Arctic Corner, Inc. v. U.S.

Citation845 F.2d 999
Decision Date02 May 1988
Docket NumberNos. 87-1617,87-1618,s. 87-1617
Parties34 Cont.Cas.Fed. (CCH) 75,472 ARCTIC CORNER, INC., Appellant, v. The UNITED STATES, Appellee.
CourtU.S. Court of Appeals — Federal Circuit

Frank R. Ciesla, Giordano, Halleran & Ciesla, Middletown, N.J., argued for appellant.

Genevieve Holm, Commercial Litigation Branch, Dept. of Justice, Washington, D.C., argued for appellee. With her on the brief were Richard K. Willard, Asst. Atty. Gen., David M. Cohen, Director and Mary Mitchelson, Asst. Director. Also on the brief was Gill E. Bass, U.S. Army Corps of Engineers, North Atlantic Div., of counsel.

Before MARKEY, Chief Judge, ARCHER and MAYER, Circuit Judges.

MARKEY, Chief Judge.

ORDER

Arctic Corner, Inc., (Arctic) filed what it called an "appeal" from two "decisions" of the Armed Services Board of Contract Appeals (board): ASBCA Nos. 33251 and 33509, 87-2 BCA p 19,859 (1987), aff'd on reconsid., 13 July 1987; ASBCA Nos. 34216 and 34340, 87-3 BCA p 20,139 (1987), purporting to grant summary judgment for the United States on Arctic's claims in connection with three contracts. We will dismiss the appeal.

The facts are set forth in the opinions of the board and will be only summarized here.

After partial performance of the contracts, Arctic defaulted and was terminated. It appealed each termination, but settled those cases. See 87-2 BCA at 100,468-69.

After Arctic's default, Indemnity Insurance Company of North America (surety) completed the work. Arctic sent the government an invoice for work completed, the amount being the contract price plus interest and minus certain items. The government refused payment and Arctic appealed to the board. Before the board, Arctic admitted its claim was "subject to an adjustment for monies paid the surety for completing the contract."

The board granted summary judgment because it viewed Arctic's claims as barred by the above-described settlement of the appealed terminations. The board also said Arctic "is essentially seeking to recover for work performed by the surety after the contract was terminated for default."

The parties vigorously argue the effect of the settlement. This court lacks jurisdiction over the appeal, however, and will not therefore discuss those arguments.

Before us, Arctic says it "is seeking to recover the Contract balances remaining after payment to the Surety," and admits that it has no right to recover for work it performed before it was terminated for default, "except to the extent that once a Surety is reimbursed for its completion costs, the remaining balance must be paid to the original contractor." It is undisputed that the surety has not yet submitted its final payment request. 1

An actual case or controversy is a prerequisite to justiciability of Arctic's appeal, U.S. Const. art. III, Sec. 2; Babbitt v. United Farm Workers Nat'l Union, 442 U.S. 289, 297, 99 S.Ct. 2301, 2308, 60 L.Ed.2d 895 (1979) (threshold question whether appellees alleged case or controversy within meaning of Art. III). A court may and should raise the question of its jurisdiction sua sponte at any time it appears in doubt. Duke City Lumber Co. v. Butz, 539 F.2d 220, 221 n. 2 (D.C.Cir.1976) (citing Mansfield, Coldwater & Lake Michigan Ry. v. Swan, 111 U.S. 379, 384, 4 S.Ct. 510, 512-13, 28 L.Ed. 462 (1884)). At the heart of the "case or controversy" requirement is the prohibition against advisory opinions. See Babbitt, 442 U.S. at 305, 99 S.Ct. at 2312; C. Wright, A. Miller, & E. Cooper, Federal Practice & Procedure: Jurisdiction 2d Sec. 3532.1 (1984).

Arctic can have no claim at all unless and until after two events occur: (1) the surety must submit a bill of costs; and (2) that bill must be for less than the unpaid contract balance. Jurisdiction would exist in this court only after two further events occur: (3) submission and denial of Arctic's claim; (4) board affirmance of that...

To continue reading

Request your trial
76 cases
  • Wood-Ivey Systems Corp. v. U.S.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • 9 Septiembre 1993
    ...may be considered at any time, even for the first time on appeal, and can be raised sua sponte by the court. Arctic Corner, Inc. v. United States, 845 F.2d 999, 1000 (Fed.Cir.1988). Further, parties cannot overcome the lack of jurisdiction by stipulation, waiver or estoppel. California v. L......
  • United States v. Gateway Import Mgmt., Inc.
    • United States
    • U.S. Court of International Trade
    • 3 Julio 2018
    ..."court may and should raise the question of its jurisdiction sua sponte at any time it appears in doubt." Arctic Corner, Inc. v. United States, 845 F.2d 999, 1000 (Fed. Cir. 1988) (citations omitted). The Court may dismiss a case for lack of subject-matter jurisdiction on its own motion bec......
  • Amsted Rail Co. v. U.S. Int'l Trade Comm'n
    • United States
    • U.S. Court of International Trade
    • 15 Noviembre 2022
    ..."court may and should raise the question of its jurisdiction sua sponte at any time it appears in doubt." Arctic Corner, Inc. v. United States, 845 F.2d 999, 1000 (Fed. Cir. 1988). The court must evaluate and "enforce the limits of its jurisdiction" in all cases, especially those that invok......
  • Jackson v. United States
    • United States
    • U.S. Claims Court
    • 19 Septiembre 2022
    ... ... Chairman and CEO of SmartCopper Broadband, Inc., a new ... company launched for the purpose of re-introducing ... actions brought before it. Arctic Corner, Inc. v. United ... States , 845 F.2d 999, 1000 (Fed. Cir ... ...
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT