Ark. Pub. Serv. Comm'n v. Fed. Energy Regulatory Comm'n, 16-1305

Decision Date01 June 2018
Docket NumberNo. 16-1305,16-1305
Citation891 F.3d 377
Parties ARKANSAS PUBLIC SERVICE COMMISSION, Petitioner v. FEDERAL ENERGY REGULATORY COMMISSION, Respondent Entergy Services, Inc., et al., Intervenors
CourtU.S. Court of Appeals — District of Columbia Circuit

Dennis Lane argued the cause for petitioner. With him on the briefs were Glen L. Ortman, John E. McCaffrey, Washington, DC, and Randolph Hightower. Marie Denyse Zosa entered an appearance.

Gregory W. Camet, New Orleans, LA, Mark Strain, and Marnie A. McCormick, Austin, TX, were on the briefs for intervenor Entergy Services, Inc. in support of petitioner. Megan E. Vetula entered an appearance.

Lona T. Perry, Deputy Solicitor, Federal Energy Regulatory Commission, argued the cause for respondent. With her on the brief were David L. Morenoff, General Counsel, and Robert H. Solomon, Solicitor. Anand Viswanathan, Attorney, entered an appearance.

David E. Pomper, Washington, DC, argued the cause for intervenors Louisiana Public Service Commission, et al. With him on the brief were Stephen Charles Pearson, Michael R. Fontham, Noel J. Darce, Dana Shelton, Justin A. Swaim, Clinton Andrew Vince, Presley Randolph Reed Jr., Jennifer Anne Morrissey, and Chad James Reynolds. Paul L. Zimmering, New Orleans, LA, entered an appearance.

Before: Henderson and Wilkins, Circuit Judges, and Sentelle, Senior Circuit Judge.

Sentelle, Senior Circuit Judge

The Arkansas Public Service Commission petitions for review of a Federal Energy Regulatory Commission ("FERC") final order. Entergy Servs., Inc. , 154 FERC ¶ 61,173 (Mar. 4, 2016), reh’g denied in part and granted in part , 156 FERC ¶ 61,112 (Aug. 16, 2016). In the order under review, FERC held that an operating company withdrawing from a multi-state energy system must continue to share the proceeds of a pre-departure settlement with the other member companies. The Arkansas Public Service Commission (the "Arkansas Commission"), acting on behalf of Arkansas energy consumers, contends that FERC's order to share the settlement benefits and its method of allocating the benefits of the settlement was unlawful, arbitrary, capricious, and unsupported by substantial evidence. Because we conclude that FERC had a lawful basis to order the sharing of the benefits of the settlement and was reasoned in its allocation methodology, we deny the petition for review.

I. Background
A. Factual History

Beginning in 1951, six companies in Arkansas, Louisiana, Mississippi, and Texas (collectively, the "Operating Companies") entered into an arrangement to share the costs and benefits of power generation and transmission. To that end, they formed the Entergy Corporation, a publicly held and traded utility holding company. The Entergy Corporation is the corporate parent of intervenor Entergy Services, Inc. ("Entergy Services"). The Operating Companies memorialized their arrangement in the Entergy System Agreement ("System Agreement"), a FERC-approved rate plan that governs the multi-state system's generation and transmissions facilities operated as a single system (the "Entergy System") and administered by Entergy Services. Over the years, Entergy Services supplemented the System Agreement with seven service schedules, MSS-1 through MSS-7, which updated the cost-sharing and energy capacity plan. The System Agreement "has been a feature of many cases before this Court." Council of New Orleans v. FERC , 692 F.3d 172, 174 (D.C. Cir. 2012) ; see, e.g. , Arkansas Pub. Serv. Comm’n v. FERC , 712 Fed.Appx. 3, 4 (D.C. Cir. 2018) ; Louisiana Pub. Serv. Comm’n v. FERC , 522 F.3d 378, 383 (D.C. Cir. 2008) ; Louisiana Pub. Serv. Comm’n v. FERC , 174 F.3d 218, 220 (D.C. Cir. 1999).

The System Agreement provided for the possibility of withdrawal by an Operating Company and required an eight-year notice of intent to withdraw by any company preparing to do so. On December 19, 2005, Operating Company Entergy Arkansas gave such a notice, announcing its intention to withdraw on December 18, 2013. Two years later, another Operating Company, Entergy Mississippi, gave a similar notice. The current controversy over the effects of the withdrawal concerns a settlement entered with coal transporter Union Pacific in state court litigation before the withdrawal of the two Operating Companies.

In April 2008, Entergy Arkansas, Entergy Services, and other parties settled Arkansas state court litigation against Union Pacific (the "Union Pacific Settlement"). The settlement, as relevant to the present petition for review, locked in a below-market rate for the rail delivery of coal by extending an Entergy Arkansas contract with Union Pacific to the period between July 1, 2012 and June 30, 2015. Entergy Arkansas remained in the System Agreement until partway through this period.

Under the System Agreement, the Operating Companies purchase excess energy from other Operating Companies at-cost. The service schedules set out the price for energy purchases. That price incorporates the cost of coal transportation as one component. Entergy Arkansas was still participating in the System Agreement when Union Pacific failed to make the coal deliveries in the conduct underlying the settlement. Therefore, Entergy Arkansas passed a portion of the increased coal costs to the other Operating Companies under service schedule MSS-3. Likewise, prior to Entergy Arkansas's departure from the System Agreement, Entergy Arkansas also shared its beneficial coal transportation costs under the Union Pacific Settlement with the other Operating Companies. Additionally, some of the Operating Companies had other mechanisms outside of the System Agreement to realize some of the benefits of Entergy Arkansas's reduced coal transportation costs, such as shared ownership of the two affected plants and separate power purchasing agreements. However, the Union Pacific Settlement did not address Entergy Arkansas's impending withdrawal from the System Agreement.

B. Procedural History

On November 19, 2009, FERC accepted Entergy Arkansas and Entergy Mississippi's notices of withdrawal from the Entergy System. Entergy Servs., Inc. , 129 FERC ¶ 61,143 (Nov. 19, 2009) ("Withdrawal Order"), reh’g denied , 134 FERC ¶ 61,075 (Feb. 1, 2011) ("Withdrawal Rehearing Order") (collectively, "Withdrawal Proceedings"). In the Withdrawal Proceedings, FERC found that the System Agreement "contain[ed] no provisions requiring withdrawing Operating Companies to pay a fee or otherwise compensate other remaining Operating Companies prior to withdrawing." Withdrawal Order P. 60. Accordingly, FERC held that Entergy Arkansas and Entergy Mississippi should not have to pay any exit fees to the other Operating Companies upon their departure from the Entergy System.

Intervenor Louisiana Public Service Commission (the "Louisiana Commission"), which represents the interests of Louisiana's energy consumers, filed exceptions to the Withdrawal Order, arguing that FERC should allocate the Union Pacific Settlement benefits as part of the Withdrawal Proceedings. FERC responded that the Louisiana Commission's concerns regarding the allocation of the Union Pacific Settlement Benefits were "beyond the scope of this proceeding and are more appropriately raised" in a future proceeding regarding the structure of the post-withdrawal Entergy System. Withdrawal Rehearing Order at n.54. FERC went on to reinforce that it would still review "future operating arrangements" to ensure they were "just and reasonable" in accordance with FERC's statutory obligations under 16 U.S.C. § 824d.

On September 14, 2011, still concerned about the allocation of the Union Pacific Settlement benefits, the Louisiana Commission filed a complaint under section 206 of the Federal Power Act. Louisiana Pub. Serv. Comm’n , 138 FERC ¶ 61,029 (Jan. 19, 2012). Again, FERC reiterated that it was "premature" to consider the allocation of the Union Pacific Settlement benefits and opined that the Louisiana Commission's concerns would be resolved "in the future proceeding regarding the structure of the post-withdrawal Entergy system." Id. at P. 53. Prior to the start of the Withdrawal Proceedings, the Louisiana Commission had also raised the allocation of the Union Pacific Settlement benefits during a 2008 bandwidth proceeding, but it withdrew the issue without prejudice based on the expectation it would be resolved in later proceedings.

On August 14, 2012, this Court affirmed the Withdrawal Proceedings, including FERC's conclusion that the System Agreement does not impose an exit fee or continuing obligation on withdrawing Operating Companies. Council of New Orleans , 692 F.3d at 174-77. We also recognized that FERC "must still review the post-withdrawal arrangements to ensure that they are just, reasonable and not unduly discriminatory." Id . at 177.

In November 2012, under section 205 of the Federal Power Act, Entergy Services filed its proposal for its post-withdrawal successor plan. The successor plan included the necessary revisions to the System Agreement and the formation of a new integrated utility system (the Midcontinent Independent System) comprised of the remaining Operating Companies. The Louisiana Commission again protested the filing. For the fourth time, the Louisiana Commission raised the issue of the Union Pacific Settlement benefits. In response, the Arkansas Commission and Entergy Services challenged FERC's authority to order Entergy Arkansas to share the Union Pacific Settlement benefits because Entergy Arkansas was no longer participating in the System Agreement. FERC established a hearing to address these issues. Entergy Servs., Inc. , 145 FERC ¶ 61,247 (Dec. 18, 2013), reh’g denied , 153 FERC ¶ 61,154 (Nov. 9, 2015).

Following settlement discussions and a hearing, the Administrative Law Judge determined that the Union Pacific Settlement benefits should be allocated among the Operating Companies and adopted an allocation methodology. Entergy Servs., Inc. , 149 FERC ¶ 63,022 (Dec. 12, 2014)...