PLS Coat & Suit Corp. v. United States
Citation | 180 F. Supp. 400 |
Decision Date | 20 January 1960 |
Docket Number | No. 213-56,513-56.,213-56 |
Parties | P.L.S. COAT & SUIT CORP. v. UNITED STATES. Arthur S. SACHS, as Trustee in Bankruptcy of Ansonia Garment Co., Inc., Bankrupt v. UNITED STATES. |
Court | Court of Federal Claims |
Edwin J. McDermott, Philadelphia, Pa., for plaintiff in No. 213-56.
Lawrence S. Smith, Washington, D. C., with whom was George Cochran Doub, Asst. Atty. Gen., for defendant.
In these cases plaintiffs seek to recover extra costs alleged to have been incurred in manufacturing raincoats under contracts with the Department of the Navy. Each plaintiff had two contracts under which claims have been made. Plaintiffs allege that their costs were increased because the raincoat material which was furnished by the Government was not in conformity with contract specifications and was otherwise defective.
Defendant has moved for summary judgments dismissing plaintiffs' petitions on the grounds (1) that plaintiffs' claims are barred because of their failure to comply with contract provisions relative to replacement of defective material, failure to obey the contracting officer's written instructions regarding such replacement, and failure to follow the disputes and appeals provision of the contracts; (2) that the decisions of the Armed Services Board of Contract Appeals (ASBCA) on questions of fact relating to the quality of the Government-furnished cloth which decisions were adverse to plaintiffs, should be accorded finality here; and (3) that irrespective of the aforementioned decisions, summary judgments should be granted defendant on the basis of independent documentary evidence now before the court in the form of affidavits and exhibits in support of its motions.
Plaintiffs urge recovery on two grounds: First, that defendant breached the contracts in its failure to furnish non-defective cloth, or second that under applicable contract provisions plaintiff is entitled to an equitable adjustment of the contract prices because of the defective cloth supplied.
With respect to one of the contracts in the PLS case, No. DA30-352-TAP-135, recovery must be denied on the grounds that plaintiff itself has failed to conform to the contract provisions. The applicable provisions are as follows:1
Under these provisions the Government upon proper notice was to have the opportunity to replace defective material, and/or provide for an equitable adjustment of the contract price. The need for a prompt request to the contracting officer is quite obvious. Both provisions make reference to the Changes provision in the contract which provides that any claim by the contractor for adjustment under this clause is to be made within 30 days from the date of receipt of the notification of change by the contractor. However, the Changes provision further states that the contracting officer if he decides the facts warrant it may receive and act upon any such claim at any time prior to final payment. It also provides that failure to agree shall constitute a dispute concerning a question of fact within the Disputes clause of the contract.
Deliveries under this contract were completed May 15, 1953, and final payment was made June 18, 1953. Plaintiff's claim directed to the contracting officer was made on January 12, 1954, some seven months after final payment. It was rejected on the very same grounds which we find applicable here, i. e., that it was untimely under the contract provisions. The ASBCA, despite the Government's assertion of untimeliness, rendered a decision against plaintiff on the merits of the claim. However, the question as to whether plaintiff's claim was timely and in conformity with the contract provisions is one of law which may be decided here. Poloron Products, Inc. v. United States, 116 F.Supp. 588, 126 Ct.Cl. 816, 824. We hold it was not, and plaintiff's petition with regard to its claim under this contract must be dismissed. Adherence must be had to those provisions of Government contracts which provide the mechanics for settling disputes on the administrative level. United States v. Joseph A. Holpuch Co., 328 U.S. 234, 66 S.Ct. 1000, 90 L.Ed. 1192; United States v. Blair, 321 U.S. 730, 735, 64 S.Ct. 820, 88 L.Ed. 1039.
We now pass to a consideration of plaintiffs' claims under the remaining contract in the P.L.S. case and the two contracts in the Sachs case. The ASBCA board in denying plaintiffs' appeals found that the Government-furnished cloth met specifications, and while it did present difficulties in the manufacturing process, it was suitable for use in manufacturing the raincoats called for by the contracts.
Under the Disputes clause of the contract, supra, and the so-called Wunderlich statute, 68 Stat. 81, 41 U.S.C.A. § 321, the board's decision is "final and conclusive unless the same is fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or is not supported by substantial evidence."
In actions where the decision of the board is contested the plaintiffs must as we stated in Volentine & Littleton v. United States, 145 F.Supp. 952, 954, 136 Ct.Cl. 638, "do more than repeat the derogatory language of the statute." Facts must be alleged which if proved will show that under the language of the above statute the board's decision cannot stand.
Taking the position that the petitions fail in this regard and that therefore the board's decision should be accorded finality, defendant has moved for summary judgments on the basis of the board's decision, as well as on the basis of independent documentary evidence attached as exhibits and affidavits to its motions.
Plaintiffs' position in urging a denial of defendant's motions is in the first instance one of...
To continue reading
Request your trial-
Nager Electric Company, Inc. v. United States
...This rule (and its predecessor) have often been enforced at the instance of the defendant. See, e.g., P.L.S. Coat & Suit Corp. v. United States, 180 F.Supp. 400, 148 Ct. Cl. 296 (1960); United Foundation Corp. v. United States, 158 Ct.Cl. 41, 42-43 21 Defendant would have the contractor fil......
-
Anthony Grace & Sons, Inc. v. United States
...independently by the court even though the sole record before the court is the administrative record. P. L. S. Coat & Suit Corp. v. United States, 180 F.Supp. 400, 148 Ct.Cl. 296 (1960); Beacon Construction Co. v. United States, 314 F.2d 501, 161 Ct.Cl. 1 (1963); WPC Enterprises, Incorporat......
-
Timber Access Industries Co., Inc. v. United States
...164 Ct.Cl. 131 (1964); Beacon Construction Co. v. United States, 161 Ct.Cl. 1, 314 F.2d 501 (1963); P.L.S. Coat & Suit Corp. v. United States, 148 Ct.Cl. 296, 180 F.Supp. 400 (1960). 1. CONTRACT Plaintiff first contends that the contract alone controls the method of price redetermination an......
-
United States v. Hamden Co-operative Creamery Co.
...interesting and difficult question whether the district court should have considered this evidence. Compare P. L. S. Coat & Suit Corp. v. United States, 180 F.Supp. 400 (Ct.Cl.1960), and Volentine and Littleton v. United States, 145 F.Supp. 952 (Ct.Cl.1956), with United States Nat'l Bank of......