Anderson-Ross Floors, Inc. v. Scherrer Const. Co., Inc.
Decision Date | 01 August 1978 |
Docket Number | No. 77-106,ANDERSON-ROSS,77-106 |
Citation | 379 N.E.2d 786,19 Ill.Dec. 914,62 Ill.App.3d 713 |
Court | United States Appellate Court of Illinois |
Parties | , 19 Ill.Dec. 914 FLOORS, INC., Plaintiff-Appellee, v. SCHERRER CONSTRUCTION CO., INC., Orput-Orput & Associates, Inc., and Marshall S. Stevens, Defendants-Appellants. |
Conzelman, Schultz & Snarski, Waukegan, for defendants-appellants.
Hall, Meyer, Fisher, Holmberg & Snook, Waukegan, Jenner & Block, Chicago, for plaintiff-appellee.
Anderson-Ross, Inc., as a subcontractor filed suit against the general contractor, Scherrer Construction Co., Inc., the architectural firm of Orput-Orput, Inc., and the construction manager for the architect Marshall S. Stevens, to recover payment for the installation of a gymnasium floor in a grade school. Following a bench trial judgment was entered in favor of plaintiff and against the general contractor for $5180 and costs and Scherrer appeals. No judgment was entered against the other defendants.
In issue is whether the plaintiff performed in accordance with his agreement "to the satisfaction of the architect" and whether recovery may be had when no architect's certificate has been issued and the school board owner has refused to accept the work.
The record of the trial is before us on a stipulated report of proceedings, no actual transcript having been prepared. Robert E. Ross, the president of the plaintiff company, testified that Stevens was present as the representative of the architect during the installation of the flooring, had an opportunity to observe the work but made no adverse comment. He said that his corporation had been installing floors for fifteen years during which time between three hundred and four hundred of such floors had been laid. He explained the "Robbins lock-type floor system" which was the method he used. In February or March of 1971 he had the following conversation with Marshall Stevens:
"Q(by ROSS): What's the matter, MARSHALL?
A(by MARSHALL STEVENS): There are complaints of spaces between the boards.
Q(by ROSS): Sure there are a few but, you are bound to get them.
A(by MARSHALL STEVENS): Yes, BOB, it looks all right to me."
On cross-examination the witness testified that he did not return to the site after March of 1971 although the Scherrer Construction Company requested meetings.
Marshall Stevens testified as an adverse witness to his employment as a construction manager and to the fact that he was not a registered architect. He said he had a conversation with Ross at the site in the early part of 1971 but he could not remember whether he had told Ross that in his opinion the floor was typical and adequate and he would recommend payment. He identified a letter which he wrote to the general contractor on March 19, 1971, which states in part:
(Plaintiff's Exhibit 3)
Stevens also identified a letter which he wrote to the school board on January 25, 1971, which included the following statement:
Stevens also testified that it was possible to have tight joints at all times. He further testified that he had observed the spaces open and close over a period of time and also that the last time he visited the gymnasium it was being put to its intended use. He said that he had advised the school board that the spaces would not adversely affect its use and that he knew of no repairs having been made to the floor.
Professor Henry L. Mikolajczyk, testified on behalf of the plaintiff, that he had been teaching for thirty-one years, and that for the past twelve years he was a professor at the University of Illinois in the matter of the technical nature of materials; that he was a registered architect in engineering in charge of design of all Chicago facilities for the University of Illinois; that he did research in the area of materials and building construction materials and was a consultant architect, a member of the Illinois Society of Architects.
Professor Mikolajczyk testified that he had examined the second grade maple used in the floor construction and its moisture content. The stipulated substance of his testimony included the following:
The subcontract was also placed in evidence (Plaintiff's Exhibit 1) showing a contract price of $10,500. As pertinent the subcontract included the following:
Neither the contract between Scherrer and the ...
To continue reading
Request your trial-
Corbetta Const. Co. of Illinois, Inc. v. Lake County Public Bldg. Commission
...a contractor by claiming he or the architect was not "satisfied" with it (see Anderson-Ross Floors, Inc. v. Scherrer Construction Co. (2d Dist., filed August 1, 1978), Ill.App., 19 Ill.Dec. 914, 379 N.E.2d 786), it could well have a misleading effect here where the issue was the owner's rig......