Aspen Consulting, LLC v. Sec'y of the Army

Citation25 F.4th 1012
Decision Date09 February 2022
Docket Number2021-1381
Parties ASPEN CONSULTING, LLC, Appellant v. SECRETARY OF the ARMY, Appellee
CourtUnited States Courts of Appeals. United States Court of Appeals for the Federal Circuit

Ian Cronogue, Baker, Cronogue, Tolle & Werfel, LLP, McLean, VA, argued for appellant. Also represented by Gerald Howard Werfel.

Corinne Anne Niosi, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for appellee. Also represented by Brian M. Boynton, Martin F. Hockey, Jr., Patricia M. McCarthy ; Allen Scott Black, United States Army Corps of Engineers, Little Rock, AR.

Before Moore, Chief Judge, Dyk and Cunningham, Circuit Judges.

Dyk, Circuit Judge.

Aspen Consulting, LLC, ("Aspen") appeals a final decision of the Armed Services Board of Contract Appeals (the "Board"). The Board denied Aspen's appeal, which sought compensation for the U.S. Army Corps of Engineers' (the "government's") failure to deposit contractually owed payments in the account designated in the contract. We reverse the Board's finding that the government did not breach the contract and remand for further proceedings consistent with this opinion. On remand, the Board must determine whether the government has established an affirmative defense of payment.

BACKGROUND

Aspen is based in San Antonio, Texas. In 2013, Aspen received a government contract to outfit United States military health and dental clinics in Germany ("the contract" or "the Vilseck project"). The contract contains a payment clause, incorporating Federal Acquisition Regulation ("FAR") 52.232-33 (2003), which states:

The Government shall make payment to the Contractor using the [Electronic Funds Transfer] EFT information contained in the Central Contractor Registration (CCR) database. In the event that the EFT information changes, the Contractor shall be responsible for providing the updated information to the CCR database.

J.A. 233. FAR 52.232-33 was promulgated in 1999 to facilitate an efficient shift to mandatory federal EFT payments required by the Debt Collection Improvement Act of 1996, and was amended in 2003 to require that contractors "provide certain business information, including their ... (EFT) information only once into a common Governmentwide data source." 68 Fed. Reg. 16,366 (Apr. 3, 2003). The Department of Defense intended for the CCR database to be the "primary Government repository for Contractor information required for the conduct of business with the Government." Id. at 16,369. A separate FAR provision, which was not incorporated into Aspen's contract with the government, details procedures for government payments using EFT information not listed in the CCR database. See FAR 52.232-34 (2013). The CCR database designated an Aspen Bank of America account as the proper place for payment. The government directed its first twelve payments under the contract to that account, but directed its next two payments, totaling $264,470.70, to an account at Commerzbank AG ("CZ account") that was not listed in the CCR database.

The CZ account was opened in 2008 by Aspen's Senior Vice President and Chief Operating Officer, Ben French, who was based in Germany and was responsible for overseeing day-to-day management of the Vilseck project. French opened the CZ account "with Aspen's knowledge," and "Aspen regularly transferred funds to the" CZ account. J.A. 262. Aspen used the CZ account to pay employee wages in Euros, to pay German- and U.S.-based subcontractors and vendors, and to receive payments for other non-government work that it performed in Germany. Even though the account was regularly used for Aspen business in Germany, the company's U.S.-based owners and officers, Gaye and Kent Toppert, lacked signatory authority and could not withdraw funds from the account. Still, Aspen often requested and promptly obtained copies of the CZ account statements from French.

In January 2015, citing concerns that Aspen "would not be able to meet [its] financial obligations ... related to [the] Vilseck Project," J.A. 762, French requested that the contracting officer send the monthly Vilseck payment "directly into [a] German Aspen Account at Commerzbank," J.A. 863. In an email to the contracting officer requesting the payment change, French (through his assistant) urged that paying to the CZ account would "make things much easier" for "tax purposes" and help "keep [Aspen's] records straight." Id. Even though Aspen's account as listed in the CCR database never changed, and the contract's express terms required that all payments be directed to that account, the government made two payments—in February and March 2015—to the CZ account.

In May 2015, Mrs. Toppert realized that the Vilseck project's two invoices had not been paid to the Bank of America account designated in the CCR database. She informed the government that its payments to the CZ account failed to comply with the contract's FAR clause and sent the government a request for payment to recover the funds. When the contracting officer contacted French, French maintained that the account was "fully legitimate" and that Mrs. Toppert was "apprised of the fact that it [was] being used to pay Vilseck [project] related vendor invoices." J.A. 289.

In March 2016, the government denied the request for payment. The government maintained that it was not improper to pay the CZ account because Aspen held French out as having "apparent authority to negotiate" on behalf of Aspen and "to sign contract modifications, submit invoices, submit requests for equitable adjustments[,] and submit delay cost proposals." J.A. 428. The government also noted that Mrs. Toppert "was aware of the CZBank account which was receiving and disbursing funds for Aspen," and concluded that "payments which would duplicate those already made to and received by Aspen Consulting LLC [could not] be issued." Id.

In July 2016, Aspen filed a certified claim with the contracting officer to recover $264,470.79 plus interest—the value of the allegedly misdirected payments. The contracting officer's final decision denied the claim because French had apparent authority to direct payment to the CZ account, and because the payments, despite not complying with the contract's payment terms, "were used to satisfy Aspen['s] ... debts and obligations." J.A. 60. Aspen appealed to the Board.

In October 2020, the Board issued its final written decision denying Aspen's appeal. The Board's decision noted that the relevant FAR provision stated, "the Contractor shall be responsible for providing the updated information to the CCR database." J.A. 3. The Board concluded that this implied that a contractor could change its EFT information before updating it in the CCR database. The Board determined also that French had done so, had at least apparent authority to do so, and that any failure to update the information in the CCR database by the time payment was made was Aspen's fault, not the government's. As a result, the Board found that the government did not breach the contract by failing to pay the account listed in the CCR database. The Board did not reach the question whether the government's payments to the CZ account could eliminate the government's liability if Aspen benefitted from the payments. Aspen appeals. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(10).

DISCUSSION

The Board's interpretation of a contract, including "[i]nterpretation and application of the FAR," Sec'y of Def. v. Northrop Grumman Corp. , 942 F.3d 1134, 1139 (Fed. Cir. 2019), is a legal question that we review de novo, 41 U.S.C. § 7107(b)(1) ; Pac. Gas & Elec. Co. v. United States , 838 F.3d 1341, 1350 (Fed. Cir. 2016) (citing S. Nuclear Operating Co. v. United States , 637 F.3d 1297, 1301 (Fed. Cir. 2011) ). The Board's factual findings are conclusive unless they are "fraudulent, arbitrary, or capricious," "so grossly erroneous as to necessarily imply bad faith," or "not supported by substantial evidence." § 7107(b)(2)(A)(C).

A

Aspen argues that the Board erred in denying its breach of contract appeal because the Board erroneously interpreted the contract's FAR clause; the government breached the contract by making payments to the CZ account; and the government's breach was material.

"A party breaches a contract when it is in material noncompliance with" its terms. Gilbert v. Dep't of Just. , 334 F.3d 1065, 1071 (Fed. Cir. 2003). "What was required by way of contract performance" is a question of law, and what the "allegedly breaching party ... did or did not do" in relation to that required performance is a question of fact. Id. at 1071–72 (citing Mass. Bay Transp. Auth. v. United States , 129 F.3d 1226, 1231 (Fed. Cir. 1997) ). Whether a party's "non-compliance with the terms of a contract is material, so as to constitute a breach, is a mixed question of fact and law." Id. at 1071.

To assess whether the government breached the contract, we start with the text of the FAR clause, the "plain and unambiguous" meaning of which controls. Arko Exec. Servs., Inc. v. United States , 553 F.3d 1375, 1379 (Fed. Cir. 2009) (quoting Hercules Inc. v. United States , 292 F.3d 1378, 1380–81 (Fed. Cir. 2002) ). The incorporated FAR clause states, in part, "[t]he Government shall make payment to the Contractor using the EFT information contained in the Central Contractor Registration (CCR) database." J.A. 233. The plain language unambiguously requires the government to pay Aspen using the EFT information contained in the CCR database. Its use of mandatory language, that payments "shall" be made "using the EFT information ... in the [CCR] database," indicates that the contract afforded the government no discretion to pay an account other than the one listed in the CCR database.

Other language in the payment clause addresses changes to a party's EFT information and states, "In the event that the EFT information changes, the Contractor shall be responsible for providing the updated information to the CCR database." Id....

To continue reading

Request your trial
5 cases
  • Ash v. Office of Pers. Mgmt.
    • United States
    • U.S. Court of Appeals — Federal Circuit
    • February 9, 2022
  • SLS Fed. Servs. v. United States
    • United States
    • U.S. Claims Court
    • January 3, 2023
    ...outset. We agree with SLS. We begin with the regulation's text, which, if unambiguous, controls. Aspen Consulting, LLC v. Sec'y of Army, 25 F.4th 1012, 1016 (Fed. Cir. 2022). DFARS 215.306 provides that, "[f]or acquisitions with an estimated value of $100 million or more, contracting office......
  • SLS Fed. Servs. v. United States
    • United States
    • U.S. Claims Court
    • January 3, 2023
    ... ... For ... instance, the Army Corps of Engineers found a way to evaluate ... contractors' prices ... controls. Aspen Consulting, LLC v. Sec'y of ... Army , 25 F.4th 1012, 1016 (Fed ... ...
  • SLS Fed. Servs. v. United States, 22-1215
    • United States
    • U.S. Claims Court
    • January 3, 2023
    ... ... For ... instance, the Army Corps of Engineers found a way to evaluate ... contractors' prices ... controls. Aspen Consulting, LLC v. Sec'y of ... Army , 25 F.4th 1012, 1016 (Fed ... ...
  • Request a trial to view additional results
1 firm's commentaries

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT