Allis-Chalmers Corp. v. Philadelphia Elec. Co.

Decision Date10 July 1975
Docket NumberALLIS-CHALMERS,No. 74-1936,74-1936
Citation521 F.2d 360,32 A.L.R.Fed. 751
PartiesCORPORATION, Appellee, v. PHILADELPHIA ELECTRIC COMPANY, Appellant, v.CORPORATION, Defendant on Counterclaim, v. WESTINGHOUSE ELECTRIC CORPORATION, Third-Party Defendant.
CourtU.S. Court of Appeals — Third Circuit

William T. Coleman, Jr., Richard L. Bazelon, Gary R. Leadbetter, Philadelphia, Pa., Dilworth, Paxson, Kalish, Levy & Coleman, Philadelphia, Pa., for appellant.

Philip M. Hammett, James D. Crawford, Ralph G. Wellington, Philadelphia, Pa., Schnader, Harrison, Segal & Lewis, Philadelphia, Pa., for appellee.

Before ALDISERT, GIBBONS and GARTH, Circuit Judges.

OPINION OF THE COURT

GARTH, Circuit Judge.

In this diversity case the district court: (1) granted summary judgment on the plaintiff's complaint before adjudicating the defendant's pending counterclaim; and (2) certified that judgment as final under Fed.R.Civ.P. 54(b). This appeal challenges the district court's grant of summary judgment, its 54(b) certification, and its refusal to stay enforcement of the judgment. We dismiss the appeal and hold that the certification of the district court's grant of summary judgment as final under Rule 54(b) of the Federal Rules of Civil Procedure must be vacated because of the failure of the court to articulate reasons for the certification. 1

I.

The plaintiff, Allis-Chalmers Corporation (hereinafter "AC"), having sold eight transformers to the defendant, Philadelphia Electric Corporation (hereinafter "PECO"), and having received payment for only five, commenced this action to compel payment for the remaining three transformers and for the cost of certain repairs made by AC to PECO's equipment. PECO's answer admitted the amounts claimed by AC 2 but asserted as a set-off and counterclaim unrelated claims which, if established, would exceed in amount the sums claimed by AC. 3

After issue had thus been joined, the plaintiff moved ". . . pursuant to Rule 56 and 54(b) of the Federal Rules of Civil Procedure, for summary judgment against defendant. . . ." AC accompanied its motion with affidavits establishing that it was due $497,742.70. As indicated Supra note 2, PECO filed no affidavit disputing this claim but rather argued that its set-off and counterclaim barred the entry of summary judgment in favor of AC. The district court held that, since PECO's counterclaim was factually unrelated to the plaintiff's cause of action and since there were no genuinely disputed issues of material fact concerning plaintiff's claim, ". . . the entry of summary judgment on plaintiff's claim is not only proper but is required under Federal Rule 56. . . ." Therefore, on July 19, 1974, the district court entered an order granting summary judgment for plaintiff. The order recites in relevant part:

". . . The Court, finding that no just cause exists for delaying the entry of this judgment, hereby directs that such judgment be entered pursuant to Rule 54(b) of the Federal Rules of Civil Procedure, in the amount of four hundred ninety seven thousand seven hundred forty-two dollars and seventy cents ($497,742.70) plus interest and costs."

This appeal requires us in the first instance to consider the propriety of the district court's 54(b) certification. Although both AC and PECO have focused on the summary judgment disposition as the central issue on this appeal, we cannot reach that issue unless our jurisdiction has been properly invoked by an appealable order. This Court obtains jurisdiction only when an appeal is taken from a final order (28 U.S.C. § 1291) or from an appealable interlocutory order (28 U.S.C. § 1292). As the Supreme Court stated in Sears, Roebuck & Co. v. Mackey, 351 U.S. 427, 437-38, 76 S.Ct. 895, 900-01, 100 L.Ed. 1297 (1956):

". . . The District Court Cannot, in the exercise of its discretion, treat as 'final' that which is not 'final' within the meaning of § 1291. But the District Court May, by the exercise of its discretion in the interest of sound judicial administration, release for appeal final decisions upon one or more, but less than all, claims in multiple claims actions. . . .

Rule 54(b) . . . scrupulously recognizes the statutory requirement of a 'final decision' under § 1291 as a basic requirement for an appeal to the Court of Appeals. . . ."

Hence, our jurisdiction depends upon whether the district court properly granted 54(b) certification. If that court abused its discretion in certifying the summary judgment as final, we are without jurisdiction to entertain this appeal. See B. B. Adams General Contractors, Inc. v. Department of Housing and Urban Development, 501 F.2d 176 (5th Cir. 1974). Since we cannot consider the merits of a non-final order, we turn first to the threshold question of the propriety of the 54(b) certification.

II.

Fed.R.Civ.P. 54(b) 4 is designed to facilitate the entry of judgment on one or more claims, or as to one or more parties, in a multi-claim/multi-party action. The rationale for its adoption was stated by the Supreme Court in Sears, Roebuck & Co. v. Mackey, supra 351 U.S. at 432, 76 S.Ct. at 898, as follows:

"With the Federal Rules of Civil Procedure, there came an increased opportunity for the liberal joinder of claims in multiple claims actions. This, in turn, demonstrated a need for relaxing the restrictions upon what should be treated as a judicial unit for purposes of appellate jurisdiction. Sound judicial administration did not require relaxation of the standard of finality in the disposition of the individual adjudicated claims for the purpose of their appealability. It did, however, demonstrate that, at least in multiple claims actions, some final decisions, on less than all of the claims, should be appealable without waiting for a final decision on All of the claims . . .."

The rule attempts to strike a balance between the undesirability of piecemeal appeals and the need for making review available at a time that best serves the needs of the parties. Aetna Insurance Co. v. Newton, 398 F.2d 729, 734 (3d Cir. 1968); RePass v. Vreeland, 357 F.2d 801, 804 (3d Cir. 1966); Panichella v. Pennsylvania Railroad Co., 252 F.2d 452, 454 (3d Cir. 1958); See Wright & Miller, Federal Practice and Procedure: Civil § 2654 (1973). ". . . (T)he District Court is used as a 'dispatcher.' It is permitted to determine, in the first instance, the appropriate Time when each 'final decision' upon 'one or more but less than all' of the claims in a multiple claims action is ready for appeal. . . ." Mackey, supra 351 U.S. at 435, 76 S.Ct. at 899. In Panichella, supra at 455, we previously addressed the proper exercise of the district court's discretion with respect to 54(b) certification. We said:

". . . ordinarily an application for a 54(b) order requires the trial judge to exercise considered discretion, weighing the overall policy against piecemeal appeals against whatever exigencies the case at hand may present. Indeed, the draftsmen of this Rule have made explicit their thought that it would serve only to authorize 'the exercise of a discretionary power to afford a remedy in the infrequent harsh case * * *.' 28 U.S.C.A., Federal Rules of Civil Procedure, 118-119 note. It follows that 54(b) orders should not be entered routinely or as a courtesy or accommodation to counsel. The power which this Rule confers upon the trial judge should be used only 'in the infrequent harsh case' as an instrument for the improved administration of justice and the more satisfactory disposition of litigation in the light of the public policy indicated by statute and rule. See 6 Moore, Federal Practice, 1953, 264-65."

A proper exercise of discretion under Rule 54(b) requires the district court to do more than just recite the 54(b) formula of "no just reason for delay." The court should clearly articulate the reasons and factors underlying its decision to grant 54(b) certification. 5 ". . . It is essential . . . that a reviewing court have some basis for distinguishing between well-reasoned conclusions arrived at after a comprehensive consideration of all relevant factors, and mere boiler-plate approval phrased in appropriate language but unsupported by evaluation of the facts or analysis of the law. . . ." Protective Committee v. Anderson, 390 U.S. 414, 434, 88 S.Ct. 1157, 1168, 20 L.Ed.2d 1 (1968) (compromise of claims in bankruptcy). In the same vein, the Second Circuit in Gumer v. Shearson, Hammill & Co., Inc.,516 F.2d 283 (2d Cir. 1974) said:

"We suggest to the district courts that in the future it would be helpful to us in reviewing the exercise of discretion in granting a Rule 54(b) certificate if the court, rather than incorporating in the certificate (footnote omitted) the conclusory language of Rule 54(b), would make a brief reasoned statement in support of its determination that, 'there is no just reason for delay' and its express direction for 'the entry of a final judgment as to one or more but fewer than all of the claims or parties' where the justification for the certificate is not apparent. . . ."

Accord, Schwartz v. Compagnie General Transatlantique, 405 F.2d 270, 275 (2d Cir. 1968) (". . . the trial court (should) marshall the competing considerations and state the ones considered to be most important."). See Wright & Miller, Federal Practice and Procedure: Civil § 2659 (1973).

We endorse the suggestion contained in Gumer as a most desirable practice. Because it will convey to litigants the reasons for the court's decision and will afford the appellate court a meaningful basis for review, we incorporate that practice as a requirement for all Rule 54(b) certifications.

In reviewing 54(b) certifications, other courts have considered the following factors, 6 Inter alia : (1) the relationship between the adjudicated and unadjudicated claims; 7 (2) the possibility that the need for review might or might not be mooted by future developments in the...

To continue reading

Request your trial
343 cases
  • Local P-171, Amalgamated Meat Cutters and Butcher Workmen of North America v. Thompson Farms Co.
    • United States
    • U.S. Court of Appeals — Seventh Circuit
    • February 26, 1981
    ...review. See Bank of Lincolnwood v. Federal Leasing, Inc., 622 F.2d 944, 949 (7 Cir. 1980), quoting Allis-Chalmers Corp. v. Philadelphia Electric Co., 521 F.2d 360, 364 (3 Cir. 1975). Both of these functions were served by the § 1292(b) certification here. It unequivocally manifests the dist......
  • Gardner v. Westinghouse Broadcasting Co.
    • United States
    • U.S. Court of Appeals — Third Circuit
    • March 28, 1977
    ...erected a major, useless, and frequently disregarded impediment to the utilization of Rule 54(b). See Allis Chalmers Corp. v. Philadelphia Electric Co., 521 F.2d 360 (3d Cir. 1975). Thus, each of the alternative safeguards upon which we premised the Hackett holding has now been eliminated o......
  • National Gypsum Co. v. Continental Brands Corp., Civ. A. No. 93-12027-NG
    • United States
    • U.S. District Court — District of Massachusetts
    • July 14, 1995
    ...is no just reason for delay." The First Circuit has cited with approval the list of factors set forth in Allis-Chalmers Corp. v. Philadelphia Electric Co., 521 F.2d 360 (3rd Cir. 1975), as a helpful guide in making this determination. See Spiegel v. Trustees of Tufts College, 843 F.2d 38, 4......
  • In re Diet Drugs Products Liability
    • United States
    • U.S. Court of Appeals — Third Circuit
    • March 10, 2005
    ...in order to allow immediate appeal. Weiss v. York Hosp., 745 F.2d 786, 802 (3d Cir.1984); see also Allis-Chalmers Corp. v. Philadelphia Electric Co., 521 F.2d 360, 363 (3d Cir.1975) (explaining that Rule 54(b) "attempts to strike a balance between the undesirability of piecemeal appeals and......
  • Request a trial to view additional results
1 books & journal articles

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT