followed, or the revised plans, which also were not followed in detail, would not have been satisfactory. There is no evidence that the defects were not due to the departure from the plans. There is no showing that the third-party defendant was guilty of any negligence or lack of due care, or failure to comply with the prevailing standards in his profession.

This brings us to the question what rule should be applied to the liability of an architect or an engineer to his principal. A professional man is not a guarantor of his work. For example, a physician is not liable for damages if he fails to cure his patient. A lawyer is not liable for damages if he fails to win his...

To continue reading

Request your trial
7 cases
  • U.S. v. Decoster
    • United States
    • U.S. Court of Appeals — District of Columbia Circuit
    • 19 d2 Outubro d2 1976
    ... ... 21 In Nader v. Allegheny Airlines, Inc., 167 U.S.App.D.C. 350, 361, 512 F.2d 527, 538 ... ...
  • Ehrenhaft v. Malcolm Price, Inc.
    • United States
    • D.C. Court of Appeals
    • 14 d3 Novembro d3 1984
    ...that degree of skill and care ordinarily used by their colleagues." Id. at 676 (footnote omitted) (citing Frank M. Dorsey & Sons v. Friskman, 291 F.Supp. 794, 796-97 (D.D.C. 1968)). Judge Doyle made no specific findings as to whether Atherton might also be liable under the contract, and acc......
  • Evergreen Eng'g, Inc. v. Green Energy Team LLC
    • United States
    • U.S. District Court — District of Hawaii
    • 31 d2 Julho d2 2012
    ...and liability is not dependant upon whether the “exact results” were obtained. [ Id. at 8–9 (citing Frank M. Dorsey & Sons, Inc. v. Frishman, 291 F.Supp. 794 (D.D.C.1968)).] Evergreen argues that GET's Motion is not merely based in contract, but also involves tort liability: “[p]rofessional......
  • Dansby v. United States
    • United States
    • U.S. District Court — Southern District of New York
    • 24 d4 Outubro d4 1968
    ... ... No. 68 Civ. 2547 ... United States District Court S. D. New ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT