ADC Fairways Corp. v. Johnmark Const., Inc., 821067

Decision Date25 April 1986
Docket NumberNo. 821067,821067
Citation343 S.E.2d 90,231 Va. 312
PartiesADC FAIRWAYS CORPORATION v. JOHNMARK CONSTRUCTION, INC. Record
CourtVirginia Supreme Court

Roger E. Warin (Robert E. McLaughlin, Jeffrey P. Moran, Elizabeth A. Noyes-Palmer, Felice Busto, Steptoe & Johnson, Washington, D.C., on briefs), for appellant.

Gary A. Reese (Patterson & Reese, Fairfax, on brief), for appellee.

Present: CARRICO, C.J., COCHRAN, POFF, COMPTON, STEPHENSON and THOMAS, JJ., and GORDON, Retired Justice.

THOMAS, Justice.

This is a contract dispute. ADC Fairways Corporation was a real estate development company engaged in the business of rehabilitating apartment buildings and converting them for sale as condominiums. On March 12, 1980, ADC entered into a contract with Johnmark Construction, Inc. for the rehabilitation and conversion of the Ivymount apartments in northern Virginia. This was the second such contract between ADC and Johnmark.

Pursuant to the Ivymount contract, Johnmark agreed to turn over to ADC approximately seven rehabilitated units per week beginning April 18, 1980. Johnmark fell behind in its delivery schedule. A dispute arose between the parties as to the cause of the delay in rehabilitating the Ivymount units. In order to resolve this dispute, the parties, on June 18, 1980, executed a modification of the March 12, 1980 contract. The modified contract brought the parties current in payments and essentially forgave all matters theretofore in dispute.

Under the June 18 modification, Johnmark agreed to rehabilitate and turn over to ADC seven units per week beginning July 3, 1980. On that date, the promised seven units were not ready. An ADC employee, frustrated about the continued delay, directed Johnmark to leave the job; this directive was not authorized by ADC. Johnmark returned to work on July 8 or 9, 1980, having lost approximately two working days. Pursuant to the modified agreement, seven more units, in addition to the seven due on July 3, 1980, were to be turned over to ADC on July 10, 1980. According to ADC, the units were not ready at that time. Ultimately, on July 24, 1980, each party advised the other that they viewed the contract to have been breached. On that day, Johnmark left the job permanently.

Johnmark sued ADC claiming that ADC breached the contract by insisting "upon changing the lighting fixtures, moldings, appliances, etc., after they were installed or ordered, and refused to pay extra for the change or approve the units until the changes had been made;" by instructing its employees " 'to find something wrong with the units' even if there was nothing wrong, and thereby to avoid or delay paying the Plaintiff;" and by "arbitrarily refusing to accept units; delaying payments; making changes; and altering approval procedures."

ADC denied that it breached the contract and asserted, by way of defense, that Johnmark had breached the contract by failing "to perform under the terms of the contracts as modified ... and pursuant to letter communication of July 24, 1980." ADC also contended that by entering the June 18 modification Johnmark waived "any and all claims, disputes, actions and or causes of action" that Johnmark may have had against ADC prior to June 18, 1980. Finally, ADC claimed that because Johnmark was the breaching party, even if ADC owed monies to Johnmark, ADC was nevertheless entitled to an offset for additional costs to complete the Ivymount project.

The case was tried to the court sitting without a jury. The trial court ruled that ADC was the breaching party. On the issue of breach, the trial court explained in a bench ruling as follows: "I find that the Plaintiff [Johnmark] did perform under the contract. I find that delays were caused by ADC, going right to the top man, Daly, whose employees would change things and Daly would change that, adding expense to his own business, extra time, and extra work to the Plaintiff."

With regard to the issue of offset, the trial court said two things: First, that because the delays were attributable almost solely to ADC, ADC was not entitled to an offset for costs to complete the project. Second, the court found that ADC failed to prove the amount of the claimed offset.

On appeal, ADC contends the trial court erred in three ways: (1) in finding that Johnmark performed properly under the contract; (2) in awarding lost profits to Johnmark; and (3) in failing to allow ADC an offset for increased interest costs incurred by ADC because of delays in completing the contract. We will discuss the assignments of error in sequence.

I. Breach

A. Breach by ADC

The trial court ruled that Johnmark performed the contract while ADC breached. ADC contends that the situation is the other way around. According to ADC, the essence of the trial court's opinion regarding breach is that ADC continued to make changes in the choice of certain items to be installed in the units and therefore wrongfully delayed Johnmark in the completion of the work. ADC says that pursuant to the contract and the modification, it had a right to call for changes and thus cannot be held liable for breach for doing what it had a right to do. Second, ADC submits that Johnmark cannot rely on any delay caused by ADC unless Johnmark requested in writing an extension of time for the delay caused by ADC. Without such a written request, ADC contends, Johnmark cannot complain of the delay.

The problem with the arguments advanced by ADC is that they do not respond fully to all the grounds upon which the trial court concluded that ADC breached the contract. Consequently, even if we were to rule in favor of ADC on both points, we would still have to affirm the trial court's determination. This is so because the trial court also found that ADC breached by dismissing Johnmark from the job without complying with the terms of the contract and by the actions of ADC inspectors who "purposely" picked at inconsequential items for the purpose of "delaying payment." Both of these conclusions are supported by credible evidence. Thus, the trial court's determination that ADC breached must be affirmed.

2. Breach by Johnmark

ADC contends further that even if it breached, so did Johnmark. The importance of this contention appears to be that if Johnmark breached, it cannot recover damages for lost profits.

With regard to Johmark's breach, ADC says Johnmark did not complete the units in a workmanlike manner on the schedule set forth in the contract and that Johnmark failed to submit a written request for extension of time as required by the contract. The first two points have been resolved against ADC by the trial court's ruling that the units were arbitrarily refused and that Johnmark was wrongfully dismissed from the job. To say that Johnmark's work was arbitrarily refused is tantamount to saying that its work was of a quality that it should have been accepted. Thus, ADC's contention that the work was not done in a workmanlike manner must be rejected. Further, to say that the work was arbitrarily rejected and that Johnmark was wrongfully dismissed from the job is tantamount to saying that Johnmark is not responsible for not meeting the construction schedule. Thus, ADC's second point must also be rejected.

...

To continue reading

Request your trial
15 cases
  • Harmon v. Cb Squared Services Inc.
    • United States
    • U.S. District Court — Eastern District of Virginia
    • 2 de junho de 2009
    ...contract where he himself has breached the contract." Def. Br. in Supp. at 7 (emphasis added) (citing ADC Fairways Corp. v. Johnmark Construction, Inc., 231 Va. 312, 343 S.E.2d 90 (1986)). Because Plaintiff advances no breach of contract claims against Defendant CB Squared, however, the Cou......
  • Preferred Sys. Solutions, Inc. v. GP Consulting, LLC
    • United States
    • Virginia Supreme Court
    • 14 de setembro de 2012
    ...Claims for compensatory damages—in this case, lost profits—must be proved with reasonable certainty. ADC Fairways Corp. v. Johnmark Constr., Inc., 231 Va. 312, 318, 343 S.E.2d 90, 93 (1986). The standard of review for a damages calculation has been framed as whether there were “sufficient f......
  • Commercial Business Systems, Inc. v. Bellsouth Services, Inc.
    • United States
    • Virginia Supreme Court
    • 13 de janeiro de 1995
    ...Goldstein v. Kaestner, 243 Va. 169, 173, 413 S.E.2d 347, 349-50 (1992). BellSouth, relying largely upon ADC Fairways Corp. v. Johnmark Const., Inc., 231 Va. 312, 343 S.E.2d 90 (1986), contends that CBS's revenue and cost estimates under a contract equivalent to Halifax's contract were too s......
  • Suntrust Mortg., Inc. v. United Guar. Residential Ins. Co. of North Carolina
    • United States
    • U.S. District Court — Eastern District of Virginia
    • 19 de agosto de 2011
    ...defense pled by a party in its capacity as a defendant.33 The Supreme Court of Virginia's decision in ADC Fairways Corp. v. Johnmark Construction, Inc., 231 Va. 312, 343 S.E.2d 90 (1986), further undermines UG's assertion that contract damages and the first material breach doctrine are mutu......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT