Berkel & Co. Contractors, Inc. v. Palm & Assoc., Inc.
Decision Date | 08 September 2004 |
Docket Number | No. 71A03-0307-CV-294.,71A03-0307-CV-294. |
Citation | 814 N.E.2d 649 |
Court | Indiana Appellate Court |
Parties | BERKEL & COMPANY CONTRACTORS, INC., Appellant-Defendant, v. PALM & ASSOCIATES, INC., Appellee-Plaintiff. |
Sean E. Kenyon, Robert J. Konopa, Konopa Reagan & Kenyon, South Bend, IN, Attorneys for Appellant.
Robert J. Palmer, Jeffery A. Johnson, Richard F. Nugent, Jr., May Oberfell & Lorber, South Bend, IN, Attorneys for Appellee.
Berkel & Company Contractors, Inc. ("Berkel") appeals the trial court's grant of partial summary judgment to Palm & Associates, Inc. ("Palm") on its breach of contract claim, the trial court's denial of Berkel's cross-motion for summary judgment, and the trial court's findings of fact and conclusions thereon awarding damages to Palm. Berkel raises three issues, which we consolidate and restate as:
We affirm.
The relevant facts follow. In early 2002, Berkel, as a sub-contractor, contracted with Black & Veatch Construction, Inc. ("Black & Veatch"), as the general contractor, to install approximately 800 pilings1 for a generating plant in St. Joseph County, Indiana ("the Project") being built by Black & Veatch. Berkel contacted Palm about performing some surveying work on the Project, and on April 3, 2002, Berkel issued a purchase order to Palm.
The purchase order listed that Palm was to "[v]erify pile locations in Electronics Drawings against plan sheet dimensions prior to staking" and to "[p]repare a pre-drill staking drawing showing grid-lines, caps, piles, pile designation, with corresponding staking numbers" for a price "[n]ot to exceed $780.00[.]" Appellant's Appendix at 16. The purchase order also included a provision that Palm would supply the following:
Field Crew — 2 men full time during the course of our work[.]
Id. The terms of the purchase order called for Berkel to compensate Palm for these services at a price of $110 per hour. The purchase order further had a provision that "[m]aterials and equipment must meet standards required by state and federal regulations and any project requirement." Id. On April 11, 2002, two of Palm's employees began performance of the work listed under the purchase order and completed one and one-half hours of work. On April 15, 2002, Berkel learned that all subcontractors were required to employ union labor and told Palm that Palm would be required to use union labor on the Project. Palm told Berkel that it would talk to the local unions and that the price in the purchase order would need to be adjusted if Palm was to have a working agreement with the union. On April 19, 2002, Palm had not yet worked out an agreement with the union, and Berkel hired another surveyor to complete the work that Palm had agreed to perform. Berkel then informed Palm that it was to perform no further work under the purchase order and paid Palm for its work already completed.
Palm then filed a complaint for breach of contract against Berkel. Palm later filed a motion for partial summary judgment on its breach of contract claim, arguing that "Berkel breached its agreement to have Palm perform certain tasks and compensate Palm according to the purchase order." Appellant's Appendix at 44. Berkel filed a cross-motion for summary judgment, arguing that: (1) the purchase order did not constitute a contract; and (2) even if the purchase order was a contract, Palm breached it by refusing to use union labor. Following a hearing on the motions, the trial court granted Palm's motion for partial summary judgment and denied Berkel's cross-motion for summary judgment.
Thereafter, a bench trial was held on the issue of damages, and Berkel asserted an affirmative defense of failure to mitigate damages. Pursuant to Indiana Trial Rule 52, Berkel requested that the trial court enter findings of facts and conclusions thereon, and the trial court issued the following order:
The first issue is whether the trial court erred by granting partial summary judgment to Palm on its breach of contract claim and by denying Berkel's cross-motion for summary judgment. Our standard of review for the grant of a motion for summary judgment is well settled. Summary judgment is appropriate only where the evidence shows that there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. Ind. Trial Rule 56(C); Mangold ex rel. Mangold v. Ind. Dep't of Natural Res., 756 N.E.2d 970, 973 (Ind.2001). The standard of review is not altered by cross-motions for summary judgment on the same issues. Indiana Ins. Co. v. American Cmty. Servs., Inc., 718 N.E.2d 1147, 1152 (Ind.Ct.App.1999). All facts and reasonable inferences drawn from those facts are construed in favor of the nonmoving party. Mangold, 756 N.E.2d at 973. Review of a summary judgment motion is limited to those materials designated to the trial court. Id.
The essential elements of a breach of contract action are the existence of a contract, the defendant's breach thereof, and damages. Rogier v. Am. Testing and Eng'g Corp., 734 N.E.2d 606, 614 (Ind.Ct.App.2000), reh'g denied, trans. denied. Berkel argues that the...
To continue reading
Request your trial-
Tyler v. Trs. of Purdue Univ.
... ... Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d ... See Mills v. First Fed. Sav. & Loan Assoc. of Belvidere, 83 F.3d 833, 84142 (7th Cir.1996) ... Collins, 871 N.E.2d at 372 (citing Berkel & Co. Contractors, Inc. v. Palm & Assocs., Inc., ... ...
-
Leaf Funding, Inc. v. Brogan Pharmaceuticals, Inc.
...damages. Indiana Bureau of Motor Vehicles v. Ash, 895 N.E.2d 359, 365 (Ind.Ct.App. 2008) (quoting Berkel & Co. Contractors, Inc. v. Palm & Assocs., Inc., 814 N.E.2d 649, 655 (Ind.Ct.App.2004)).2 As noted, in response to summary judgment, Defendants do not dispute the existence of the contra......
-
Entm't USA, Inc. v. Moorehead Commc'ns, Inc.
... ... While seeking to recover "the benefit of the bargain," Berkel & Co. Contractors, Inc. v. Palm & Assocs., Inc. , 814 N.E.2d 649, 658 ... ...
-
Neurology & Pain Mgmt. Assocs., P.C. v. Bunin
... ... Anderson v ... Liberty Lobby , Inc ., 477 U.S. 242, 255 (1986). Summary judgment is ... Berkel & Co ... Contractors v ... Palm & Assocs ., Inc ., ... ...