Allis-Chalmers Co. v. City of Atlantic, Cass County
| Decision Date | 13 December 1913 |
| Citation | Allis-Chalmers Co. v. City of Atlantic, Cass County, 144 N.W. 346, 164 Iowa 8 (Iowa 1913) |
| Parties | ALLIS-CHALMERS COMPANY, Appellee, v. CITY OF ATLANTIC, CASS COUNTY, Appellant |
| Court | Iowa Supreme Court |
Appeal from Cass District Court.--HON. E. B. WOODRUFF, Judge.
ACTION at law to recover for alleged conversion of electrical machinery and fixtures. From a verdict and judgment in favor of the plaintiff, this appeal is taken by the defendant.
Reversed.
Thomas Whitmore, W. R. Green, C. A. Meredith, and Thomas B. Swan for appellant.
Max W Babb, Willard & Willard, and H. C. Case, for appellee.
I.
This action was brought to recover for the conversion of certain electrical machinery. The appellee claims: That the appellant converted to its own use fifty-eight transformers, three exciters, one 230 K. W. generator, and one switchboard, and that by reason of said conversion the appellee is damaged in the sum of $ 8,284.06, with interest thereon from November 8, 1911, at 6 per cent. That the appellee contracted said property to one Joseph A. Bortenlanger, conditionally, appellee retaining the title to or ownership of said property, "until full and final payment therefor shall have been made according to the terms of said contract, which was as follows: 80 per cent. on or before the 10th of the month following shipment; 20 per cent. on completion of plant, but in any event not later than four months from date of shipment." The exciters and transformers arrived at Atlantic about the 18th day of July, 1911. The generator and switchboard reached Atlantic about the 26th day of July, 1911. No part of the consideration has ever been paid, and the appellant is in possession of said property in controversy, having refused to deliver the same to appellee upon demand made prior to the commencement of this action.
For answer the defendant claimed that the plaintiff sold, furnished, and delivered said transformers, exciters, generator, and switchboard, and each and all of them, to said Joseph A. Bortenlanger with the intention and for the purpose of having the said Bortenlanger use the same in the construction of a power plant and lighting system for the defendant city under a contract which the said Joseph A. Bortenlanger Company had with the defendant city, and the said Joseph A. Bortenlanger did so use the same with the knowledge and consent of the plaintiff. It therefore alleges: That plaintiff is barred and estopped from maintaining this action, because it first clothed Joseph A. Bortenlanger with the indicia of ownership by delivering the property in question to him, and then without objection stood by and permitted appellant, without any notice, actual or constructive, of the claim made thereto by appellee, to pay Joseph A. Bortenlanger, its contractor, $ 3,352.40, or 90 per cent. of the estimated value of the transformers and exciters, and by reason of such payment the appellant claims to have the right of possession of all the property in controversy, and that the appellee is barred and estopped from asserting title thereto. That Joseph A. Bortenlanger, who had agreed with the appellant to furnish the material and build for it an electric light and power plant and install in said appellant's power house on appellant's land, used said property in controversy, and the same had become a fixture thereto, and thereby had become and was the absolute property of the appellant. It is also pleaded and was proven that Bortenlanger failed to complete his contract, became insolvent, and that the defendant city was compelled to take charge of and finish the work at large expense to itself above the original contract price. It denies that it had notice, actual or constructive, of plaintiff's claim, alleges that payments were made by it to Bortenlanger under their contract from time to time as he became entitled to such, and that included in the estimates for which payments were made were the items for which recovery is now sought by the plaintiff.
There was a trial to a jury, resulting in a verdict in favor of plaintiff for $ 8,284.06, with interest, and the defendant appeals.
II. The appellant is a city of the second class; the appellee was at the time of the transaction under consideration a foreign corporation, with its principal place of business outside of Iowa; and Joseph A. Bortenlanger and the Joseph A. Bortenlanger Company were also nonresidents of the state. Desiring to erect and establish an electric light plant for municipal purposes, the city of Atlantic, on the 21st day of March, 1911, entered into a contract with the Joseph A. Bortenlanger Company under which the latter, for a consideration of $ 43,000 and certain old machinery, agreed to furnish and install the necessary machinery and fixtures, and to furnish all material and labor for the completion of the plant according to the plans and specifications which were made the basis of the contract. On March 15, 1911, Allis-Chalmers Company made proposal to furnish certain machinery for said work, such proposal having been directed to Mr. Joseph Bortenlanger for the city of Atlantic, Iowa which was on the 15th day of March, 1911, accepted by Bortenlanger at Omaha, Neb., and on the 5th day of April, 1911, such was approved by the Allis-Chalmers Company at Milwaukee, Wis., thus completing the execution of the contract.
So far as is pertinent to the principal question raised in the case, the provisions of the contract between Bortenlanger and the Allis-Chalmers Company were as follows:
The title and right of possession to the machinery herein specified remains in the company until all payments hereunder (including deferred payments and any notes or renewals thereof, if any) shall have been fully paid in cash, and it is agreed that the said machinery shall remain the personal property of the company, whatever may be the mode of attachment to realty or otherwise, until fully paid in cash. Upon failure to make payments, or any of them, as herein specified, the company may retain any and all partial payments which have been made, as liquidated damages, and shall be entitled to take immediate possession of said property, and be free to enter the premises where said machinery may be located, and to remove the same as its property, without prejudice to any further claims on account of damages which the company may suffer from any cause.
This contract was filed for record May 17, 1911, in the office of the county recorder of Cass county, Iowa in which county is the city of Atlantic, which was before any part of the machinery claimed had been furnished; but, as both of the parties were nonresidents, such did not amount to constructive notice, were such sufficient. Code, section 2906. Four estimates were made of the work done by Bortenlanger under his contract with the city, and payments were made upon them in accordance with the provisions of the contract. Included in the estimates upon which payments were made were a considerable portion, but not all, of the machinery and equipment furnished by the Allis-Chalmers Company, but that which was not in the estimate was delivered and awaiting installation. No part of the money received by Bortenlanger was paid to the Allis-Chalmers Company. On the 9th day of September, 1911, by formal written notice to the mayor and city council of Atlantic, Bortenlanger abandoned the contract with the city, and thereafter the city caused the work to be completed.
It is claimed, and the evidence tends to support the fact, that while no actual notice of the reserved title in Allis-Chalmers Company was served on the mayor, or members of the city council, that notice was acquired by certain members of the council. It also is claimed that the engineer who prepared the original estimates for the city had notice of such claim, and that his relation to the city and to the work was such as to charge the city with notice. It appears, and the evidence tends to show, that the machinery and appliances furnished by the Allis-Chalmers Company were so erected and attached to the real estate owned by the city as to be a permanent and fixed improvement thereto, and a part of the real estate. It further appears by concession of counsel, which, however, was not in the presence of the jury, but to the court, that the appellee knew, before furnishing it, and when contracting with Bortenlanger, that it was intended to be so used.
III. Many errors are assigned. Some relate to instructions given the failure to instruct upon questions directly raised by the pleadings, and rulings upon the admissibility of evidence. Many of them depend upon the determination of the law as to the ultimate right of recovery under conditions...
Get this document and AI-powered insights with a free trial of vLex and Vincent AI
Get Started for FreeStart Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial of vLex and Vincent AI, Your Precision-Engineered Legal Assistant
-
Access comprehensive legal content with no limitations across vLex's unparalleled global legal database
-
Build stronger arguments with verified citations and CERT citator that tracks case history and precedential strength
-
Transform your legal research from hours to minutes with Vincent AI's intelligent search and analysis capabilities
-
Elevate your practice by focusing your expertise where it matters most while Vincent handles the heavy lifting
Start Your Free Trial
-
Allis-Chalmers Co. v. City of Atlantic
... ... 346ALLIS-CHALMERS CO.v.CITY OF ATLANTIC.Supreme Court of Iowa.Dec. 13, 1913 ... Appeal from District Court, Cass County; E. B. Woodruff, Judge. Action at law to recover for alleged conversion of electrical machinery and fixtures. From a verdict ... ...