Woolen Mill Associates v. F.E.R.C.

Decision Date30 October 1990
Docket NumberNos. 89-1388,89-1389,s. 89-1388
Citation917 F.2d 589
PartiesWOOLEN MILL ASSOCIATES, Petitioner, v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent, Burlington Electric Department, City of Winooski, Vermont, Winooski One Partnership, Intervenors.
CourtU.S. Court of Appeals — District of Columbia Circuit

Carmen L. Gentile, with whom David E. Goroff and William J. Collins, Washington, D.C., were on the brief, for petitioner in 89-1388 and 89-1389.

Katherine Waldbauer, Atty., F.E.R.C., with whom William S. Scherman, General Counsel, and Joseph S. Davies, Deputy Sol., F.E.R.C., Washington, D.C., were on the brief, for respondent in both cases.

Peter C. Kissel, with whom Elisa J. Grammer, Washington, D.C., for Winooski One Partnership, Frances E. Francis and Marc R. Poirier, Washington, D.C., for Burlington Elec. Dept., and William J. Madden, Jr., Washington, D.C., for City of Winooski, were on the joint brief, for intervenors in both cases. William E. Wargo, Winooski, Vt., also entered an appearance, for intervenor City of Winooski.

Before MIKVA, SILBERMAN and HENDERSON, Circuit Judges.

Opinion for the Court filed by Circuit Judge HENDERSON.

HENDERSON, Circuit Judge:

The petitioner in these consolidated proceedings, Woolen Mill Associates ("WMA"), seeks review of orders issued by respondent Federal Energy Regulatory Commission (the "Commission") which (1) granted a license to the intervenors, The City of Burlington Electric Department ("Burlington") and the Winooski One Partnership (the "Partnership"), to construct, operate and maintain a hydroelectric project on the Winooski River in Chittenden County, Vermont and (2) certified the project as a Qualifying Small Power Production Facility. For the reasons set forth below, we deny the petitions for review.

I.

In 1980, Burlington applied to the Commission for a license to refurbish and expand an existing timber crib dam on the Winooski River near Burlington, Vermont, for the production of hydroelectric power. Some time later, Burlington reached an agreement with the Partnership to jointly undertake the project, to be known as the "Chace Mill Hydroelectric Project," and the two filed an amended application on November 3, 1986. At that time they planned to install bascule gates atop the timber crib dam, thereby restoring it to its original height of 136 feet above sea level 1 and enlarging its impoundment to approximately 5.5 acres, and to add an intake structure, two buried penhouses, a powerhouse, a tailrace and a fish trapping station. On March 30, 1987, Burlington and the Partnership filed a correction to the amended application reflecting plans both to consolidate the intake structure and powerhouse, eliminating the need for penhouses, and to install the bascule gates on a new concrete abutment immediately downstream from the existing timber crib dam rather than erecting them atop the existing dam as originally contemplated.

On August 21, 1987, the Commission issued a notice of application setting October 2, 1987, as the deadline for comments, protests or motions to intervene in the licensure proceeding. In response WMA, which owns an apartment building near the site of the proposed facility, filed with the Commission a document opposing the license and petitioning to intervene and several petitions and letters signed by area residents opposed to the licensure. On November 3, 1988, the Commission issued an order licensing the Chace Mill project. WMA then filed a petition for rehearing which the Commission denied by order dated April 21, 1989.

While the licensing proceeding was pending, Burlington and the Partnership also applied to the Commission for certification of the Chace Mill project as a Qualifying Small Power Production Facility under section 210 of the Public Utilities Regulatory Policies Act of 1978 ("PURPA"), as amended by section 8(a) of the Electric Consumers Protection Act of 1986 ("ECPA"), 16 U.S.C. Sec. 824a-3 (1988). WMA filed a petition to intervene in the certification proceeding and a motion to consolidate the certification and license proceedings. On October 3, 1988, the Commission issued an order granting WMA leave to intervene in the certification proceeding and certifying the Chace Mill project as a Qualifying Small Power Production Facility. WMA petitioned for rehearing on the certification and the petition was denied by order dated April 21, 1989.

WMA has petitioned this Court to review both the licensing and the certification orders. We address the two matters separately.

II.

First, WMA seeks review of the licensing orders on the grounds that (1) the record does not support the Commission's finding that the project is in the public interest and (2) the Commission deprived WMA of due process by failing to conduct a hearing or to provide requested discovery. We find neither ground meritorious.

First, we consider WMA's challenge to the Commission's finding that the Chace Mill project is in the public interest. Section 4(e) of the Federal Power Act authorizes the Commission to issue licenses to construct and operate dams on navigable streams. 16 U.S.C. Sec. 797(e) (1988); see Idaho Power Co. v. FERC, 865 F.2d 1313, 1314 (D.C.Cir.1989). Section 10(a) of the Federal Power Act requires as a condition for licensing that "the project adopted, including the maps, plans, and specifications, shall be such as in the judgment of the Commission will be best adapted to a comprehensive plan for improving or developing a waterway or waterways for the use or benefit of interstate or foreign commerce, for the improvement and utilization of water-power development, for the adequate protection, mitigation, and enhancement of fish and wildlife (including related spawning grounds and habitat), and for other beneficial public uses, including irrigation, flood control, water supply, and recreational and other purposes referred to in section 797(e) of this title." 16 U.S.C. Sec. 803(a) (1988). Pursuant to this provision, the Commission must, before issuing a license, make a determination that a given facility is "in the public interest," after considering all relevant factors, including "future power demand and supply, alternate sources of power, the public interest in preserving reaches of wild rivers and wilderness areas, the preservation of anadromous fish for commercial and recreational purposes, and the protection of wildlife." Udall v. FPC, 387 U.S. 428, 450, 87 S.Ct. 1712, 1724, 18 L.Ed.2d 869 (1967); see also Idaho Power Co. v. FERC, 865 F.2d at 1314-15; Friends of the River v. FERC, 720 F.2d 93, 97-98 (D.C.Cir.1983).

In the November 3, 1988 licensing order, the Commission, relying on an "Environmental Assessment" produced by its staff and appended to the order, concluded the project is in the public interest because a need for additional energy exists which the Chace Mill facility can help fill. At the same time, the Commission concluded, the Chace Mill facility will conserve nonrenewable energy sources and reduce pollution by displacing fossil fuel power generation. In its rehearing order, the Commission further found, relying on a staff "Safety and Design Assessment" which had been appended to the November 3, 1988 order, that the project will serve the public interest by providing economic benefit in the form of an annual levelized savings of $603,000 over alternative energy sources. In addition, both orders found that construction of the project will not have any significant adverse effect on the environment or on WMA's rental income. WMA's challenge notwithstanding, all of these findings are supported by substantial evidence, namely the findings and data set forth in the Environmental Assessment 2 and in the Safety and Design Assessment. 3 Accordingly, we decline to review the Commission's conclusion that the project is in the public interest. See 16 U.S.C. Sec. 825 l(b) (1988); Friends of the River, 720 F.2d at 98.

Next, we consider WMA's contention that the Commission deprived it of due process by failing to hold a hearing or provide discovery. We reject this argument for the following reasons.

First, the decision whether to conduct a hearing is in the Commission's discretion, Cerro Wire & Cable Co. v. FERC, 677 F.2d 124, 128 (D.C.Cir.1982), and it is not an abuse of that discretion to deny a motion for hearing when there are no material facts in dispute, Pennsylvania Pub. Utility Comm'n v. FERC, 881 F.2d 1123, 1126 (D.C.Cir.1989); Cerro, 677 F.2d at 128-29. Further, mere allegations of disputed fact are insufficient to mandate a hearing; a petitioner must make an adequate proffer of evidence to support them. Pennsylvania, 881 F.2d at 1126; Cerro, 677 F.2d at 124. We find no abuse of discretion in the Commission's failure to conduct a formal evidentiary hearing as the record reveals no substantial evidence contradicting any material finding by the Commission. In addition, we note that WMA had ample opportunity to submit whatever evidence it desired throughout the licensure proceeding. Accordingly, we find no due process violation in the Commission's failure to conduct a formal hearing.

Nor do we find any deprivation of due process in the alleged discovery denial. WMA requested two broad classes of documents in letters its counsel sent to the Director of the Commission's Office of Hydroelectric Licensing. 4 The Commission's rules, however, require that any request for the documents sought be made pursuant to the Freedom of Information Act, 18 C.F.R. Sec. 380.9 (1990), and that the request be "in writing, addressed to the Director of Public Affairs, and clearly marked Freedom of Information Act Request." 18...

To continue reading

Request your trial
10 cases
  • Environmental Defense Fund, Inc. v. E.P.A.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (District of Columbia)
    • 19 Abril 1996
    ...a reasonable exercise of the Agency's express statutory discretion to set conformity determination deadlines. See Woolen Mill Assocs. v. FERC, 917 F.2d 589, 593 (D.C.Cir.1990). III. Next, the petitioners challenge two additional regulations on the ground that they permit untimely implementa......
  • Moreau v. F.E.R.C.
    • United States
    • United States Courts of Appeals. United States Court of Appeals (District of Columbia)
    • 15 Enero 1993
    ...that FERC need not conduct an evidentiary hearing when there are no disputed issues of material fact, see, e.g., Woolen Mills Assocs. v. FERC, 917 F.2d 589, 592 (D.C.Cir.1990); Pennsylvania Pub. Util. Comm'n v. FERC, 881 F.2d 1123, 1126 (D.C.Cir.1989), and that even where there are such dis......
  • Rover Pipeline, LLC & Energy Transfer Partners, L.P.
    • United States
    • Federal Energy Regulatory Commission
    • 20 Enero 2022
    ... 178 FERC ¶ 61, 028 Rover Pipeline, LLC and Energy Transfer Partners, L.P. No. ...v. FERC , 129 F.3d 157, 164 (D.C. Cir. 1997); see also. Woolen Mill Assocs. v. FERC , 917 F.2d 589, 592 (D.C. Cir. 1990); Minisink ......
  • Safety v. Fed. Energy Regulatory Comm'n
    • United States
    • United States Courts of Appeals. United States Court of Appeals (District of Columbia)
    • 15 Agosto 2014
    ...(alteration in original). We review the Commission's denial of a hearing request for abuse of discretion. Woolen Mill Assocs. v. FERC, 917 F.2d 589, 592 (D.C.Cir.1990). Petitioners assert that a hearing would have resolved “several key factual disputes,” but when push comes to shove, they p......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT