Gulf & Western Industries, Inc. v. US

Decision Date17 December 1980
Docket NumberNo. 384-77.,384-77.
Citation639 F.2d 732
PartiesGULF & WESTERN INDUSTRIES, INC. v. The UNITED STATES.
CourtU.S. Claims Court

Thomas E. Harrison, Jr., New York City, atty. of record, for plaintiff. George J. Battersby, New York City, of counsel.

Frances L. Nunn, Washington, D. C., with whom was Asst. Atty. Gen. Alice Daniel, Washington, D. C., for defendant. Marsha D. Peterson, Washington, D. C., of counsel.

Before COWEN, Senior Judge, and KUNZIG and SMITH, Judges.

ON THE PARTIES' CROSS-MOTIONS FOR SUMMARY JUDGMENT

PER CURIAM:

This case comes before the court on plaintiff's request, filed March 19, 1980, for review by the court of the recommended decision of Trial Judge C. Murray Bernhardt, filed January 28, 1980, pursuant to Rule 166(c) on defendant's motion and plaintiff's cross-motion for partial summary judgment, having been submitted to the court on the briefs and oral argument of counsel. Upon consideration thereof, since the court agrees with the trial judge's recommended decision, with modifications therein by the court, it hereby affirms and adopts the recommended decision, as modified and hereinafter set forth, as the basis for its decision in this case. Accordingly, as to Count 11 of plaintiff's First Amendment to Petition, plaintiff's cross-motion for summary judgment is denied, defendant's motion for summary judgment is granted, and Count 11 is dismissed.

OPINION OF TRIAL JUDGE

BERNHARDT, Trial Judge:

This case comes before the court for Wunderlich Act review1 of the decision of the Armed Services Board of Contract Appeals (Board) in ASBCA No. 22204 (79-1 BCA ¶ 13,706) which granted in part and denied in part the government's plea in bar of plaintiff's claims under the Changes clause of its supply contract. Count 11 of plaintiff's First Amendment to Petition herein challenges the Board action.2 The review is pursuant to the parties' cross-motions for partial summary judgment only as to Count 11 of the First Amendment to Petition. The Board decision is affirmed.

On July 15, 1971, plaintiff contracted to furnish the Army 515 155 mm XM-549 warheads for $79,191.55. The standard Changes clause in the contract provided in relevant part:

* * * Any claim by the Contractor for adjustment under this clause must be asserted within 30 days from the date of receipt by the contractor of the notification of change; provided, however, that the Contracting Officer, if he decides that the facts justify such action, may receive and act upon any such claim asserted at any time prior to final payment under this contract. * * *

Flinchbaugh Products, the division of Gulf & Western performing the contract, encountered difficulties in developing a heat treating process for the HF-1 steel required by contract specifications. Also a dispute arose concerning the interpretation of inspection requirements under the contract, the government maintaining that the contract required plaintiff to perform a magnetic particle inspection on the interior surface of each warhead, and plaintiff contending the contrary.

Plaintiff presented no formal claims to the contracting officer until June 23, 1977, when it alleged five causes of action, viz: defective specifications, breach of implied warranty, superior knowledge of the government, commercial impossibility, and the extra magnetic particle inspection requirement. Concluding that the first four claims concerned production problems under the contract, and that the fifth concerned contract interpretation, the Board aggregated the production claims as one which it termed the "defective specifications" claim. The magnetic particle inspection claim retained its identity as a separate independent claim unrelated to the defective specifications claim. The consolidation was not prejudicial to plaintiff.

The Board found that final payment under the contract occurred on October 19, 1972, when plaintiff received the government's check of October 10, 1972, in payment of what both parties then regarded as the final delivery under the contract.3 The issue then presented for determination was which if any of plaintiff's claims was asserted prior to final payment. The Board held that by letter of May 18, 1972, plaintiff had manifested a present intention to seek recovery with respect to the magnetic particle inspection claim. As to the defective specification claim, however, it found that none of plaintiff's oral or written communications prior to final payment of October 19, 1972, manifested a present intention to seek an equitable monetary adjustment of contract price, nor place the contracting officer on actual or constructive notice that such a claim would be filed.

Accordingly, the Board sustained the government's plea in bar as to the defective specifications claim, but denied the plea with respect to the magnetic particle inspection claim and remanded the latter to the parties for eventual trial on the merits. Upon plaintiff's motion the Board proceedings have been stayed pending resolution of the present review.

The issues for decision by the court are:

1. (a) Did the existence of the unresolved inspection claim suspend the final payment until its resolution, thus preventing final payment from occurring on October 19, 1972, as found by the Board?

(b) If final payment did occur on October 19, 1972, may plaintiff nevertheless assert thereafter new and different claims unrelated to the preserved magnetic particle inspection claim?

2. If final payment did occur and plaintiff is precluded from bringing additional and unrelated claims after October 19, 1972, did it nevertheless assert constructively a claim for defective specifications prior to that day by manifesting to the contracting officer, actually or constructively, a present intention to seek recovery under the contract?4 The answer to each question is in the negative.

Although no universal definition of the term final payment is known, the court and the Board have generally adopted the common sense view that after all deliveries are complete and a payment is then made of the contract balance, such payment is considered final as the term is used in the Changes clause. Jo-Bar Mfg. Corp. v. United States, 210 Ct.Cl. 149, 535 F.2d 62 (1976); Specialty Assembling & Packing Co. v. United States, 156 Ct.Cl. 252, 298 F.2d 794 (1962); United Ammunition Container, Inc., ASBCA No. 21886, 78-2 BCA ¶ 13,253; Machinery Associates, Inc., ASBCA No. 14510, 72-2 BCA ¶ 9476. To paraphrase the Board in Machinery Associates, Inc., supra, when a payment is made in the normal course of events following delivery, acceptance, and the submission of an invoice requesting payment such as in the present case, that payment is a final payment as contemplated by the standard Changes clause.

Determining what constitutes the "fact of final payment" depends upon the totality of facts and circumstances of a particular case. To reach this determination, we apply the standard of whether a trier of fact could reasonably and logically consider a certain payment to be the "final payment". The Board herein found that final payment reasonably occurred on October 19, 1972. It cannot be said that its determination is not factually supported in the record or is legally erroneous.

Flinchbaugh delivered its eighth, and what proved to be its final shipment under the contract, on August 25, 1972. Thereafter, a bilateral modification was entered into, effective September 27, 1972, whereby the parties agreed to a convenience termination of the remaining 78 units scheduled under the contract. The fifth and final payment under the contract was issued by check dated October 10, 1972, which reached the plaintiff on October 19, representing payment for the delivery of 58 warheads on August 25. When added to the four previous partial payments, the total corresponded to the complete contract price as modified on September 27, 1972. The Board found that the "Advice of Payment" voucher which followed the check, although inadvertently marked "6th partial", reflected a clerical error and did not materially affect the character of the payment as final. Pursuant to the requirement of the Material Inspection and Receiving Report, subparagraph 1-301, Block 2(c) of ASPR, Appendix I, the plaintiff submitted a corrected copy of DD Form 250 prepared for its August 25, 1972, shipment identifying it as the final shipment under contract 0048.

Based upon the Board's findings, additional support from the record, and the plaintiff's lengthy delay of almost 5 years in filing a formal defective specifications claim, the Board's conclusion that the October 19, 1972, payment, under all the facts and circumstances, constituted "final payment" is affirmed.

It is well established that —

Where the contracting officer knows, or is properly chargeable with knowledge, that at the time of final payment the contractor is asserting a right to additional compensation, even though formal claim therefor has not been filed, the fact of final payment does not bar consideration of a later formal claim. * * * Jo-Bar Mfg. Corp. v. United States, supra, 210 Ct.Cl. at 157, 535 F.2d at 66.

However, it does not follow therefrom that after final payment the contractor is privileged to make for the first time new and different claims unrelated to those asserted prior to final payment.

The plaintiff cites previous Board decisions (principally three: Leader Mfg. Co., ASBCA No. 4416, 58-2 BCA ¶ 1877, Lansdale Tube Co., ASBCA No. 5837, 61-2 BCA ¶ 3260, and Aerodex, Inc., ASBCA No. 7121, 1962 BCA ¶ 3492) for the proposition that the existence of a previously asserted and timely claim "suspends" final payment pending the resolution of the outstanding claim. Those decisions differ significantly from the instant case. In each of them it was the precise claim asserted before final payment that was held to be preserved notwithstanding final payment. In none of them does it appear that the Board considered the...

To continue reading

Request your trial
5 cases
  • Cooper v. United States
    • United States
    • U.S. Claims Court
    • 17 Diciembre 1980
  • Gulf & Western Industries, Inc. v. United States
    • United States
    • U.S. Claims Court
    • 24 Febrero 1982
    ...also wrote, rejecting certain claims by the same contractor growing out of a different contract. Gulf & Western Industries, Inc. v. United States, 226 Ct.Cl. 159, 639 F.2d 732 (1980). After that decision, the Department of Justice informed the plaintiff's counsel of Judge Grossbaum's ex par......
  • Envirotech Corp. v. Tennessee Valley Authority
    • United States
    • U.S. District Court — Western District of Kentucky
    • 28 Septiembre 1988
    ...deemed to the employer, is not sufficient. TVA had to know that Envirotech was actually making a claim. Gulf & Western Industries, Inc. v. United States, 639 F.2d 732, 737 (Ct.Cl.1980). When Envirotech made no written request within 30 days, TVA was entitled to believe no such claim would b......
  • American Western Corp. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 28 Marzo 1984
    ...either party to a Government contract. As authority for this proposition, the amici cite the cases of Gulf & Western Industries, Inc. v. United States, 226 Ct.Cl. 159, 639 F.2d 732 (1980), and Dubois Construction Corp. v. United States, 120 Ct.Cl. 139, 98 F.Supp. 590 In Gulf & Western the c......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT