S & S Paving & Constr., Inc. v. Berkley Reg'l Ins. Co.
| Court | Arizona Court of Appeals |
| Writing for the Court | DOWNIE, Judge |
| Citation | S & S Paving & Constr., Inc. v. Berkley Reg'l Ins. Co., 239 Ariz. 512, 372 P.3d 1036 (Ariz. App. 2016) |
| Decision Date | 12 May 2016 |
| Docket Number | No. 1 CA–CV 15–0239.,1 CA–CV 15–0239. |
| Parties | S & S PAVING AND CONSTRUCTION, INC., an Arizona corporation, Plaintiff/Appellant, v. BERKLEY REGIONAL INSURANCE COMPANY, a Delaware corporation, Defendant/Appellee. |
Carmichael & Powell, P.C. By Trysta M. Puntenney, David J. Sandoval, Phoenix, Counsel for Plaintiff/Appellant.
Jennings, Haug & Cunningham, LLP By Chad L. Schexnayder, Robert John Lamb, Phoenix, Counsel for Defendant/Appellee.
OPINION
¶ 1 S & S Paving and Construction, Inc. (“S & S”) appeals the dismissal of its bad faith claim against Berkley Regional Insurance Company (“Berkley”). We hold that a surety on a payment bond issued under Arizona's “Little Miller Act” may not be sued for bad faith and therefore affirm the judgment of the superior court.
¶ 2 The City of Prescott retained Spire Engineering, LLC (“Spire”) to act as general contractor for the Demerse Avenue Overlay Project (“the Project”). Berkley issued a payment bond for the Project. See Ariz. Rev. Stat. (“A.R.S.”) § 34–222(A)(2) ().
¶ 3 In October 2011, S & S's attorney sent a demand letter to Berkley, stating that S & S had performed paving work for the Project pursuant to its subcontract with Spire and had not been paid $23,763. Berkley acknowledged the claim, requested additional information, and advised that its review of S & S's demand “does not toll the running of any statute of limitations or other time period.”
¶ 4 S & S provided Berkley with the requested information, which included a proof of claim. Berkley acknowledged receipt of the documentation in December 2011 and stated that it needed to ascertain Spire's position regarding S & S's claim, after which it would communicate further. Berkley reiterated that its investigation of the claim “in no way waives or alters any rights, interests or defenses that we may have under our bond or applicable law.” No further communication occurred between the parties until May 2013, when counsel for S & S sent another demand letter, and Berkley responded that S & S's claim was untimely.
¶ 5 In November 2013, S & S sued Berkley for breach of contract and bad faith.1 Berkley moved for summary judgment on both claims. The superior court ruled that the breach of contract claim was barred by the statute of limitations. See A.R.S. § 34–223(B) (). The court also dismissed S & S's bad faith claim, concluding there was no “contractual relationship or special relationship for the claim to survive.” The court denied S & S's motion for reconsideration and awarded Berkley attorneys' fees.
¶ 6 S & S timely appealed. We have jurisdiction pursuant to A.R.S. §§ 12–120.21(A)(1) and –2101(A)(1).
¶ 7 We review a grant of summary judgment de novo. Chalpin v. Snyder, 220 Ariz. 413, 418, ¶ 17, 207 P.3d 666, 671 (App.2008). Summary judgment is appropriate if “there is no genuine dispute as to any material fact and the moving party is entitled to judgment as a matter of law.” Ariz. R. Civ. P. 56(a). We will affirm the judgment if it is correct for any reason. Ariz. Bd. of Regents v. State ex rel. Ariz. Pub. Safety Ret. Fund Manager, 160 Ariz. 150, 154, 771 P.2d 880, 884 (App.1989).
¶ 8 In 1969, Arizona adopted the Little Miller Act, A.R.S. §§ 34–221, et seq. (“the Act”). See SCA Constr. Supply v. Aetna Cas. & Sur. Co., 157 Ariz. 64, 65–66, 754 P.2d 1339, 1340–41 (1988). Modeled after the federal Miller Act, 40 U.S.C. § 270a, et seq., the Act requires contractors on public works projects to furnish payment bonds “for the protection of claimants supplying labor or materials to the contractor or his subcontractors.” A.R.S. § 34–222(A)(2). A claimant who is not paid in full for labor or materials “shall have the right to sue on such payment bond.” A.R.S. § 34–223(A). “The purpose behind both of the Miller Acts is to provide security for those who supply materials or labor in the construction of public projects.” SCA Constr., 157 Ariz. at 66, 754 P.2d at 1341. Such statutory protection is necessary because no lien rights exist on public projects. See F.D. Rich Co. v. United States ex rel. Indus. Lumber Co., 417 U.S. 116, 122, 94 S.Ct. 2157, 40 L.Ed.2d 703 (1974) ().
¶ 9 S & S does not challenge the dismissal of its breach of contract claim on statute of limitations grounds. See A.R.S. § 34–223(B) (). It instead contends the superior court erred by dismissing its bad faith claim because sureties issuing payment bonds under the Act have a duty to “undertake an investigation adequate to determine whether a claimant's claim is tenable or valid.” According to S & S, sureties owe the same duty of good faith to claimants under the Act as insurance companies owe to insureds.
¶ 10 S & S asks us to graft a common law remedy onto a statutory scheme that includes within its ambit both the availability of complete relief and specific conditions precedent to recovery. But “where a statute expressly provides a particular remedy or remedies, a court must be chary of reading others into it.” Transamerica Mortg. Advisors, Inc. v. Lewis, 444 U.S. 11, 19, 100 S.Ct. 242, 62 L.Ed.2d 146 (1988) ; see also State ex rel. Horne v. AutoZone, Inc., 229 Ariz. 358, 362–63, 275 P.3d 1278, 1282–83 (2012) ().
¶ 11 The Arizona Legislature has defined the breadth of liability under the Act. Section 34–222(F) dictates the terms that payment bonds must include—one of which is the statement that “all liabilities on this bond shall be determined in accordance with the provisions, conditions and limitations of title 34, chapter 2, article 2, Arizona Revised Statutes, to the same extent as if they were copied at length in this agreement.” (Emphasis added.) “All liabilities” is a broad term. Recognizing a common law bad faith remedy would be inconsistent with the legislature's defined liability for Act sureties. And this Court has long-recognized that “[w]hen a corporate surety undertakes an obligation on a bond pursuant to a specific statutory requirement, its liabilities are measured by the terms of that statute.” Brown Wholesale Elec. Co. v. Merchs. Mut. Bonding Co., 148 Ariz. 90, 95, 713 P.2d 291, 296 (App.1984) ; see also Norquip Rental Corp. v. Sky Steel Erectors, Inc., 175 Ariz. 199, 202, 854 P.2d 1185, 1188 (App.1993) ().
¶ 12 In addition to defining a surety's liability, the Act dictates the procedures that claimants must follow in order to recover against payment bonds. See R.E. Monks Constr. Co. v. Aetna Cas. & Sur. Co., 189 Ariz. 575, 579, 944 P.2d 517, 521 (App.1997) (). When a statutory scheme “creates a right and also provides a complete and valid remedy for the right created, the remedy thereby given is exclusive.” Blankenbaker v. Jonovich, 205 Ariz. 383, 387, ¶ 18, 71 P.3d 910, 914 (2003).
¶ 13 But for its failure to timely file suit, S & S had a “complete and valid remedy” under the Act. See id. Because a payment bond is “sufficient to pay all claims, and is the sole source from which laborers and materialmen are to be paid, it necessarily follows that laborers and materialmen who do not timely avail themselves of this remedy fall into the category of general creditors of the contractor.” Gen. Acrylics v. U.S. Fid. & Guar. Co., 128 Ariz. 50, 55, 623 P.2d 839, 844 (App.1980). Concluding that S & S is relegated to the status of general creditor and may not assert a bad faith claim against Berkley is consistent with the treatment of private project claimants under Arizona's mechanics' lien statutes. Cf. Trio Forest Prod., Inc. v. FNF Constr., Inc., 182 Ariz. 1, 2, 893 P.2d 1, 2 (App.1994) (). Mechanics' lien claimants are required to strictly comply with various statutory requirements, or lien-based recovery is barred. See, e.g., Scottsdale Mem'l Health Sys. v. Clark, 157 Ariz. 461, 470, 759 P.2d 607, 616 (1988) (); MLM Constr. Co. v. Pace Corp., 172 Ariz. 226, 232, 836 P.2d 439, 445 (App.1992) (); James Weller, Inc. v. Hansen, 21 Ariz.App. 217, 223, 517 P.2d 1110 (1973) ().
¶ 14 S & S relies heavily on Dodge v. Fidelity & Deposit Co. of Maryland, 161 Ariz. 344, 778 P.2d 1240 (1989) —a case we find distinguishable. In Dodge, the plaintiff-homeowners contracted with a residential contractor for the construction of a home. Their contract required a performance bond, which the defendant-surety provided. After the contractor failed to complete the project, the homeowners filed suit. As relevant here, they alleged bad faith against the surety. The surety prevailed in the superior court and on appeal to this Court. The Arizona Supreme Court reversed, however, holding that the bad faith claim could proceed, and stating:
The purpose of...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Rosenberg v. Sanders
...1099, 1102 (App. 2018), and will "affirm the judgment if it is correct for any reason," S & S Paving & Const., Inc. v. Berkley Reg'l Ins. Co. , 239 Ariz. 512, 514, ¶ 7, 372 P.3d 1036, 1038 (App. 2016). ¶14 Summary judgment is appropriate when "there is no genuine dispute as to any material ......
-
In re 140-30-017e
...either standard and we will affirm a grant of summary judgment if correct for any reason. S & S Paving & Constr., Inc. v. Berkley Reg'l Ins. Co. , 239 Ariz. 512, ¶ 7, 372 P.3d 1036 (App. 2016).5 Shonk suggests the mobile home is personal property and because the drugs were sold inside the m......
-
Mesquite Power, LLC v. Ariz. Dep't of Revenue
...to state a claim, we need not address the dismissal as a matter of jurisdiction. See S&S Paving and Constr., Inc. v. Berkley Reg'l Ins. Co. , 239 Ariz. 512, 514, ¶ 7, 372 P.3d 1036, 1038 (App. 2016).6 "Statutory value" is not a defined term. See A.R.S. § 42-11001. We presume Mesquite means ......
-
Rahn v. City of Scottsdale
...8 (2016) (citations omitted). But, we will affirm summary judgment if it is correct for any reason. S & S Paving & Const., Inc. v. Berkley Reg'l Ins. Co., 239 Ariz. 512, 514, ¶ 7 (App. 2016) (citation omitted).I. Wrongful Arrest¶14 Rahn contends the superior court erred in granting summary ......
-
§ 14.6.7 FEE AWARDS MUST BE REASONABLE
...140 Ariz. 597, 684 P.2d 169 (App. 1984).................................... 14-10 S&S Paving & Constr, Inc. v. Berkley Reg'l Ins. Co., 239 Ariz. 512, 372 P.3d 1036 (App. 2016).... 14-6 Santa Fe Ridge Homeowners' Ass'n v. Bartschi, 219 Ariz. 391, 199 P.3d 646 (App. 2008)............... 14-11......
-
SECTION 603 TYPES OF BONDS
...bond was binding on the principal and surety jointly and severally. In S & S Paving & Construction, Inc. v. Berkley Regional Ins. Co., 239 Ariz. 512, 372 P.3d 1036 (App. 2016), the court held that the little Miller act does not impose on sureties a duty of good faith or duty to investigate ......
-
§ 14.5.1 LITTLE MILLER ACT
...v. Capitol Indem. Corp., 183 Ariz. 74, 79, 900 P.2d 1210, 1215 (1995); see also S&S Paving & Constr., Inc. v. Berkley Reg'l Ins. Co., 239 Ariz. 512, 516, ¶ 15, 372 P.3d 1036, 1040 (App. 2016) (noting that "an award of attorneys' fees is mandatory" under the Little Miller Act). In one case, ......