Arthur N. Olive Co. v. United States
Decision Date | 08 December 1961 |
Docket Number | No. 5881.,5881. |
Citation | 297 F.2d 70 |
Parties | ARTHUR N. OLIVE CO., Inc., et al., Defendants, Appellants, v. UNITED STATES of America, for the use and benefit of Dan C. MARINO, etc., Plaintiff, Appellee. |
Court | U.S. Court of Appeals — First Circuit |
Charles E. Gennert, Boston, Mass., with whom Herbert L. Crimlisk and Withington, Cross, Park & McCann, Boston, Mass., were on brief, for appellants.
Philip D. Epstein, Boston, Mass., for appellee.
Before WOODBURY, Chief Judge, and HARTIGAN and ALDRICH, Circuit Judges.
This is an appeal from a judgment following a jury verdict in the United States District Court for the District of Massachusetts for the use plaintiff, Dan C. Marino (hereinafter called Marino), in an action to recover on a payment bond filed under the Miller Act. 49 Stat. 793, 40 U.S.C.A. § 270a et seq. Marino, a resident of Massachusetts, is engaged in the contracting business.
On June 25, 1958, the appellant, Arthur N. Olive Co., Inc., (hereinafter called Olive), a Massachusetts corporation, contracted with the United States to construct Sewerage System Modifications at three NIKE Battery sites in Massachusetts. Olive furnished a payment bond with the New Amsterdam Casualty Company as surety. On August 7, 1958 Olive subcontracted a portion of his prime contract to Marino for $62,000. Incident to this subcontract, Marino furnished labor and materials valued at some $55,000 to $57,000, leaving a total of $5,000 to $6,000 worth of work unperformed at the time that work was discontinued because of an alleged breach of the contract by Olive.
In addition to the work which he performed incident to the subcontract, Marino at Olive's direction performed "extra" work at the same sites which were the subject of the original agreement. These extras, some but not all of which were contemplated in the initial subcontract, embraced such projects as drilling, blasting, trenching and laying pipe. Testimony of Marino indicated that the value of these extras amounted to approximately $37,000. Marino, in establishing the basis for the extras testified that his charges were fair and reasonable in each instance. He was unable to identify with any notable specificity the precise profit margin on a particular project. However, his testimony indicated that while his minimum profit margin was ten percent, in some instances it rose to as much as thirty-five percent.
Ninety days having elapsed since he performed the last of his work on the NIKE installations, Marino brought this action to recover under the "payment bond" filed pursuant to the Miller Act. Both Olive and New Amsterdam were joined as defendants in this suit. At the time that he initiated this action, Marino had billed Olive $54,000 under the subcontract and had been paid $52,500.
Marino's complaint, invoking the jurisdiction of the district court under the Miller Act, recited the fact that he had agreed with Olive to furnish labor and materials for the Sewerage System Modifications, that such labor and materials were actually furnished and "that by reason of furnishing the aforesaid materials there became due and owing to the use plaintiff, Dan C. Marino, the sum of forty-two thousand one hundred eleven dollars 9/100 ($42,111.09) with interest thereon. * * *"
Following a lengthy trial, the jury returned a verdict for Marino in the sum of $30,633.17 to which interest was added.
The principal questions on this appeal arise from the instructions of the trial judge to the jury on the elements which it might consider in awarding Marino damages. In discussing the question of damages the trial judge charged the jury:
"If you find for the plaintiff you are to assess damages sufficient in amount to compensate the plaintiff for the loss you find he actually sustained; that is, he is to recover the amount you find to be due for any extras which you find he performed at the request of the Olive Company, plus any amount you find still to be due, if you find such, on the basic contract plus the profit, if any, he would have made on the remaining unperformed portion of the contract which was not completed by him, and to determine this last figure you are to take the balance unpaid on the contract and subtract from it what you find to be the cost of completing the unfinished work."
Appellant objected to that portion of the charge which permitted the recovery of profit on unperformed work under the basic contract. It also objected to the language in the charge which would permit a recovery of profit on the "extras" which were supplied by Marino. Appellant argues that by permitting the jury to award profits "on the remaining unperformed portion of the contract which was not completed by him" the trial judge, in effect, permitted Marino to recover damages for a breach of the contract. It urges that recovery of such damages — by a subcontractor situated as Marino — would be manifestly outside the purview of the Miller Act. We agree with appellant's position in this regard.
The Miller Act, like its statutory predecessor, the Heard Act, 28 Stat. 278, was enacted to give those supplying labor and materials for government construction contracts, protection comparable to that furnished by mechanics' and materialmen's liens where private construction is involved. United States v. Harman, 192 F.2d 999 (4 Cir. 1951); see, United States v. Munsey Trust Co., 332 U.S. 234, 241, 67 S.Ct. 1599, 91 L.Ed. 2022 (1947). So far as is relevant here the Miller Act provides: "(a) Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished * * * shall have the right to sue on such payment bond for the * * * balance * * * unpaid at the time of institution of such suit * * *." 40 U.S. C.A. § 270b(a).
The Act is a Congressional recognition of the equity in favor of those whose actual expenditure of work or utilization of material has enhanced the value of the property in question. However, since the statute was enacted to confer rights equivalent to those which would accrue under a lien where private construction is involved and since unrealized...
To continue reading
Request your trial-
UNITED STATES, ETC. v. Guy H. James Construction Co.
...case was decided under the Heard Act, which was the statutory predecessor to the Miller Act. See also Arthur N. Olive Co. v. United States, 297 F.2d 70, 72 (1st Cir. 1961), United States v. MacDonald Construction Co., 281 F.Supp. 1010 (E.D.Mo. As reasoned by the Ninth Circuit Court of Appea......
-
Blakeslee Arpaia Chapman, Inc. v. EI Constructors, Inc.
...recover reasonable value of services and materials for work performed, including profit and overhead); Arthur N. Olive Co. v. United States ex rel. Marino, 297 F.2d 70, 73 (1st Cir. 1961) (subcontractor entitled to recover under Miller Act value of extra work performed, which includes profi......
-
U.S. ex rel. Metric Elec. v. Enviroserve, Inc.
...to that furnished by mechanics' and materialmen's liens where private construction is involved." Arthur N. Olive Co. v. United States ex rel. Marino, 297 F.2d 70, 72 (1st Cir.1961); See also GE Supply v. C & G Enterprises, Inc., 212 F.3d 14, 17 (1st Cir.2000). The Act provides in pertinent ......
-
B. C. Richter Contracting Co. v. Continental Cas. Co.
...to the breach may not be recovered from the surety, even though the principal may be liable. (Arthur N. Olive Co. v. United States for Use and Benefit of Marino, 297 F.2d 70 (1st Cir. 1961); United States for Use and Benefit of Moran Towing Corp. v. Hartford Accident & Indemnity Co., 204 F.......
-
26.6 Payment Issues
...Kirchdorfer, 869 F. Supp. at 396 n.8.[440] Skip Kirchdorfer, 869 F. Supp. at 394; Arthur N. Olive Co. v. United States ex rel. Marino, 297 F.2d 70 (1st Cir. 1961).[441] 635 F.Supp2d 434 (E.D. Va. 2009).[442] Id. at 440.[443] Artistic Stone Crafters, Inc. v. Safeco Ins. Co. of Am., 726 F.Sup......
-
§ 10.5 The Miller Act
...489 F2d 756 (6th Cir 1974); (4) lost profit on an unperformed or delayed contract, Arthur N. Olive Co. v. United States ex rel. Marino, 297 F2d 70, 72 (1st Cir 1961); United States ex rel. Gutman v. P.J. Carlin Constr. Co., 254 F Supp 1001, 1002 (EDNY 1965); and (5) money advanced to the co......
-
Chapter 12 - § 12.3 • PAYMENT BONDS
...Lite-Air Prods., Inc. v. Fid. & Deposit Co., 437 F. Supp. 801, 804 (E.D. Pa. 1977).[54] Arthur N. Olive Co. v. U.S. ex rel. Marino, 297 F.2d 70 (1st Cir. 1961); L.P. Friestedt Co. v. U.S. Fireproofing Co., 125 F.2d 1010 (10th Cir. 1942); U.S. ex rel. Mobile Premix Concrete, Inc., 515 F. Sup......