American Bonding Co. of Baltimore v. United States
Decision Date | 16 June 1916 |
Docket Number | 2077. |
Parties | AMERICAN BONDING CO. OF BALTIMORE et al. v. UNITED STATES, to Use of FRANCINI et al. |
Court | U.S. Court of Appeals — Third Circuit |
F. B Bracken, of Philadelphia, Pa. (Welles & Torrey, of Scranton Pa., of counsel), for plaintiffs in error.
R Stuart Smith, of Philadelphia, Pa. (O'Brien & Kelly, of Scranton, Pa., and Morgan, Lewis & Bockius, of Philadelphia Pa., of counsel), for defendants in error.
Before BUFFINGTON, McPHERSON, and WOOLLEY, Circuit Judges.
In October, 1910, Mark P. Wells contracted with the United States to build a post office at York, Pa., and gave the bond required by the act of 1905, conditioned, inter alia, to pay all persons supplying labor or material. The building was finished and accepted, a settlement was made with Wells, and the balance due him was paid over. But, as several subcontractors were still unpaid, one of them brought the present suit against Wells and his surety on February 4, 1914, and others intervened soon afterward. This writ is taken by the surety only.
The first question to be decided is whether the suit was premature; i.e., whether it was brought before the six months had expired within the United States alone has the right to sue. U.S. v. McCord, 233 U.S. 157, 34 Sup.Ct. 550, 58 L.Ed. 893; Stitzer v. U.S. (C.C.A. 3d) 182 F. 513, 105 C.C.A. 51. On this point, the facts are as follows:
On August 2, 1913, the Supervising Architect of the Treasury addressed a letter to the Secretary recommending a settlement with Wells upon certain terms, and this settlement, slightly changed, was approved by the Assistant Secretary, who appended the following memorandum without date:
The undisputed evidence shows that this memorandum was not signed before August 9, and that the balance thus found due was not paid before August 16. Now, if this were all, it might be argued with some force that August 9 was the earliest date assignable for the 'settlement,' and therefore that the action was brought several days too soon.
But other evidence leads to the opposite conclusion. On the whole case it appears that (since September 12, 1912, at least) the Treasury 'treats as the date of final settlement mentioned in said acts' (of 1894 and 1905) 'the date on which the Department approves the basis of settlement under such contract recommended by the Supervising Architect, and orders payment accordingly. ' This language is contained in Department Circular No. 45, bearing the date just mentioned, and this circular was sent to some, perhaps to all, of the subcontractors. Moreover, it was proved that, when several of these contractors asked the Department when settlement had been made with Wells, the Treasury replied, in December, 1913, or January, 1914, that 'final settlement under the contract referred to above was authorized August 2, 1913. ' It was also shown that the following official indorsements appeared upon the contract: 'Final payment authorized Aug. 2/13,' and 'Guarantee expires 8/2/15.' The latter indorsement refers to a clause in the specifications guaranteeing certain work for a period of two years. No suit has been brought by the government. Clearly, therefore, the Department adopted August 2, 1913, as the date of final settlement, and so informed the subcontractors-- among them, the firm by whom the suit was begun on February 4.
At the time of the trial the courts were not in agreement in their answers to the question, What constitutes a 'settlement' between a contractor and the government? But since then the question has been answered definitely in Illinois Surety Company v. United States, for use of Peeler (decided Feb. 21, 1916) 240 U.S. 214, 36 Sup.Ct. 321, 60 L.Ed. 609. As that case has not yet been regularly reported, we quote from it freely. There the suit was brought on March 4, 1913. At the trial it appeared that on August 21, 1912, the Treasury Department had stated and determined what balance was due the contractor, although the money had not been paid until September 11. The surety contended that the suit was premature, because six months had not elapsed since the date of payment. But the Supreme Court held that August 21 was to be taken as the date of final settlement, and in the course of the discussion used the following language:
To continue reading
Request your trial-
Ford Motor Credit Co. v. Lototsky
...Co., 152 F.2d 875, 880 (3rd Cir.), cert. denied 327 U.S. 789, 66 S.Ct. 810, 90 L.Ed. 1015 (1946); American Bonding Co. of Balt. v. United States, 233 F. 364, 369, 147 C.C.A. 300 (3rd Cir.), error dismissed, 242 U.S. 661, 37 S.Ct. 113, 61 L.Ed. 550 (1916); Monongahela St. Ry. Co. v. Philadel......
-
United States Casualty Co. v. District of Columbia
...Surety Co. v. United States to the use of Peeler, 1916, 240 U.S. 214, 36 S.Ct. 321, 60 L.Ed. 609; American Bonding Co. v. United States, to Use of Francini, 3 Cir., 1916, 233 F. 364; Pederson v. United States, for the Use of Washington Iron Works, 9 Cir., 1918, 253 F. 622; United States, to......
-
Feutz v. Massachusetts Bonding & Ins. Co., 5873.
...614, 61 L.Ed. 1206; National Surety Co. v. Lincoln County 9 Cir., 238 F. 705, 151 C.C.A. 555; American Bonding Co. v. United States to Use of Francini 3 Cir., 233 F. 364, 147 C.C.A. 300; note in 12 A.L.R. 382, and cases When a part of Feutz' contract with Murphy was assigned, to the extent ......
-
Golden West Construction Company v. United States, 6780.
...without the consent of the surety, results in prejudice to the surety's interest. See American Bonding Co. of Baltimore et al. v. United States to Use of Francini et al. (3 C.A.), 233 F. 364; Piel Construction Co. v. Commonwealth of Pennsylvania to Use of Hendricks (3 C.A.), 35 F.2d 265; Na......