McCloskey & Co. v. Minweld Steel Co., 11421
Decision Date | 28 February 1955 |
Docket Number | No. 11421,11422.,11421 |
Citation | 220 F.2d 101 |
Parties | McCLOSKEY & CO., a Corporation of the State of Delaware, Appellant, v. MINWELD STEEL CO., Inc., a Corporation of the State of Pennsylvania. McCLOSKEY & CO., a Corporation of the State of Delaware, Appellant, v. MINWELD STEEL CO., Inc., a Corporation of the State of Pennsylvania, and The Travelers Indemnity Company, a Corporation of the State of Connecticut. |
Court | U.S. Court of Appeals — Third Circuit |
George Walter, Smith, Pittsburgh, Pa. (Smith & Hodel, Pittsburgh, Pa., on the brief), for appellants.
Charles E. Kenworthey, Pittsburgh, Pa. (Walter T. McGough Reed, Smith, Shaw & McClay, Pittsburgh, Pa., on the brief), for appellees.
Before GOODRICH, McLAUGHLIN and HASTIE, Circuit Judges.
Plaintiff-appellant, a general contractor, sued on three contracts alleging an anticipatory breach as to each. At the close of the plaintiff's case the district judge granted the defense motions for judgment on the ground that plaintiff had not made out a cause of action.
By the contracts involved the principal defendant,1 a fabricator and erector of steel, agreed to furnish and erect all of the structural steel required on two buildings to be built on the grounds of the Hollidaysburg State Hospital, Hollidaysburg, Pa. and to furnish all of the long span steel joists required in the construction of one of the two buildings. Two of the contracts were dated May 1, 1950 and the third May 26, 1950. By Article V of each of the contracts "Should the Sub-Contractor the defendant herein * * * at any time refuse or neglect to supply a sufficiency * * * of materials of the proper quality, * * * in and about the performance of the work required to be done pursuant to the provisions of this agreement * * *, or fail, in the performance of any of the agreements herein contained, the Contractor shall be at liberty, without prejudice to any other right or remedy, on two days' written notice to the Sub-Contractor, either to provide any such * * * materials and to deduct the cost thereof from any payments then or thereafter due the Sub-Contractor, or to terminate the employment of the Sub-Contractor for the said work and to enter upon the premises * * *."
There was no stated date in the contracts for performance by the defendant subcontractor. Article VI provided for completion by the subcontractor of its contract work "by and at the time or times hereafter stated to-wit:
Appellee Minweld Steel Co., Inc., the subcontractor, received contract drawings and specifications for both buildings in May, 1950. On June 8, 1950, plaintiff McCloskey & Co. wrote appellee asking when it might "expect delivery of the structural steel" for the buildings and "also the time estimated to complete erection." Minweld replied on June 13, 1950, submitting a schedule estimate of expecting to begin delivery of the steel by September 1, and to complete erection approximately November 15. On July 20, 1950 plaintiff wrote Minweld threatening to terminate the contracts unless the latter gave unqualified assurances that it had effected definite arrangements for the procurement, fabrication and delivery within thirty days of the required materials. On July 24, 1950 Minweld wrote McCloskey & Co. explaining its difficulty in obtaining the necessary steel. It asked McCloskey's assistance in procuring it and stated that "We are as anxious as you are that there be no delay in the final completion of the buildings or in the performance of our contract, * * *."2
Plaintiff-appellant claims that by this last letter, read against the relevant facts, defendant gave notice of its positive intention not to perform its contracts and thereby violated same.3 Some reference has already been made to the background of the July 24th letter. It concerned Minweld's trouble in securing the steel essential for performance of its contract. Minweld had tried unsuccessfully to purchase this from Bethlehem Steel, U. S. Steel and Carnegie-Illinois. It is true as appellant urges that Minweld knew and was concerned about the tightening up of the steel market.4 And as is evident from the letter it, being a fabricator and not a producer, realized that without the help of the general contractor on this hospital project particularly by it enlisting the assistance of the General State Authority,5 Minweld was in a bad way for the needed steel. However, the letter conveys no idea of contract repudiation by Minweld. That company admittedly was in a desperate situation. Perhaps if it had moved earlier to seek the steel its effort might have been successful. But that is mere speculation for there is no showing that the mentioned producers had they been solicited sooner would have been willing to provide the material.
Minweld from its written statement did, we think, realistically face the problem confronting it. As a result it asked its general contractor for the aid which the latter, by the nature of the construction, should have been willing to give. Despite the circumstances there is no indication in the letter that Minweld had definitely abandoned all hope of otherwise receiving the steel and so finishing its undertaking. One of the mentioned producers might have relented. Some other supplier might have turned up. It was McCloskey & Co. who eliminated whatever chance there was. That concern instead of aiding Minweld by urging its plea for the hospital construction materials to the State Authority which represented the Commonwealth of...
To continue reading
Request your trial-
McAlpine v. AAMCO Automatic Transmissions, Inc.
...manifest an absolute and unequivocal refusal to perform. Pennsylvania Law Encyclopedia, Vol. 8, § 365, at 414; McCloskey & Co. v. Minweld Steel Co., 220 F.2d 101 (3d Cir. 1955); McClelland v. New Amsterdam Casualty Co., 322 Pa. 429, 185 A. 198 (1936). Thus, this court need not consider whet......
-
National Union Fire Ins. Co. of Pittsburgh, Pa. v. Robert Christopher Associates
...Co. v. Wilkoff Co., 272 Pa. 172, 116 A. 150; [shortage resulting from contract vendee's purchases]; see also, McCloskey & Co., v. Minweld Steel Co., 220 F.2d 101 [3d Cir.] [shortage produced by Korean War] As a final matter, individual defendants J. Christopher Burch and Robert Burch mainta......
-
Beohm v. Pickel (In re Pickel)
...the purpose of the contract that nonperformance makes the agreement worthless. Fairfax, supra at 1327 [ citing McCloskey & Co. v. Minweld Steel Co., 220 F.2d 101 (3d Cir.1955) ]; Restatement, supra § 250, comments b and c; Corbin, supra, § 973. Otherwise, only a partial breach may be found.......
-
2401 Pennsylvania Ave. Corp. v. Federation of Jewish Agencies of Greater Philadelphia
...is still the rule of law in Pennsylvania. See, William B. Tanner v. WIOO, Inc., 528 F.2d 262 (3d Cir.1975); McCloskey v. Minweld Steel Co., 220 F.2d 101 (3d Cir.1955); Alabama Football, Inc. v. Greenwood, 452 F.Supp. 1191 (D.C.Pa.1978); Wolgin v. Atlas United Financial Corp., 397 F.Supp. 10......
-
Players, Owners, and Contracts in the Nfl: Why the Self-help Specific Performance Remedy Cannot Escape the Clean Hands Doctrine
...begins, creating an actual breach. See RESTATEMENT (SECOND) OF CONTRACTS § 250(a) (1979). See also McCloskey and Co. v. Minweld Steel Co., 220 F.2d 101, 104 (3d Cir. 1955) (quoting McClelland v. New Amsterdam Cas. Co., 185 A. 198, 200 (Pa. 1936)). "In order to give rise to a renunciation am......