Transamerica Ins. Co. v. U.S.

Decision Date24 March 1993
Docket NumberNo. 91-5099,91-5099
Citation989 F.2d 1188
Parties, 38 Cont.Cas.Fed. (CCH) P 76,495 TRANSAMERICA INSURANCE COMPANY, Plaintiff-Appellant, v. The UNITED STATES, Defendant-Appellee.
CourtU.S. Court of Appeals — Federal Circuit

John V. Burch, P.C., Bovis, Kyle & Burch, Atlanta, GA, argued for plaintiff-appellant.

Edward G. Gallagher, Wickwire Gavin, P.C. Washington, DC, argued for amicus curiae, American Ins. Ass'n.

Richard E. Rice, Atty., Commercial Litigation Branch, Dept. of Justice, Washington, DC, argued for defendant-appellee. With him on the brief were Stuart M. Gerson, Asst. Atty. Gen., David M. Cohen, Director and Terrence S. Hartman, Asst. Director. Also on the brief was Reeves Lewis, Trial Atty., U.S. Army Corps of Engineers, of counsel.

Before PLAGER, LOURIE and RADER, Circuit Judges.

PLAGER, Circuit Judge.

Plaintiff Transamerica Insurance Company (Transamerica) was the performance bond surety on two construction contracts with defendant United States (United States or government), the second of which was defaulted on by the contractor. Transamerica sued the government, under the doctrine of equitable subrogation, for recovery of funds payable by the government to the contractor under an equitable adjustment to the first contract, which the contractor sought and obtained after completing the first contract. The funds were sought as mitigation of Transamerica's losses incurred when it took over and completed performance of the second contract. The Court of Federal Claims 1 granted the motion of the government for judgment on the pleadings, and dismissed Transamerica's complaint. 2 We reverse and remand for further proceedings.

BACKGROUND

The United States, through the U.S. Army Corps of Engineers, entered into two separate contracts with the Bodenhamer Building Corporation (Bodenhamer), both regarding construction at Fort Bragg, North Carolina. Contract No. DACA-21-85-C-0104 (the 0104 contract) was for construction of the Commissary Warehouse and Class VI Store--it will be referred to hereafter as the Commissary contract--and Contract No. DACA-2187-C-0054 (the 0054 contract) was for construction of the Bowley Elementary School--hereafter the School contract. Transamerica, a surety bond company, issued payment and performance bonds for both of the contracts on behalf of Bodenhamer for the benefit of the government.

Bodenhamer defaulted on the School contract. Transamerica, pursuant to its obligations as surety, took over and completed the construction of the elementary school by obtaining a replacement contractor. Transamerica claims that it incurred over $1,000,000 in losses while undertaking its obligations under this performance bond.

Bodenhamer apparently completed its work under the Commissary contract, and filed a claim with the Corps of Engineers for equitable adjustment in an amount exceeding $500,000. Transamerica, having closely monitored Bodenhamer's progress on its claim for adjustment, sought the funds owed by the government to Bodenhamer pursuant to the settlement reached on the claim. Transamerica claims that it gave written notice to the government that it sought under the doctrine of equitable subrogation the funds owed Bodenhamer. However, the government disbursed the funds to Bodenhamer.

Transamerica sued the government in the Court of Federal Claims, arguing that it had been damaged by the government's disregard of Transamerica's right of equitable subrogation. Transamerica argued that it was therefore entitled to damages from the government.

The government moved to dismiss Transamerica's claim for lack of jurisdiction and for failure to state a claim upon which The Court of Federal Claims thus rejected Transamerica's argument that it was entitled to set off its losses incurred under the School contract against funds owed to Bodenhamer under the Commissary contract. Transamerica had argued that, because the government could have set off any losses it incurred through completion of the School contract against funds it owed to the contractor under the Commissary contract, Transamerica could, under equitable subrogation, step into the government's shoes and set off the losses it incurred through completion of the same contract against these same funds. In coming to its conclusion, the Court of Federal Claims relied largely on Dependable Ins. Co. v. United States, 846 F.2d 65 (Fed.Cir.1988), and the authorities cited therein, viz., Security Ins. Co. v. United States, 428 F.2d 838, 192 Ct.Cl. 754 (1970); Ram Constr. Co. v. American States Ins. Co., 749 F.2d 1049 (3d Cir.1984); Western Casualty & Sur. Co. v. Brooks, 362 F.2d 486 (4th Cir.1966); Balboa Ins. Co. v. United States, 775 F.2d 1158 (Fed.Cir.1985); and Universal Sur. Co. v. United States, 10 Cl.Ct. 794 (1986). The Court of Federal Claims reasoned that these authorities stand for the proposition that a "surety's rights and remedies are limited to recovery of retained funds from the contract generating the claim," id. at 677 (citing Dependable, 846 F.2d at 67), and that this result is not changed just because the surety enters into a number of construction bonds with the same contractor. Id. Therefore, Transamerica could not set off its losses against the funds owed to Bodenhamer because those losses arose out of a different contract. Id.

                relief may be granted.   The Court of Federal Claims concluded it had jurisdiction;  that issue is not appealed here and need not be further addressed.   However, once the court reached the merits of Transamerica's argument, it concluded that "Transamerica as performance bond surety on Contract 0054 [the School contract] is unable to recover funds the government owed to Bodenhamer on Contract 0104 [the Commissary contract]."  22 Cl.Ct. at 677
                

Transamerica appealed here, challenging the Court of Federal Claims' decision. Transamerica argues, as it did before the Court of Federal Claims, that the instant action is distinguishable from, and warrants a different result than that in, Dependable and the cases cited therein. In Transamerica's view, Dependable involved a situation in which the government had a competing claim to the funds at issue; the use of those funds to offset the surety's losses would have preempted the government's competing claim. Here, since the government has no such competing claim that could be preempted, Transamerica should be able to offset through equitable subrogation its losses against these funds.

Transamerica points out that this result provides an incentive for a surety to complete a project, as usually preferred by the government, because the surety is not made any worse off than the surety would have been had the government chosen to complete the project itself. Any loss is most efficiently, and most fairly, shifted to the defaulting contractor, who is really the party responsible for the loss.

In support of its position, Transamerica cites us to District of Columbia v. Aetna Ins. Co., 462 A.2d 428 (D.C.Ct.App.1983). That case concerned a performance bond surety for two public works projects with the District of Columbia government involving the same contractor. 462 A.2d at 429. Upon default by the contractor on one of the projects, the surety completed the project and then sought to recover through equitable subrogation funds arising from the other project which the contractor completed. As in the present situation, the surety in District of Columbia gave written notice to the District asserting its rights to the funds owed the contractor by the District on the contractor-completed contract. The surety and the contractor were the only claimants for the retained funds; the District was only a stakeholder. Nevertheless, the district later disbursed the funds to the contractor.

The surety in District of Columbia sued the District, arguing that it was subrogated to the rights of the District to offset its where, as here, the only claimants to monies held by a government agency are the surety and a defaulting contractor, the surety who has performed under a public works performance bond agreement, upon full satisfaction of its surety obligation, is subrogated to all of the rights and remedies which the government might have had against the principal had the government been forced to complete the project itself. Among these remedies is the common law right of setoff.

                loss against the profit on the second contract.   The Court of Appeals held that
                

. . . . .

In the present situation, the District had notice of both the facts giving rise to an equitable right in Aetna, and Aetna's claim under these rights as manifested in the letters.... We have found no limitations upon the right of subrogation which would justify the District's actions in this instance.

... [W]e do not suggest that the District of Columbia must or should engage in an interpleader action in each of its many construction projects. Rather, we simply hold that in the absence of other competing parties where a surety gives a reasonable written notice of a claim adverse to that of a defaulting contractor for whom it has performed its bond, prudent use of the interpleader process may assist the District in resolving the dispute rather than burden it.

462 A.2d at 432 (footnote omitted).

A brief on appeal was also filed in this case by the American Insurance Association (AIA), as Amicus Curiae, supporting Transamerica's position. AIA argues that, under general surety law, Transamerica is subrogated to whatever rights the government could have asserted against Bodenhamer had the government completed the School contract. The government could have offset any losses it might have incurred had it completed the School contract itself against the funds it owed Bodenhamer under the Commissary contract. Therefore, as the completing surety and under the doctrine of equitable subrogation, Transamerica should have access to the same offset.

The government argues that the Court...

To continue reading

Request your trial
8 cases
  • Dunn & Black, P.S. v. U.S.
    • United States
    • U.S. District Court — District of Washington
    • 25 d5 Fevereiro d5 2005
    ...the dates the bonds were issued. The bond for the Warren Project was issued on July 12, 1999. Further, relying on Transamerica Ins. Co. v. U.S., 989 F.2d 1188 (Fed.Cir.1993), intervenors argue that when a surety has bonded multiple projects with the same principal and obligee, the surety ma......
  • Fid. & Guaranty Ins. Underwriters, Inc. v. United States
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 6 d5 Novembro d5 2015
    ...contractor's default. See, e.g., Nat'l Sur. Corp. v. United States, 118 F.3d 1542, 1545 (Fed.Cir.1997) (following Balboa ); Transamerica Ins. Co., 989 F.2d at 1194–95 (same).II.On appeal, USF & G does not contend that it was in privity of contract with the Postal Service. Rather, as it did ......
  • Insurance Co. of the West v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 23 d5 Março d5 2001
    ...Balboa, 775 F.2d at 1161-63; Nat'l Sur. Corp. v. United States, 118 F.3d 1542, 1545 (Fed. Cir. 1997); Transamerica Ins. Co. v. United States, 989 F.2d 1188, 1194-95 (Fed. Cir. 1993). Notice from the surety to the government was essential, for the government owes no duty to the surety unless......
  • Fireman's Fund Ins. Co. v. England
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 27 d3 Novembro d3 2002
    ...to which they were not a party. See Balboa Ins. Co. v. United States, 775 F.2d 1158, 1160 (Fed.Cir.1985); Transamerica v. United States, 989 F.2d 1188 (Fed.Cir.1993). Fireman's Fund's reliance on those cases is misplaced. They were suits for damages against the United States brought in what......
  • Request a trial to view additional results
2 books & journal articles
  • Project update 1995: illustrative provisions of a general indemnity agreement taken in connection with contract surety bonds.
    • United States
    • Defense Counsel Journal Vol. 62 No. 2, April 1995
    • 1 d6 Abril d6 1995
    ...held that completing sureties can be entitled to funds from other contracts for the same obligee. Transamerica Ins. Co. v. United States, 989 F.2d 1188, reh'g denied, 998 F.2d 972 (Fed. Cir. 1993); District of Columbia v. Aetna Ins. Co., 462 A.2d 428 (D.C. 1983); Ram Constr. Co. Inc. v. Ame......
  • Annual survey of fidelity and surety law, 1993.
    • United States
    • Defense Counsel Journal Vol. 61 No. 1, January 1994
    • 1 d6 Janeiro d6 1994
    ...Ins. Co. v. United States, 16 Cl.Ct. 555 (1989); United States Fidelity and Guaranty Co. v. United States, 16 Cl.Ct. 541 (1989). (41.)989 F.2d 1188 (Fed.Cir. 1993), rev'g and remanding 22 Cl.Ct. 674 (42.)462 A.2d 428 (D.C.App. 1983).

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT