Pope & Talbot v. Blanchard Lumber Co.

Decision Date08 January 1947
Docket NumberNo. 11321.,11321.
Citation159 F.2d 134
PartiesPOPE & TALBOT, Inc. v. BLANCHARD LUMBER CO. OF SEATTLE.
CourtU.S. Court of Appeals — Ninth Circuit

Lillick, Geary, Olson & Charles, Ira S. Lillick, Gilbert C. Wheat and Edward D. Ransom, all of San Francisco, Cal., for appellant.

Farnham P. Griffiths, Charles E. Finney, Martha T. Naylor, McCutchen, Thomas, Matthews, Griffiths & Greene, all of San Francisco, Cal., for appellee.

Before DENMAN, HEALY and ORR, Circuit Judges.

DENMAN, Circuit Judge.

Pope & Talbot, Inc. appeal from a decree in admiralty awarding appellee damages in the amount of freight withheld by appellant upon an agreed sale of appellee's lumber at the port of Los Angeles, California, where appellant's steamer Absaroka, carrying the lumber, took refuge after being torpedoed by a Japanese submarine.

Appellant was carrying the lumber on a bill of lading having a freight earned clause like that in the case of Pope & Talbot, Inc., v. Guernsey-Westbrook Company, 9 Cir., 159 F.2d 139. Appellee contends, as was contended in the Guernsey-Westbrook case, that the clause applies only to the freight which the carrier had declared due on the receipt of the goods. For the reasons stated in the companion case, we hold that the freight to be deemed earned "ship or goods lost or not lost" clause applies to freight other than so declared due.

The remaining question in this admiralty appeal is whether the appellant carrier has lost its right to its earned freight because of its abandonment of the voyage at the port of Los Angeles where the Absaroka sought refuge after her injury. While in the trial de novo of an admiralty appeal we pay due regard to the findings of the trial court, we feel that it erred in its holding that a long extended delay caused by the attack of an enemy vessel in war time cannot warrant the termination of the obligation of the carrier to proceed with the voyage under a bill of lading provision that such a war injured vessel may "store the goods ashore * * * at the port or place where the vessel then is" and that "such disposition of the goods shall constitute a final delivery thereof * * * but the carrier shall retain a lien on the goods for all proper charges" if the "carriage of the cargo is likely to be delayed."1

We think the facts show a likelihood of a very long delay beyond anything contemplated by the parties. While not necessary to bring the case within the delay provision, we think the delay amounts to a complete frustration of the vessel's intercoastal voyage from St. Helens, Oregon, to Philadelphia, Pennsylvania.

We further are of the opinion that the effect of the torpedoing of the vessel was such as "may cause" a decision that it was "unsafe or impracticable to proceed from * * * the port" of Los Angeles by reason of the presence of a war hazard greater than what was anticipated on December 13, 1941, when the bill of lading was issued, and because of the condition of the cargo after submersion and soaking with fuel oil.

Appellant is a lumber manufacturer engaged in selling its manufactured product and also a steamship owner engaged in the intercoastal transport of lumber for itself and its buyers. Appellee bought from appellant 270,170 feet of green Douglas fir lumber to be transported by appellant under the above bill of lading provisions in the Absaroka from St. Helens to Philadelphia, a voyage customarily of less than two weeks duration.

The Pearl Harbor attack of December 7, 1941, preceded the issuance of the Absaroka bills of lading on December 13. At that time no Japanese submarines had been reported on the Pacific Coast of the United States and it was a matter of speculation whether the Japanese would attempt submarine warfare on a coast some 7,000 miles from its naval bases. On December 20, the vessel's second day from St. Helens, the Absaroka was ordered by radio by Navy officials to come into San Francisco Bay because of a rumor of the presence of a submarine on the coast. This caused delay, the order being countermanded on December 21. The vessel resumed her voyage, intending to stop at the port of Los Angeles for fuel.

On December 24, while about five miles from the latter port, the Absaroka was struck by a torpedo between the No. 4 and No. 5 holds, approximately at the level of the 'tween deck. The explosion tore a hole in the shell of the ship approximately 15 feet by 20 feet in size, blew off a small part of the after deckload of lumber and caused the vessel to settle heavily by the stern with an 18° list to starboard. In addition to the injury on the starboard side, the deck frames above and below and the side frames on the port side were heavily bent and distorted. A general alarm was sounded, SOS signals were flashed by radio and the master immediately ordered the crew to abandon ship. Had it not been for the buoyancy of the submerged fir lumber in her holds, the vessel would have sunk. Coast Guard cutters and privately owned tugs went to the assistance of the Absaroka, which commenced to tow the vessel towards Los Angeles Harbor.

The Absaroka was towed by six tugs inside the San Pedro breakwater and was there beached on Cabrillo Beach. Salvage operations were carried out, the lumber cargo not lost was discharged, the discharge being completed on January 7, 1942. Some of the lumber was soaked with fuel oil leaking from punctured double-bottom tanks. After cleaning oil and debris from the No. 5 hold and the machinery space, the Absaroka was placed on dry dock at the plant of the Bethlehem Steel Company on January 19, 1942. Upon completion of survey of the vessel's damages, repair specifications were drawn and a repair contract was negotiated with the Bethlehem Steel Company for an agreed price of $310,000, the tender being dated January 22, 1942. Additional damages were discovered during the performance of repairs and a supplementary specification covering these damages was prepared and submitted to the Bethlehem Steel Company, who submitted a tender in the amount of $14,827 under date of May 7, 1942, to cover this additional work. Repairs were completed and a satisfactory dock trial was run on May 9, 1942.

After deliberating seven weeks until February 5, 1942, that is after five weeks delay beyond the contemplated two weeks voyage to Philadelphia was to have been completed, appellant gave its notice of abandonment. Appellant does not claim that this first five weeks delay is its justification for abandonment under the "likely to be delayed" clause, but that it is justified by the five weeks plus the further "likely" delay which a carrier rationally would anticipate in the then conditions arising from the war with Japan.

It then was obvious to the maritime public and a matter of judicial notice to an admiralty court that the destruction of naval vessels at Pearl Harbor and the enormous injuries to and losses of merchant ships by submarine attack on the Atlantic and Gulf waters would cause all repair facilities of all American shipyards to be crowded beyond their capacity and that priorities would be given by the government to those vessels most needed for a two ocean war. While under ordinary conditions the time for the Absaroka's repairs would take about 45 days, it was a rational anticipation of the appellant's manager that without a special government priority the vessel would be "likely" not to be repaired for months.

The repairs were not completed until May 9, 1942, and then only after the War Shipping Administration on April 4 had given notice that it proposed to take over the vessel. It is likely there would have been many weeks more delay in waiting for the completion of repairs if the ship had not had the priority of a use by the government. As it was the actual delay was 142 days to which should be added 5 days for stowage of her cargo and supplying her if her voyage was to be continued. That is to say, 21 weeks, being 19 weeks delay beyond the normal two weeks voyage.

It is our opinion that no such delay was within even the remote contemplation of the parties as "likely" to occur on December 13 when the bill of lading was issued; and that on February 5, 1942, when the notice of abandonment was given, at least such delay was an imminent likelihood within the meaning of the words "likely to be delayed" of the abandonment clause of the bill of lading.

In the bill of lading there is another printed clause providing that "Carrier is not and shall not be required to deliver said packages at the port of discharge or port of destination at any particular time, or to meet any particular market, or in time for any particular use." Appellee argues that this provision nullifies the provision for abandonment because of war conditions creating a delay beyond any reasonable anticipation of the parties — here nine...

To continue reading

Request your trial
1 cases
  • Pope & Talbot v. Guernsey-Westbrook Co.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • 8 janvier 1947
    ...on the abandonment of that vessel's voyage from St. Helens, Oregon, to Brooklyn, New York. In the case of Pope & Talbot, Inc. v. Blanchard Lumber Co. of Seattle, 9 Cir., 159 F.2d 134, we have held justified the abandonment of the voyage after the torpedoing of the vessel on December 24, 194......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT