JB Esker & Sons v. Cle-Pa's Partnership

Decision Date10 October 2001
Docket NumberNo. 5-99-0811.,5-99-0811.
Citation757 N.E.2d 1271,259 Ill.Dec. 136,325 Ill. App.3d 276
PartiesJ.B. ESKER & SONS, INC., Plaintiff-Appellee, v. CLE-PA'S PARTNERSHIP, Defendant-Appellant.
CourtUnited States Appellate Court of Illinois

H. Carl Runge, Jr., Law Offices of H. Carl Runge, Jr., Ltd., Collinsville, for Appellant.

Lou J. Viverito of Taylor Law Offices, P.C., Effingham, for Appellee.

Justice GOLDENHERSH delivered the opinion of the court:

J.B. Esker & Sons, Inc. (plaintiff), filed a complaint for the foreclosure of a mechanic's lien against Cle-Pa's Partnership (defendant). Defendant filed an answer and a counterclaim. The matter went to trial. Plaintiff was awarded $938 and defendant was awarded $26,145. After a later hearing, defendant was awarded $13,532 in attorney fees and $3,730.77 in costs. Defendant appeals, contending that the trial court improperly declined to award expert witness fees and the full amount of attorney fees. We reverse in part and remand.

I. FACTS

On June 1, 1993, the parties entered into a contract wherein defendant agreed to pay plaintiff $238,870 to perform concrete and paving construction for a Grandpa's store in Greenville, Illinois. The contract contained the following clause:

"15.4 ATTORNEY'S FEES. Should either party employ an attorney to institute suit or demand arbitration to enforce any of the provisions hereof, to protect its interest in any matter arising under this Agreement, to collect damages for the breach of the Agreement, or to recover on a surety bond given by a party under this Agreement, the prevailing party shall be entitled to recover reasonable attorney's fees, costs, charges, and expenses expended or incurred therein."

On August 4, 1994, plaintiff filed a complaint seeking the foreclosure of a mechanic's lien against defendant. According to the complaint, defendant defaulted on the final balance due in the amount of $33,403. Defendant filed an answer, affirmative defenses, and a counterclaim. In its two affirmative defenses, defendant alleged that charges for additional work claimed by plaintiff were not done with change orders as required by the contract and that defendant was entitled to keep the withheld amount, as the contract allowed defendant to keep 10% of its payment until the completion of an inspection and the acceptance of the work by defendant. In its counterclaim, defendant alleged that as a result of unworkmanlike performance by plaintiff, defendant anticipated having to take up a portion of the tile laid on the concrete and level the concrete floor.

The bench trial extended over a period of six days. The trial commenced on January 21, 1998, and was recessed on January 22, 1998. The trial resumed on March 30, 1998, and continued until recessed on April 1, 1998. The trial concluded on June 22, 1998.

Defendant presented the testimony of Dr. W. Gene Corley, structural engineer of Construction Technology Laboratories, Inc., Skokie, Illinois, who testified during two days of the trial. Dr. Corley had traveled to the store, inspected the site, and conducted a series of measurements and tests. He wrote a report on his findings and was deposed on two separate occasions. At the trial, Dr. Corley's testimony included the observations he made on his inspection and a repair estimate of $193,000. Defendant claims that Dr. Corley spent 156.3 hours on the case and that the amount of his bill was $22,925.25.

Over defendant's objection, plaintiff presented the testimony of William Gould, former vice-president of Paul Apt Floor Coverings. Gould testified that in 1994, Paul Apt Floor Coverings presented a repair estimate of $26,145. Gould testified that defendant did not authorize repair work on the estimate.

Plaintiff contended that additional expenses were incurred during construction because the ground was soft and wet. Plaintiff asserted that as a result of the conditions it had to construct an access road, use a concrete pump, and repair a curb. Plaintiff submitted documents regarding the additional work, including an invoice of $938 for curb repair.

At the close of the evidence, the court took the matter under advisement. On October 28, 1998, the court entered an order. The court noted that, including the amount to be paid under the original contract and the additional work performed, the amount requested by plaintiff was $259,291.50. The court stated that defendant paid $224,928.50, which left $34,301 unpaid. The court found that the curb repair was done at the request of defendant, and the court awarded plaintiff $938. However, the court found that plaintiff failed to prove that defendant was responsible for any other additional work performed outside the contract. In regard to the balance remaining under the contract, the court found that plaintiff's performance was defective and that defendant properly withheld 10% from the bill. The court stated, "Judgment is hereby rendered on behalf of Defendant, Cle-Pa's[,] on the Complaint for Mechanic's Lien."

The court awarded defendant $26,145 on the counterclaim. The court stated, "[T]he cement work performed by [P]laintiff breached the contract for construction; however, it is the further finding of this court that the Defendant's request to Plaintiff for continuing the construction[,] despite the knowledge of the faulty concrete, contributed to [the] further inadequacy of the concrete and the eventual damage to the floor of the Grandpa's Store." The court declined to award defendant the amount sought on the counterclaim. The court found that defendant had failed to mitigate damages and had failed to present evidence on diminution of value. The court was also critical of Dr. Corley's testimony, stating:

"Although this court finds Defendant[`s] expert testimony to be credible on the issue of lack of adequate manpower on the floor pours, this court finds the remainder of said testimony on the issue of damages not to be credible for the following reasons: [t]he labor rates he used are utilized in union agreements; he did not obtain any estimates from flooring contractors in the Greenville area for removal nor [sic] repair of the tile; [and] he used a labor unit cost of $3.00 per square feet for installing vinyl tile instead of the unit cost of $1.33 per square foot for installing vinyl composition tile."

The court ordered the parties to bear their own costs and reserved the issue of attorney fees for further hearing. Defendant filed a motion to reconsider. The motion was denied and defendant filed a petition for attorney fees. Attached to the petition was a bill from Dr. Corley for $22,925.25.

The petition also contained a sworn and subscribed affidavit from H. Carl Runge, Jr., for attorney fees and expenditures for the total amount of $22,662.07. An "Itemized Statement for Services Rendered" set forth attorney fees in the amount of $18,932. The document detailed the tasks undertaken, the date performed, and the time spent on an hourly basis at the rate of $100 per hour. This document also set forth $3,730.07 for other items, such as travel and deposition transcripts.

Also attached to the petition was an unsigned affidavit for attorney fees and costs of John W. Kelsey for $8,307.44, at an hourly rate of $95. On the letterhead of the office of John W. Kelsey were two documents entitled "Statement for Professional Services Rendered." These documents listed phone tolls, postage, and mileage expenses incurred on specific dates for certain tasks. The documents did not itemize the hours spent.

At the hearing on the petition, plaintiff argued that Runge had previously prepared a statement seeking attorney fees equivalent to one-third of the award given to defendant. Runge stated that the document was hastily prepared for plaintiff's counsel's review and that it was not signed or sworn to. (Neither party referenced this document by page number, and it could not be located in the record.)

On November 1, 1999, the court entered an order awarding defendant attorney fees in the amount of $13,532 and for "costs, charges[,] and expenses" in the amount of $3,730.77. Defendant filed this appeal.

II. ANALYSIS

Under the agreement entered into by the parties, the "prevailing party" is entitled to reasonable attorney fees, costs, charges, and expenses. A prevailing party, for purposes of awarding attorney fees, is one that is successful on a significant issue and achieves some benefit in bringing suit. Grossinger Motorcorp, Inc. v. American National Bank & Trust Co., 240 Ill.App.3d 737, 753, 180 Ill.Dec. 824, 607 N.E.2d 1337, 1348 (1992). A party that receives judgment in his favor is usually considered the prevailing party. Tomlinson v. Dartmoor Construction Corp., 268 Ill.App.3d 677, 687, 206 Ill.Dec. 371, 645 N.E.2d 376, 383 (1994). Although in some cases a court may decide there is no prevailing party, the court properly declined to make such a finding here. See Brown & Kerr, Inc. v. American Stores Properties, Inc., 306 Ill.App.3d 1023, 1035, 240 Ill.Dec. 117, 715 N.E.2d 804, 814 (1999). In this case, the trial court entered a judgment for defendant. The trial court apparently believed that defendant was the prevailing party because the court awarded some attorney fees and costs to defendant.

The success defendant had in defeating the claim against it and in securing an award on the counterclaim undoubtedly indicates that it was the prevailing party. As the prevailing party, defendant benefits from the contract.

A. Attorney Fees

Defendant contends that there should have been an award of attorney fees for the full amount submitted to the trial court. Plaintiff contends that the trial court properly exercised discretion in denying the full amount submitted. Plaintiff contends that the fact that the trial court's ruling was not totally in defendant's favor is sufficient ground, in itself, to reduce the fee. Plaintiff's arguments are unconvincing.

Generally, a party is responsible for his own attorney...

To continue reading

Request your trial
72 cases
  • Rexam Beverage Can Co. v. Bolger
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • August 24, 2010
    ...calls for the shifting of attorney fees, a trial court should award all reasonable fees.” J.B. Esker & Sons, Inc. v. Cle-Pa's P'ship, 325 Ill.App.3d 276, 259 Ill.Dec. 136, 757 N.E.2d 1271, 1277 (2001). The trial court found it reasonable to award Bolger all its fees related to its repair cl......
  • Negro Nest, LLC v. Mid-Northern Management
    • United States
    • Illinois Supreme Court
    • December 1, 2005
    ...is part of a contract and the court must determine the intention of the parties. J.B. Esker & Sons, Inc. v. Cle-Pa's Partnership, 325 Ill.App.3d 276, 285, 259 Ill.Dec. 136, 757 N.E.2d 1271, 1279 (2001). The words used will be given their plain and ordinary meaning. Qazi, 50 Ill.App.3d at 27......
  • Lobo Iv, LLC v. V Land Chi. Canal, LLC
    • United States
    • United States Appellate Court of Illinois
    • March 21, 2019
    ...Inc. , 375 Ill. App. 3d 222, 227, 314 Ill.Dec. 59, 873 N.E.2d 989 (2007) (quoting J.B. Esker & Sons, Inc. v. Cle-Pa's Partnership , 325 Ill. App. 3d 276, 280, 259 Ill.Dec. 136, 757 N.E.2d 1271 (2001) ). Here, the issue was whether Lakeside's loans had priority, and the trial court found tha......
  • Pepper Constr. Co. v. Palmolive Tower Condos., LLC
    • United States
    • United States Appellate Court of Illinois
    • September 17, 2021
    ...is an exception where a contract, as here, provides for an award of attorney fees. J.B. Esker & Sons, Inc. v. Cle-Pa's Partnership , 325 Ill. App. 3d 276, 281, 259 Ill.Dec. 136, 757 N.E.2d 1271 (2001). Section 19 of the subcontract, titled "Legal Fees," states:"In the event any legal procee......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT