Central States Power & Light Corp. v. United States Zinc Co.

Citation60 F.2d 832
Decision Date01 August 1932
Docket NumberNo. 519.,519.
PartiesCENTRAL STATES POWER & LIGHT CORPORATION v. UNITED STATES ZINC CO.
CourtUnited States Courts of Appeals. United States Court of Appeals (10th Circuit)

Elmer J. Lundy, of Tulsa, Okl. (L. M. Poe, R. E. Morgan, and Poe, Lundy & Morgan, all of Tulsa, Okl., and Francis E. Matthews, and J. R. Harmon, both of Chicago, Ill., on the brief), for appellant.

Shell Bassett, of Tulsa, Okl., for appellee.

Before LEWIS, COTTERAL, and McDERMOTT, Circuit Judges.

COTTERAL, Circuit Judge.

The Central States Power & Light Corporation brought this action to recover damages of the United States Zinc Company for breach of a contract between S. M. Williams, Jr., and the defendant, dated June 30, 1927, whereby the zinc company was to take and pay him for gas to be used in operation of its smelter at Henryetta, Okl., from October 25, 1927 to October 25, 1930. The contract was in terms binding on the assigns and successors of the parties. The plaintiff acquired the rights of Williams. The issues were framed upon an amended petition, answer, and reply, the cause was tried to a jury, and a verdict was returned for the defendant.

It is assigned as error that the court overruled motions to strike portions of the answer which set up as defenses the oral understanding defendant claimed to have had with Williams that the contract was not to obligate defendant if it discontinued the smelter; that the court treating the contract as ambiguous allowed evidence in support of that defense; that the court charged the jury to consider that evidence and denied plaintiff's request for a peremptory instruction.

The controversy is whether that defense was permissible under the terms of the contract. It designated Williams as vendor and the defendant as vendee. By section 1, the vendor agreed to sell, furnish, and deliver gas to vendee, at 7½ cents per thousand cubic feet, to the limit of vendor's capacity, but not more than a minimum later specified. Section 2 is as follows: "Vendee agrees to receive, purchase and pay for said gas at said price and on the basis above stated, and to take during the first year of the contract at least two million cubic feet of gas per day, and during the second and third years of the contract at least three million cubic feet of gas per day; provided, that, if the total requirements of vendee for gas fuel does not equal or exceed the two or three million per day that vendee shall be required to take only the amount of its total requirements."

Section 5 required the vendor to install and maintain on vendee's premises during the life of the contract all necessary meters, regulators, and equipment. Section 6 provided the contract was to remain in full force and effect for three years from the time the gas was first furnished. By section 7 the vendor was not to be responsible for failure to furnish gas occasioned by breaks in the pipe line, strikes, acts of God, or other unavoidable casualty; and it was understood vendor was to construct a pipe line for transporting the gas to the smelter, that the defendant required a continuous gas supply, and, if vendor's supply should not be delivered continually and for that reason vendee could not operate the smelter continuously and should be compelled to make arrangement for other gas for any part of the minimum, except for reasons stated in paragraph 7, then vendee should not be obligated to take the minimum, as specified in paragraph 2, but might take such amount which, taken with its other supply, should be necessary to operate the smelter.

It was shown at the trial the smelter of defendant was operated since 1916, and that defendant took and paid for the gas under the contract with plaintiff only up to June 1, 1928, when it dismantled and discontinued operation of its plant, and refused to take gas from the plaintiff. There was evidence of other related facts, such as an effort to obtain a reduced rate of the gas, notice discontinuing the purchase of gas, the unprofitable operation of the smelter, etc. The plaintiff showed its outlays made to obtain the gas and to install a pipe line to transmit and furnish the gas and its offer to supply the gas according to the contract. These matters were not questioned.

Certain testimony was received over objection by the plaintiff. F. P. Lannon, defendant's manager, testified to conversations with Williams prior to the execution of the contract. He told Williams the defendant would not sign a contract requiring it to take the gas if the plant should be curtailed, or in case of strike, war, interruption of railroads, etc. Lannon stated that at Williams' request he furnished a letter that he would sign the contract. Williams prepared and presented the contract. Lannon said he told Williams he had written him defendant would not pay for any gas if the plant was curtailed or closed down. Williams said he had taken care of that, read the proviso of section 2 to Lannon, and added, "if you take less than the two or three million you will only pay for what you take and if you close down and don't take any gas you don't pay for any"; that was distinctly understood; and Lannon said, "All right," and approved the contract and recommended it. The contract was then furnished to the companies for execution.

In another prior conversation Lannon told Williams he did not know any reason for shutting down the plant, and, in substance, it might occur and had occurred, and he felt reasonably sure of operation but would not guarantee it. Further testimony given by Lannon and Newhouse, vice president of the defendant, was to the effect that in May, 1928, a conversation took place with Poe, plaintiff's division manager, in which Newhouse asked a release of the defendant as its plant would be closed in June or the last of May, and Poe replied that, if defendant stopped using gas, the contract would be automatically canceled.

Counsel for appellant first invoke the rule which is firmly settled by authority, that parol evidence is inadmissible to contradict or modify a written contract, and it is conclusively presumed the whole engagement of the parties is expressed therein. Green v. Chicago & N. W. Railway Company (C. C. A.) 92 F. 873; McMaster v. New York Life Insurance Co. (C. C. A.) 99 F. 856; Potomac Steam-Boat Co. v. Upper Potomac SteamBoat Co., 109 U. S. 672, 3 S. Ct. 445, 27 L. Ed. 1070. Section 5035, Comp. Okl. Stat. 1921, provides that the execution of a contract in writing supersedes all the oral negotiations or stipulations concerning its matter which preceded or accompanied the execution of the instrument. This section applies to the contract in question, as its obligations were to be performed in Oklahoma. Brown v. Ford Motor Company (C. C. A. 10) 48 F.(2d) 732.

The defendant's contention was and is that there was ambiguity in the contract, due to the proviso in section 2, and for that reason it was competent to plead and prove the oral understanding of the parties to the effect that in case the smelter should be discontinued, the defendant's requirement of gas and its liability therefor were at an end.

We are unable to agree with this view of the contract. It contained an absolute provision it was to be in full force and effect for three years, and the quantity of gas to be taken and the price to be paid therefor were specified. The proviso in section 2 merely conformed defendant's obligation to its total requirements. In that respect it seems to us this language is unambiguous. It certainly cannot be construed, as defendant claims, to mean that, if the smelter should be closed or discontinued, there would be no further liability on the contract. The language used was therefore equivalent to an ordinary agreement to purchase a commodity required in a given business.

In the interpretation of a contract, the cardinal rule is that the intention of the parties is to be ascertained. But when a contract is explicit in terms, it furnishes a complete guide for ascertaining that intention. Continental Oil Co. v. Fisher Oil Company (C. C. A. 10) 55 F.(2d) 14.

The contract was entirely valid because of the mutual considerations of the parties. It bound the plaintiff to furnish the gas at a stipulated price for a definite period, and it bound the defendant to take and pay for the gas up to the requirements of the smelter as an operating plant. The authorities are uniform in holding such a contract to be mutual and binding, as the consideration to be rendered by the defendant is certain or reducible to certainty. The defendant owning an established business had the implied obligation to continue it in the usual manner, and accept during the time fixed the gas required to so conduct it. Wells v. Alexandre, 130 N. Y. 642, 29 N. E. 142, 15 L. R. A. 218; Cold Blast Transportation Co. v. Kansas City Bolt & Nut Company (C. C. A.) 114 F. 77, 57 L. R. A. 696; Burgess Sulphite Fibre Co. v. Broomfield, 180 Mass. 283, 62 N. E. 367; Hickey v. O'Brien, 123 Mich. 611, 82 N. W. 241, 49 L. R. A. 594, 81 Am. St. Rep. 227; Loudenback Fertilizer Company v. Tennessee Phosphate Company (C. C. A.) 121 F. 298, 61 L. R. A. 402; Lima Locomotive & Machine Company v. National Steel Castings Co. (C. C. A.) 155 F. 77, 11 L. R. A. (N. S.) 713; E. I. DuPont de Nemours Powder Company v. Schlottman (C. C. A.) 218 F. 353; Great Lakes & St. Lawrence Transp. Company v. Scranton Coal Company (C. C. A.) 239 F. 603; Texas Company v. Pensacola Maritime Corporation (C. C. A.) 279 F. 19, 24 A. L. R. 1336; Kamm v. Pritchard (C. C. A.) 296 F. 871; Diamond Alkali Company v. P. C. Tomson & Company (C. C. A.) 35 F. (2d) 117; Griffin v. Oklahoma Natural Gas Corporation (C. C. A.) 37 F.(2d) 545.

It is true, as counsel for the defendant claims, that the circumstances under which parties enter into a contract may be considered as well as the language used in order that the court may view the subject-matter from the standpoint of the parties. Great Lakes & St. Lawrence Transp. Company v....

To continue reading

Request your trial
5 cases
  • Tri-State Generation and Transmission Ass'n, Inc. v. Shoshone River Power, Inc., TRI-STATE
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • 5 Mayo 1989
    ...stemming from an arm's-length business deal between unrelated, private parties. For example, Central States Power & Light Corp. v. United States Zinc Co., 60 F.2d 832 (10th Cir.1932), involved a contract requiring a buyer to purchase a specified amount of gas each day for a set number of ye......
  • Prudential Ins. Co. of America v. Stack
    • United States
    • U.S. Court of Appeals — Fourth Circuit
    • 1 Agosto 1932
    ... ... defendant therein (appellee here) to the United States District Court for the Western District of ... v. Central Transportation Co., 171 U. S. 138, 18 S. Ct. 808, ... ...
  • Boyd v. Kmart Corp.
    • United States
    • U.S. Court of Appeals — Tenth Circuit
    • 29 Noviembre 1993
    ...argues for a deviation from this general rule, insisting that two other decisions of this circuit, Central States Power & Light Corp. v. United States Zinc Co., 60 F.2d 832 (10th Cir.1932), and Tri-State Generation & Transmission Ass'n v. Shoshone River Power, Inc., 874 F.2d 1346 (10th Cir.......
  • Texas Industries v. Brown, 15090.
    • United States
    • U.S. Court of Appeals — Fifth Circuit
    • 24 Febrero 1955
    ...v. Pritchard, 296 F. 871. See also Diamond Alkali Co. v. P. C. Tomson & Co., Inc., 3 Cir., 35 F.2d 117; Central States Power & Light Corp. v. United States Zinc Co., 10 Cir., 60 F.2d 832, certiorari denied 287 U.S. 660, 53 S.Ct. 123, 77 L.Ed. 570; Dawson Cotton Oil Co. v. Kenan, McKay & Spe......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT