Aero Corp. v. Department of the Navy, Civ. A. No. 79-2944.

Decision Date04 March 1981
Docket NumberCiv. A. No. 79-2944.
Citation493 F. Supp. 558
PartiesAERO CORPORATION, Plaintiff, v. DEPARTMENT OF THE NAVY, Defendant.
CourtU.S. District Court — District of Columbia

Roger N. Boyd, Jean-Pierre Swennen, Frederick W. Claybrook, Jr., Crowell & Moring, Washington, D.C., for plaintiff.

Charles F. C. Ruff, U. S. Atty., Royce C. Lamberth, Cameron McGowan Currie, Asst. U. S. Attys., Washington, D.C., for defendant; Jeffrey N. Eisenstein, John G. Judy, William K. Mahn, Dept. of the Navy, Washington, D.C., of counsel.

MEMORANDUM

OBERDORFER, District Judge.

I

This case involves the claim of plaintiff, Aero Corporation ("Aero"), that the determination of defendant, Department of the Navy ("Navy"), to make a sole-source award of a contract to perform the Service Life Extension Program ("SLEP") on twenty C-130 aircraft to Lockheed-Georgia Company ("Lockheed") was improper. Aero also seeks mandamus to compel the Navy to refer the question of Aero's capability to perform the contract for determination by the Small Business Administration.

Aero filed this action on October 30, 1979, four days after filing a bid protest with the General Accounting Office ("GAO"). Following hearings on Aero's request for a temporary restraining order on October 30 and 31, the Court declined to grant any injunctive relief because the Navy represented that award of the sole-source contract to Lockheed was not imminent. The parties were directed to agree to an expedited discovery schedule to permit an early decision on the merits by the GAO. Counsel negotiated a stipulation providing for (1) expedited discovery and (2) an agreement by the Navy not to award the contract until November 30, 1979, or until the GAO decided Aero's protest, whichever was sooner. By Order of November 1, 1979, the Court approved the stipulation and requested that the GAO expedite its consideration of the protest to provide an interim report on or before November 16, 1979.

On November 16, the GAO notified the Court and the parties that a decision on the protest would not be available before December 18, 1979. Consequently, the Court held hearings on November 19 and 20, 1979, to consider whether relief was necessary pending a decision by the GAO. At those hearings, Aero renewed its request for a preliminary injunction; the Navy reasserted its position that the SLEP program, and the Navy's consequent ability to meet its operational requirements, would be jeopardized if it did not award a contract by November 30, 1979. The Navy represented that (1) no aircraft would be "inducted" into SLEP before May, 1980, and (2) any contract with Lockheed could be terminated without prejudice to Aero if the GAO or the Court so directed.

On the basis of the Navy's representations and arguments of counsel, the Court entered an Order on November 21 denying Aero preliminary relief. The Order also embodied a Declaratory Judgment that the Navy had breached its statutory duty under 10 U.S.C. § 2304 and 2310 to facilitate review by the Court and the GAO of its decision to make a sole-source award. The Order further declared that the Navy "should not enjoy any equitable or legal advantage on account of the award of the contract, its performance in whole or in part, or the mere passage of time between now and December 31, 1979." The Order left the Navy free to enter into a letter contract with Lockheed for SLEP. The Navy and Lockheed executed such a contract on November 30, 1979. The contract called for the performance of SLEP on 13 planes, with an option to increase the total to 20 C-130's.

The Order of November 21, 1979, as further explained by Memorandum of November 28, 1979, was predicated on an indication from GAO that it could render a decision in Aero's bid protest, Docket No. B-194445.3 by December 18. The relief granted was intended to preserve the equities, while permitting the Navy and Lockheed to begin necessary pre-performance activities pending the GAO decision.

On December 14, the GAO, through its Associate General Counsel, informed the Court that it would not be able to render a decision on December 18, but was "making every effort to have a decision by December 21." At a hearing held that afternoon to consider the effect of the delay, plaintiff sought (1) to extend the effect of the Declaratory Judgment beyond December 31, if the hearing on the preliminary injunction, then scheduled for December 21, were delayed; (2) to prevent the Navy from exercising its option to expand the initial SLEP contract from 13 to 20 planes; (3) to limit the contract already in force to the preparation of parts, for which Aero has not sought to compete; and (4) to require the Navy to prepare a competitive bid package in the event that the contract was ruled invalid.

In response, the Navy represented that it would limit the option for the additional planes to the procurement of parts only. The Navy also asserted that in the event that SLEP installation were ultimately opened for competitive bidding, Lockheed would accrue no competitive advantage from its part-performance of the letter contract, since any parts or plans prepared by Lockheed would become the property of the U.S. Government.

In view of these representations, the Court found that Aero was suffering no prejudice from the prospective delay in the GAO decision, and declined to modify the relief already granted.

On December 21, the GAO reached its decision on Aero's bid protest, a copy of which is attached hereto as Appendix I. The GAO found that the Navy's decision to award a sole-source contract to Lockheed for 13 planes was not arbitrary. On the same day, a hearing was held on Aero's further motion for a preliminary injunction, at which it was decided to conduct a final hearing on the merits on February 4 and 5, 1980. An Order filed December 21, 1979, amended the Order of November 21 to reflect additional representations by the Navy that (1) none of the C-130 aircraft would be "inducted" into SLEP before February 5; and (2) that the Navy would not exercise the option for the installation portion of SLEP for the seven additional aircraft before February 5, 1980.

On January 30, 1980, Aero filed a Pretrial Brief. On February 1, 1980, the Navy filed a motion for summary judgment. The Court has elected to treat the parties' submissions as cross-motions for summary judgment, supported by exhibits, affidavits and testimony which eliminate any material factual dispute. Having reviewed these submissions, and on the basis of the hearings and entire record of this case, the Court finds that the Navy is entitled to partial summary judgment; its determination that competitive procurement of SLEP for the first 20 C-130's was reasonable and supported by substantial evidence. Aero is entitled to partial summary judgment on its claim that under the circumstances of this case, the Navy prevented Aero from obtaining timely and meaningful review of the Navy's procurement decision before this Court and the GAO. The Navy is also entitled to summary judgment on Aero's assertion that its capability to perform SLEP must be referred to the Small Business Administration for determination.

On February 8, 1980, Aero filed a motion pursuant to Rule 21, Fed.R.Civ.P., to add the Lockheed Corporation as a defendant. Both Lockheed and the Navy have opposed the motion, which the Court will deny without prejudice to its renewal by Aero if the presence of Lockheed as a party ultimately proves appropriate in order to accord Aero complete relief.

II

Findings of Fact:

1. The program at issue is the Service Life Extension Program ("SLEP") of forty-nine Navy and Marine Corps C-130 series aircraft.

2. SLEP is a program to replace or restore parts of the aircraft to extend its service life to 25,000 flight hours.

3. SLEP provides for the replacement of approximately thirty-nine parts regardless of whether they are in immediate need of service, with the exception of three parts that are inspected and replaced only if necessary. SLEP also involves several miscellaneous tasks, including upgrading field manuals and related functions.

4. Three aircraft series are included in the program: the C-130 itself, as well as the KC-130's (tankers used by the Marine Corps), and EC-130's. The EC-130's are so-called "TACAMO aircraft" that are used for communications with fleet ballistic submarines.

5. SLEP involves both the procurement and the installation of parts required to extend the life of the C-130 aircraft. The dispute underlying this action involves Aero's interest in competing for the installation phase of SLEP.

6. The Navy's C-130 fleet is currently maintained through periodic induction for Standard Depot Level Maintenance ("SDLM") and through drop-in repair. Under the SLEP program, the Navy plans to perform SDLM concurrently with SLEP.

7. Under SDLM, each aircraft is inspected and parts are replaced as necessary. Drop-in repair is performed by the SDLM contractor on aircraft in need of repair prior to the next regular SDLM induction.

8. Aero has won all competitive NAVY SDLM procurements for the C-130 and has been the exclusive SDLM contractor for the Navy in the United States for the past nine years. Aero's current SDLM contract with options extends into 1983. The Navy proposes to award contracts to Lockheed on a sole-source basis for SLEP and concurrent SDLM with respect to forty-nine aircraft. This plan will foreclose Aero's SDLM business opportunity to render SDLM service with respect to these C-130's.

9. Navy planning for SLEP began in January of 1977 with the establishment of a C-130 SLEP program subject to formal procurement planning in accordance with the Defense Acquisition Regulation ("DAR") § 1-2100. This required a procurement plan to be prepared to present an analysis of the program and to document the technical, small business, policy, operational, and other procurement considerations.

10. On February 10, 1978, the Cognizant Field Activity ...

To continue reading

Request your trial
8 cases
  • Aero Corp. v. Department of the Navy
    • United States
    • U.S. District Court — District of Columbia
    • February 16, 1983
    ...General Accounting Office (GAO), C.R. A-35, considering briefs and documentary evidence and holding a hearing, the Court filed a Memorandum (Aero I) finding and concluding that, due to the military urgency of the SLEP induction schedule,6 defendant's sole-source award of the initial SLEP co......
  • McKay v. Rockwell Intern. Corp.
    • United States
    • U.S. Court of Appeals — Ninth Circuit
    • April 20, 1983
    ...Co., 231 F.Supp. 447, 450 (S.D.N.Y.1964); see also Morrison v. Larsen, 446 F.2d 250, 253 (9th Cir.1971); Aero Corp. v. Department of the Navy, 493 F.Supp. 558, 567 (D.D.C.1981). Trials on design defects where government specifications are at issue would "involve second-guessing military ord......
  • Aero Corp. v. Department of the Navy
    • United States
    • U.S. District Court — District of Columbia
    • April 26, 1982
    ...an additional seven aircraft was not unlawful, even though the contracts were negotiated without competition. Aero Corp. v. Department of the Navy, 493 F.Supp. 558, 556-67 (1980). With respect to the other 29 aircraft that the Navy planned to overhaul in the SLEP program, however, the Court......
  • Minnesota Min. and Mfg. Co. v. Shultz, Civ. A. No. 83-3819.
    • United States
    • U.S. District Court — District of Columbia
    • February 28, 1984
    ...statutes or regulations. Kentron Hawaii, Limited v. Warner, 480 F.2d 1166, 1169 (D.C.Cir.1973); Accord, Aero Corp. v. Department of the Navy, 493 F.Supp. 558, 566 (D.D.C.1981); Dickey-John Corp. v. Bergland, 444 F.Supp. 451, 455 (D.D.C.1978). As the Court of Appeals admonished in Allis-Chal......