Asset Recovery Contracting, LLC v. Walsh Constr. Co. of Ill.
Decision Date | 01 November 2012 |
Docket Number | Docket No. 1–10–1226. |
Citation | 980 N.E.2d 708 |
Parties | ASSET RECOVERY CONTRACTING, LLC, Plaintiff–Appellant, v. WALSH CONSTRUCTION COMPANY OF ILLINOIS, Palmolive Tower Condominium, LLC, Palmolive Building Base, LLC, and National Electrical Benefit Fund, Defendants–Appellees. |
Court | United States Appellate Court of Illinois |
Eckert Seamans Cherin & Mellott, LLC, of Pittsburgh, Pennsylvania (Christopher R. Opalinski and Cornelius J. O'Brien, of counsel), and Conway & Mrowiec, of Chicago, (Timothy R. Conway, of counsel), for appellant.
Kubasiak, Fylstra, Thorpe & Rotunno, P.C.(Raymond A. Fylstra and Manuel J. Placencia, Jr., of counsel), and Law Offices of E. Bryan Dunigan(E. Bryan Dunigan, of counsel), both of Chicago, for appelleeWalsh Construction Company of Illinois.
¶ 2The instant case arose from a multimillion dollar redevelopment of the Palmolive Buildingat 919 North Michigan Avenue, Chicago, Illinois, to convert the commercial office building into residential and retail condominiums.DefendantWalsh Construction Company of Illinois (Walsh) was the general contractor for the "core and shell" phase of the project, which generally entails removal of the interior finishes and mechanical and electrical and plumbing systems in preparation for build-out work.Margaret Walsh was Walsh's senior project manager and was on the site daily beginning in March 2004.Jeff Pezza was Walsh's junior project manager and was on the jobsite daily.Walsh executed a contract with Palmolive Tower Condominiums, LLC(Palmolive), dated August 1, 2003.Pursuant to the terms of the prime contract, Palmolive's designated representatives were agents at Draper and Kramer Inc.(Draper and Kramer).
¶ 3 Walsh entered into various subcontracts for the project, including a subcontract agreement with Asset Recovery Contracting, LLC(ARC), to perform the interior demolition, dated September 12, 2003.After the events related to this construction project, ARC filed for bankruptcy and then filed the instant lawsuit against the above-captioned defendants.ARC was owned by Daniel Hoffman, who was the company's managing member; James Werner, who served as a project manager, supervisor and estimator; Allen Formeister, who was a project manager and the senior estimator; and Michael McCabe, who was ARC's accountant.Todd Westmoreland was also ARC's project coordinator and worked with Werner and Patricia Gruenke to prepare ARC's estimate for the project.Westmoreland was on the site regularly.Michael Gibbons was one of ARC's superintendents.
¶ 4 ARC decided to bid on the project in 2003.Westmoreland and Gruenke prepared ARC's debris quantity estimate for the project.On March 10, 2003, ARC submitted its initial bid for the project, which assumed a 12–month schedule for a base price of $2.9 million.Werner voiced concerns to Walsh about the various delays on a previous project on which the parties worked, at 175 West Jackson, but was assured that this project would be different.
¶ 5 In July 2003, ARC began work on the project, before ARC and Walsh signed the subcontract agreement.ARC did not sign the subcontract until March 19, 2004 and Walsh did not sign the agreement until May 5, 2004.
¶ 6 The subcontract required ARC to do the following:
"Furnish all labor, materials, equipment, insurance, taxes and supervision as required to fully fabricate, deliver F.O.B. Project and install all Demolition as more completely described in the exhibits attached hereto, in strict compliance with the plans and specifications and as directed by Contractor."
¶ 7 The project schedule was attached to the subcontract agreement as Exhibit I, which set forth the timing, sequence and duration of the work of the prime contract.Included were dates related to the timing and sequence of ARC's work under the subcontract.ARC's work was divided into three major areas of the building, to be performed concurrently: (1) the tower (floors 18 through 38); (2) the base (floors 1 through 17); and (3) three basements.The project schedule set forth that ARC's demolition work was to be completed in approximately 19 weeks.There were remaining isolated demolition activities scheduled for later in the project, but the bulk of the demolition work was scheduled to be completed within a four-month period.
¶ 8 ARC's work schedule was critical to the project, as a delay in ARC's demolition work would delay the overall schedule for the redevelopment of the building.The prime contract contained a schedule that was similar to the schedule of the ARC subcontract.Exhibit A of the prime contract contained a set of clarifications dated October 16, 2003, stating that "Walsh Construction has assumed unrestricted access to perform demolition and construction above and below existing tenants."The prime contract further provided that the contract schedule was
¶ 10 In August 2003, ARC began its work, starting with demolishing the three basement levels of the building.On September 12, 2003, ARC was informed by Walsh at a meeting that the Chicago fire department (CFD) had issued an order prohibiting demolition below any occupied floor and within two floors above any occupied floor in the building.Walsh requested, and ARC provided, cost estimates for the potential effects of this delay.On September 16, 2003, Werner wrote to Walsh outlining the costs associated with six possible scenarios which could be caused by the CFD order.Scenario six assumed the CFD order would remain in place and stated that the estimate of the cost to ARC would be $390,000.Although at this point in time the subcontract agreement had not yet been signed, ARC did not include this additional cost in the subcontract.
¶ 11 The owner attempted to obtain relief from the CFD's order for the next two months.However, while the owner did so, it allowed its tenants and sales staff, including its agent, Draper and Kramer, to remain in the building, thus effectively preventing any demolition under the prohibition of the CFD's order.Also, at the same time, the owner's funding did not come through as scheduled, which also delayed authorization to ARC to commence its work on all areas except a few selected areas of the basements.
¶ 12 Also, prior to the project, Elizabeth Arden, a tenant in the building, as well as other entities, initiated litigation against Palmolive over concerns about the impending construction.In settlement, Palmolive entered into an agreement (Arden Agreement) which was incorporated into Walsh's prime contract with Palmolive.The Arden Agreement limited the manner of demolition by prohibiting loud work or dropping debris above from above the fourth floor of the building during Elizabeth Arden's business hours.ARC's subcontract with Walsh incorporated the restrictions in the Arden Agreement within the prime contract.
¶ 13 On January 15, 2004, ARC wrote a letter to Walsh concerning terms of the proposed subcontract but did not ask for any increased costs.ARC proposed a change whereby Walsh could only "reasonably" change the sequence and pace of ARC's work.Walsh agreed to this modification and it was incorporated into the contract.ARC also proposed the following modification: "there would be no waiver of claims unless Walsh was prejudiced by ARC's failure to give notice."However, Walsh rejected this modification and it was not incorporated into the subcontract.ARC also suggested a provision obligating Walsh to pay for overtime, additional supervision, equipment, expedited material and other additional costs reasonably caused by or attributable to delay, hindrance or interference, but Walsh rejected this modification.ARC did not request an increase in the overall contract price in the subcontract.
¶ 14 On January 20, 2004, Walsh issued a revised project schedule dated January 19 to ARC and all other subcontractors.The revised project schedule increased the duration of ARC's bulk demolition work by an additional seven months through July 23, 2004, and divided ARC's work into more detailed piecemeal demolition in the major project areas.Walsh requested that all subcontractors review the revised schedule and report any problems or objections to Walsh by February 17, 2004.
¶ 15 After receipt of this revised schedule, ARC's project manager, James Werner, sent an e-mail to Walsh's project executive, Jack Keating, enclosing extended overhead cost projections for the revised schedule based on 14 additional weeks.At Keating's request, two weeks later, on February 10, 2004, Werner provided a modified version of the cost projection to one of Walsh's project managers, Jeff Pezza, which included an extended overhead cost projection of a total of $361,340, and an additional cost of $332,178 for carpet areas for the building.
¶ 16 The minutes of the Walsh February 17, 2004, subcontractor coordination meeting indicated that all dates in the revised schedule were "assumed ok."ARC attended this meeting and no objection is reflected in the minutes of the meeting.ARC and Walsh continued to negotiate the terms of the subcontract through March 18, 2004.
¶ 17 In late February or early March 2004, Margaret Walsh, another project manager for Walsh, returned to the project after an extended leave and, unaware of the delays, issued a letter to ARC objecting to its failure to complete all of its work in the tower, as required by the January 19 schedule revision.In response, Werner sent a letter to Ms. Walsh dated March 3, 2004, which detailed the delays due to the actions and inactions by the owner, the owner's engineers, and Walsh.Werner advised Ms. Walsh that ARC had submitted "change requests of $590,000 ( including any cost...
To continue reading
Request your trialUnlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Unlock full access with a free 7-day trial
Transform your legal research with vLex
-
Complete case access with no limitations or restrictions
-
AI-generated case summaries that instantly highlight key legal issues
-
Comprehensive legal database spanning 100+ countries and all 50 states
-
Advanced search capabilities with precise filtering and sorting options
-
Verified citations and treatment with CERT citator technology

Start Your 7-day Trial
-
Mulkanoor v. Am. Home Mortg. Corp (In re Mulkanoor)
...would vary or modify its terms." Asset Recovery Contr., LLC v. Walsh Constr. Co. , 2012 IL App (1st) 101226 at ¶ 67, 366 Ill.Dec. 615, 980 N.E.2d 708 (1st Dist. 2012). The documents Defendants are attempting to introduce, they argue, do not serve to vary or contradict the terms of the mortg......
-
C.O.A.L., Inc. v. Dana Hotel, LLC
...213 (1909) ); see also Asset Recovery Contracting, LLC v. Walsh Construction Co. of Illinois , 2012 IL App (1st) 101226, ¶ 62, 366 Ill.Dec. 615, 980 N.E.2d 708. "[T]he date on the contract is ordinarily the effective date, and where the contract is executed later, its contractual terms rela......
-
Motorola Solutions, Inc. v. Zurich Ins. Co.
...a basis in the evidence.” Asset Recovery Contracting, LLC v. Walsh Construction Co. of Illinois, 2012 IL App (1st) 101226, ¶ 74, 366 Ill.Dec. 615, 980 N.E.2d 708. ¶ 118 “As the trier of fact, the trial judge was in a superior position to judge the credibility of the witnesses and determine ......
-
Chandra v. Chandra
...400, 30 N.E.3d 670, and Asset Recovery Contracting, LLC v. Walsh Construction Co. of Illinois, 2012 IL App (1st) 101226, ¶ 74, 366 Ill.Dec. 615, 980 N.E.2d 708 (the interpretation of contracts is subject to de novo standard of review, but with the factual findings involved therein given def......
-
Section 12.16 Active Interference by Owner
...by a party as an exception to no-damages-for-delay clauses. See Asset Recovery Contracting, LLC v. Walsh Constr. Co. of Ill., 980 N.E.2d 708 (Ill. App. 2012) (“‘[A]ctive interference’ by a party is not one of the recognized exceptions to ‘no damages for delay’ clauses in Illinois.”). In 201......